CUY-North Royalton TLCI Sidewalk
CUY County · est $0.1M
Bid dateThursday, August 12—
CUY County · est $0.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount.
| Item | Quantity | R1Terrace Construction CO INC | R2Digioia-suburban Excavating LLC | R3Tri-mor CORP | R4Cook Paving & Construction CO INC | R5C A Agresta Construction CO | % of bid |
|---|---|---|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 5,280 SF | $5.80 | $7.00 | $8.00 | $6.25 | $10.00 | 35% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $11,000 | $16,250 | $10,000 | $16,500 | $16,000 | 13% |
| 452E10051 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS, | 150 SY | $62.55 | $71.50 | $72.00 | $80.00 | $80.00 | 11% |
| 659E00300 TOPSOIL | 152 CY | $56.90 | $60.75 | $40.00 | $55.00 | $50.00 | 10% |
| 624E10000 MOBILIZATION | 1 LS | $6,958 | $6,523 | $4,500 | $2,900 | $5,000 | 8% |
| 832E30000 EROSION CONTROL | 4,500 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1.00 |
| $1.00 |
| $1.00 |
| $1.00 |
| $1.00 |
| 5% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 1,364 SY | $2.60 | $1.75 | $2.00 | $4.50 | $4.00 | 4% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,118 | $4,050 | $3,800 | $4,500 | $5,000 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,250 | $525 | $4,500 | $5,000 | $5,000 | 3% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 150 SY | $10.90 | $8.75 | $16.00 | $45.00 | $15.00 | 2% |
| 608E53020 DETECTABLE WARNING | 16 SF | $75.40 | $17.75 | $35.00 | $35.00 | $25.00 | 1% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 18 CY | $51.25 | $89.75 | $80.00 | $140 | $60.00 | 1% |
| 203E10000 EXCAVATION | 85 CY | $10.60 | $34.00 | $50.00 | $70.00 | $75.00 | 1% |
| 659E35000 WATER | 3.7 MGAL | $210 | $67.56 | $250 | $50.00 | $20.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $663 | $1,090 | $2,500 | $1,500 | $2,501 | 1% |
| 204E10000 SUBGRADE COMPACTION | 150 SY | $2.65 | $1.50 | $2.00 | $10.00 | $2.00 | 0% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $385 | $575 | $750 | $950 | $1,000 | 0% |
| 659E20000 COMMERCIAL FERTILIZER | 0.18 TON | $1,875 | $975 | $1,500 | $1,500 | $500 | 0% |
| 203E20000 EMBANKMENT | 4 CY | $51.25 | $36.00 | $50.00 | $200 | $50.00 | 0% |
| 202E30001 WALK REMOVED, AS PER PLAN | 57 SF | $2.40 | $5.00 | $5.00 | $7.50 | $2.00 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 5,280 SF | $5.8 | $31k | 35% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $11,000 | $11k | 13% |
| 452E10051 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS, | 150 SY | $62.55 | $9k | 11% |
| 659E00300 TOPSOIL | 152 CY | $56.9 | $9k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $6,958 | $7k | 8% |
| 832E30000 EROSION CONTROL | 4,500 EACH | $1 | $5k | 5% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 1,364 SY | $2.6 | $4k | 4% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,118 | $3k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,250 | $2k | 3% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 150 SY | $10.9 | $2k | 2% |