POR-IR 76-20.05 Slide
POR County · est $3.2M
Bid dateThursday, January 26—
POR County · est $3.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 62 more items below.
| Item | Quantity | R1A P O'horo Company | R2Eclipse CO LLC | R3Rudzik Excavating INC | R4Shelly & Sands INC | R5Great Lakes Construction CO | % of bid |
|---|---|---|---|---|---|---|---|
| 204E30020 GRANULAR MATERIAL, TYPE C | 9,981 CY | $40.00 | $57.00 | $46.00 | $44.00 | $67.00 | 19% |
| 203E20000 EMBANKMENT | 40,476 CY | $7.00 | $6.50 | $7.15 | $15.50 | $14.00 | 13% |
| 203E10000 EXCAVATION | 37,843 CY | $7.00 | $7.00 | $5.00 | $9.00 | $11.00 | 12% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 2,365 SY | $85.00 | $68.00 | $96.00 | $59.00 | $92.50 | 9% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $150,000 | $64,091 | $65,000 | $34,000 | $80,000 | 7% |
| 203E35000 GRANULAR EMBANKMENT, (NO. 57 STONE) | 2,220 CY |
| Item | Quantity | R1A P O'horo Company | R2Eclipse CO LLC | R3Rudzik Excavating INC | R4Shelly & Sands INC | R5Great Lakes Construction CO |
|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 3 EACH | $500 | $905 | $800 | $400 | $780 |
| 202E23000 PAVEMENT REMOVED | 1,852 SY | $10.00 | $18.00 | $12.00 | $6.00 | $12.00 |
| 202E38000 GUARDRAIL REMOVED | 1,665 FT | $2.00 | $2.00 | $2.20 | $2.00 | $2.00 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 268 FT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $65.00 |
| $68.00 |
| $58.00 |
| $91.00 |
| $94.00 |
| 7% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $41,875 | $100,000 | $100,000 | $100,000 | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 417 CY | $230 | $230 | $234 | $219 | $245 | 4% |
| 832E30000 EROSION CONTROL | 83,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $65,399 | $78,000 | $43,000 | $110,000 | 3% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN (54" CM | 284 FT | $180 | $118 | $191 | $172 | $110 | 2% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 149 CY | $320 | $320 | $480 | $421 | $385 | 2% |
| 671E15040 EROSION CONTROL MAT, TYPE E | 13,700 SY | $3.20 | $2.60 | $3.60 | $3.00 | $2.40 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $36,349 | $25,267 | $25,994 | $17,000 | $25,000 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 1,650 FT | $21.00 | $17.60 | $19.40 | $19.00 | $17.60 | 2% |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (75 CY | $375 | $375 | $505 | $310 | $365 | 1% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 3,000 FT | $9.00 | $10.00 | $32.00 | $19.00 | $14.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $25,000 | $40,000 | $79,500 | $78,500 | $89,500 | 1% |
| 304E20000 AGGREGATE BASE | 333 CY | $75.00 | $88.00 | $100 | $86.00 | $105 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,360 FT | $9.00 | $39.00 | $55.00 | $11.00 | $24.00 | 1% |
| $44.00 |
| $27.00 |
| $44.00 |
| $43.00 |
| $60.00 |
| 202E75000 FENCE REMOVED | 269 FT | $3.00 | $2.00 | $2.20 | $2.00 | $2.00 |
| 202E75201 FENCE REMOVED FOR REUSE, AS PER PLAN | 50 FT | $4.00 | $38.40 | $42.25 | $41.00 | $38.40 |
| 202E98100 REMOVAL MISC.: GROUND MOUNTED MONITORING WELL | 5 EACH | $300 | $589 | $900 | $59.00 | $600 |
| 202E98300 REMOVAL MISC.: GEOWEB SLOPE PROTECTION REMOVED | 1,587 SY | $3.00 | $3.00 | $5.00 | $6.00 | $6.50 |
| 204E10000 SUBGRADE COMPACTION | 2,054 SY | $2.00 | $1.00 | $2.00 | $8.00 | $2.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $275 | $246 | $250 | $234 | $350 |
| 204E50000 GEOTEXTILE FABRIC, TYPE A | 16,306 SY | $1.00 | $4.00 | $2.05 | $0.75 | $5.00 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $2,150 | $2,860 | $3,150 | $3,000 | $2,860 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $850 | $480 | $530 | $515 | $480 |
| 607E15000 FENCE, TYPE 47 | 235 FT | $56.50 | $34.20 | $40.00 | $37.00 | $34.20 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 13 SY | $200 | $131 | $190 | $189 | $300 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 20 CY | $150 | $143 | $165 | $200 | $200 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $26.00 | $50.00 | $27.00 | $200 |
| 659E00300 TOPSOIL | 1,521 CY | $10.00 | $27.00 | $22.30 | $29.00 | $28.00 |
| 659E20000 COMMERCIAL FERTILIZER | 1.85 TON | $700 | $300 | $500 | $322 | $1,200 |
| 659E31000 LIME | 2.83 ACRE | $100 | $25.00 | $10.00 | $27.00 | $100 |
| 659E35000 WATER | 74 MGAL | $10.00 | $0.01 | $1.00 | $1.00 | $1.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $8,000 | $3,400 | $3,000 | $1,600 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,000 | $9,600 | $4,500 | $4,900 | $5,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $2,000 | $8,559 | $9,030 | $9,200 | $8,500 |
| 602E20000 CONCRETE MASONRY | 3.6 CY | $1,600 | $1,535 | $1,640 | $2,100 | $2,500 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 282