BEL-SR 149-23.64
BEL County · est $0.9M
Bid dateThursday, March 10—
BEL County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 132 more items below.
| Item | Quantity | R1Wolf Creek Contracting Company LLC | R2Shelly & Sands INC | R3Ohio-west Virginia Excavating CO | % of bid |
|---|---|---|---|---|---|
| 452E16020 13" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 947 SY | $103 | $135 | $127 | 16% |
| 203E20000 EMBANKMENT | 1,227 CY | $40.45 | $24.00 | $38.00 | 8% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 13" THICK | 240 SY | $179 | $205 | $185 | 7% |
| 832E30000 EROSION CONTROL | 42,000 EACH | $1.00 | $1.00 | $1.00 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 137 CY | $300 |
| Item | Quantity | R1Wolf Creek Contracting Company LLC | R2Shelly & Sands INC | R3Ohio-west Virginia Excavating CO |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,587 | $12,275 | $12,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 157 FT | $9.79 | $25.00 | $30.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 24 FT | $9.79 | $15.00 | $75.00 |
| 202E38000 GUARDRAIL REMOVED | 363 FT | $6.47 | $2.00 | $8.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $245 | $200 | $500 |
| 202E75000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $268 |
| $265 |
| 7% |
| 304E20000 AGGREGATE BASE | 359 CY | $111 | $100 | $130 | 6% |
| 632E71388 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $34,272 | $31,000 | $38,000 | 5% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $5,031 | $2,700 | $2,000 | 5% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 3 EACH | $8,344 | $6,000 | $9,000 | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 865 FT | $28.00 | $20.00 | $20.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $24,146 | $36,000 | $40,000 | 4% |
| 659E00300 TOPSOIL | 361 CY | $66.32 | $27.00 | $35.00 | 4% |
| 253E02000 PAVEMENT REPAIR | 43 CY | $502 | $448 | $300 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,064 | $40,000 | $40,000 | 3% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 471 FT | $40.26 | $52.00 | $76.00 | 3% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 2 EACH | $9,464 | $7,000 | $11,000 | 3% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 2 EACH | $9,072 | $6,750 | $10,000 | 3% |
| 611E04400 12" CONDUIT, TYPE B | 453 FT | $38.78 | $70.00 | $75.00 | 3% |
| 202E23000 PAVEMENT REMOVED | 925 SY | $18.50 | $10.00 | $35.00 | 3% |
| 632E72130 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12 | 1 EACH | $16,296 | $15,000 | $18,000 | 3% |
| 64 FT |
| $9.79 |
| $2.50 |
| $17.00 |
| 203E10000 EXCAVATION | 942 CY | $16.38 | $29.00 | $30.00 |
| 204E10000 SUBGRADE COMPACTION | 1,910 SY | $3.45 | $5.00 | $4.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 287.5 FT | $36.40 | $24.80 | $35.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 1 EACH | $3,304 | $2,980 | $3,500 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,960 | $1,460 | $2,000 |
| 607E15000 FENCE, TYPE 47 | 64 FT | $115 | $67.50 | $125 |
| 609E14000 CURB, TYPE 2-A | 41 FT | $35.16 | $42.00 | $135 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (ONE WAY) | 6 EACH | $12.32 | $9.00 | $14.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (TWO WAY) | 6 EACH | $12.32 | $9.00 | $14.00 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 27 CY | $191 | $110 | $115 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 75 CY | $189 | $50.00 | $110 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $112 | $75.00 | $120 |
| 659E10000 SEEDING AND MULCHING | 3,180 SY | $1.29 | $1.15 | $1.25 |
| 659E14000 REPAIR SEEDING AND MULCHING | 159 SY | $1.29 | $1.15 | $1.25 |
| 659E20000 COMMERCIAL FERTILIZER | 0.43 TON | $896 | $700 | $900 |
| 659E31000 LIME | 0.66 ACRE | $89.61 | $80.00 | $90.00 |
| 659E35000 WATER | 18 MGAL | $1.12 | $1.00 | $1.00 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 71 SY | $2.80 | $2.50 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,680 | $2,000 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $9,290 | $12,000 | $10,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $2,240 | $9,900 | $13,000 |
| 602E20000 CONCRETE MASONRY | 11.7 CY | $324 | $1,350 | $2,000 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 656 FT | $11.51 | $20.00 | $28.00 |
| 605E31100 AGGREGATE DRAINS | 70 FT | $19.54 | $15.00 | $24.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 260 FT | $22.62 | $27.00 | $27.50 |
| 611E13200 30" CONDUIT, TYPE A, 706.02 | 40 FT | $152 | $275 | $325 |
| 611E22200 54" CONDUIT, TYPE A, 707.01 or 707.02 | 17 FT | $394 | $450 | $760 |
| 611E98150 CATCH BASIN, NO. 3 | 2 EACH | $2,228 | $4,000 | $4,800 |
| 611E98180 CATCH BASIN, NO. 3A | 4 EACH | $1,721 | $4,200 | $3,500 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $3,105 | $2,800 | $5,500 |
| 611E99711 PRECAST REINFORCED CONCRETE OUTLET, AS PER PLAN | 2 EACH | $324 | $300 | $300 |
| 407E10000 TACK COAT | 74 GAL | $2.24 | $2.00 | $12.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 57 GAL | $16.80 | $15.00 | $12.00 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 21 CY | $547 | $488 | $320 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (30 CY | $390 | $348 | $300 |
| 441E50401 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | — | $547 | $488 | $500 |
| 625E00450 CONNECTION, FUSED PULL APART | 2 EACH | $101 | $100 | $100 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 2 EACH | $101 | $100 | $100 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 14 EACH | $101 | $100 | $100 |
| 625E10490 LIGHT POLE, CONVENTIONAL AT25B32.5 | 1 EACH | $5,264 | $5,250 | $5,500 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 1 EACH | $2,464 | $1,750 | $2,500 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 486 FT | $3.92 | $3.50 | $4.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 385 FT | $1.79 | $2.00 | $2.00 |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 594 FT | $14.56 | $9.00 | $15.00 |
| 625E25900 CONDUIT, JACKED OR DRILLED, 3" | 142 FT | $48.16 | $65.00 | $50.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 2 EACH | $616 | $650 | $650 |
| 625E29000 TRENCH | 524 FT | $13.44 | $8.00 | $14.00 |
| 625E30700 PULL BOX, 725.08, 18" | 6 EACH | $1,036 | $1,200 | $1,100 |
| 625E30706 PULL BOX, 725.08, 24" | 1 EACH | $1,344 | $1,500 | $1,300 |
| 625E31510 PULL BOX REMOVED | 2 EACH | $168 | $250 | $185 |
| 625E32000 GROUND ROD | 2 EACH | $297 | $250 | $325 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $8,848 | $8,000 | $9,000 |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $2,016 | $5,000 | $2,000 |
| 625E75400 LIGHT POLE REMOVED | 1 EACH | $280 | $500 | $300 |
| 625E75500 LIGHT POLE FOUNDATION REMOVED | 1 EACH | $168 | $250 | $185 |
| 625E75504 LUMINAIRE REMOVED FOR STORAGE | 2 EACH | $44.80 | $100 | $45.00 |
| 625E75510 POWER SERVICE REMOVED | 1 EACH | $616 | $500 | $650 |
| 625E75800 DISCONNECT CIRCUIT | 2 EACH | $140 | $250 | $150 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (BEL-149-23.67) | 1 EACH | $2,576 | $500 | $2,500 |
| 621E00100 RPM | 33 EACH | $95.20 | $85.00 | $100 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 33 EACH | $1.07 | $12.00 | $20.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 115.7 FT | $15.68 | $12.00 | $15.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 140.1 FT | $16.80 | $14.50 | $32.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 35 FT | $19.60 | $16.80 | $20.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 31.8 FT | $22.40 | $28.25 | $32.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 73.9 FT | $27.44 | $33.00 | $40.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 52.4 FT | $35.84 | $44.00 | $75.00 |
| 630E08004 ONE WAY SUPPORT, NO. 3 POST | 29.6 FT | $20.72 | $13.00 | $20.00 |
| 630E08600 SIGN POST REFLECTOR | 6 EACH | $51.52 | $45.00 | $50.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 4 EACH | $560 | $525 | $650 |
| 630E79200 SIGN ATTACHMENT ASSEMBLY, MAST ARM | 2 EACH | $560 | $595 | $700 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 6 EACH | $168 | $160 | $175 |
| 630E80100 SIGN, FLAT SHEET | 61.75 SF | $28.00 | $20.50 | $23.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 8 EACH | $896 | $885 | $1,100 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 5 EACH | $28.00 | $10.00 | $12.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 23 EACH | $84.00 | $65.00 | $75.00 |
| 630E85600 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND REERECTIO | 5 EACH | $672 | $285 | $325 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 14 EACH | $28.00 | $15.00 | $18.00 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 8 EACH | $336 | $225 | $250 |
| 646E10010 EDGE LINE, 6" | 0.35 MILE | $11,169 | $9,972 | $12,000 |
| 646E10110 LANE LINE, 6" | 0.08 MILE | $6,832 | $6,100 | $7,000 |
| 646E10200 CENTER LINE | 0.15 MILE | $15,892 | $14,189 | $15,000 |
| 646E10300 CHANNELIZING LINE, 8" | 410 FT | $2.35 | $2.10 | $2.50 |
| 646E10310 CHANNELIZING LINE, 12" | 250 FT | $2.80 | $2.50 | $3.00 |
| 646E10400 STOP LINE | 97 FT | $14.00 | $12.50 | $15.00 |
| 646E20300 LANE ARROW | 8 EACH | $190 | $170 | $200 |
| 646E50000 REMOVAL OF PAVEMENT MARKING | 1 EACH | $258 | $230 | $7,500 |
| 625E25500 CONDUIT, 3", 725.04 | 95 FT | $40.32 | $45.00 | $45.00 |
| 625E25900 CONDUIT, JACKED OR DRILLED, 3" | 173 FT | $48.16 | $65.00 | $50.00 |
| 625E29000 TRENCH | 86 FT | $13.44 | $8.00 | $15.00 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $1,036 | $1,200 | $1,100 |
| 625E32000 GROUND ROD | 4 EACH | $297 | $250 | $300 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (BEL-149-23.67) | 1 EACH | $2,576 | $500 | $2,500 |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 8 EACH | $1,288 | $875 | $1,300 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 1 EACH | $1,944 | $1,250 | $2,000 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 9 EACH | $72.80 | $50.00 | $75.00 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 765 FT | $3.36 | $3.50 | $3.50 |
| 632E68200 POWER CABLE, 2 CONDUCTOR, NO. 6 AWG | 53 FT | $6.72 | $7.00 | $7.00 |
| 632E70001 POWER SERVICE, AS PER PLAN | 1 EACH | $1,848 | $2,500 | $2,000 |
| 632E70400 CONDUIT RISER, 2" DIAMETER | 1 EACH | $616 | $500 | $650 |
| 632E72100 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 2 | 1 EACH | $8,960 | $8,500 | $10,000 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 1 EACH | $2,576 | $2,250 | $2,500 |
| 633E65523 CABINET, TYPE 332L, AS PER PLAN | 1 EACH | $13,160 | $10,500 | $15,000 |
| 633E67100 CABINET FOUNDATION | 1 EACH | $3,248 | $1,500 | $3,500 |
| 633E67200 CONTROLLER WORK PAD | 1 EACH | $672 | $750 | $750 |
| 633E68511 COMMUNICATIONS, AS PER PLAN | 1 EACH | $2,352 | $2,500 | $2,500 |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 1 EACH | $7,504 | $6,000 | $8,500 |
| 633E99000 CONTROLLER ITEM, MISC.: TIMING AND COORDINATION | 2 EACH | $616 | $1,000 | $700 |
| 809E69123 ATC CONTROLLER, AS PER PLAN | 1 EACH | $1,318 | $750 | $1,500 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 150 HOUR | $61.60 | $70.00 | $65.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 50 FT | $2.24 | $2.00 | $2.50 |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 100 FT | $28.00 | $43.60 | $65.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,632 | $2,680 | $4,000 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,372 | $2,680 | $4,000 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,560 | $7,500 | $8,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (TWO WAY) | 12 EACH | $31.36 | $10.00 | $35.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 9 EACH | $40.32 | $15.00 | $45.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 12 EACH | $35.84 | $15.00 | $40.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 9 SNMT | $1,792 | $950 | $1,800 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.07 MILE | $9,694 | $8,655 | $10,000 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.19 MILE | $6,552 | $8,550 | $7,000 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.57 MILE | $3,080 | $2,750 | $3,200 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 47 FT | $13.44 | $12.00 | $13.00 |
| 616E10000 WATER | 10 MGAL | $5.60 | $35.00 | $10.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,511 | $7,199 | $20,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $13,440 | $19,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E16020 13" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 947 SY | $103.4 | $98k | 9% |
| 203E20000 EMBANKMENT | 1,227 CY | $40.45 | $50k | 5% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 13" THICK | 240 SY | $179.11 | $43k | 4% |
| 832E30000 EROSION CONTROL | 42,000 EACH | $1 | $42k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 137 CY | $300.16 | $41k | 4% |
| 304E20000 AGGREGATE BASE | 359 CY | $111.11 | $40k | 4% |
| 632E71388 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $34,272 | $34k | 3% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $5,031 | $30k | 3% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 3 EACH | $8,344 | $25k | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 865 FT | $28 | $24k | 2% |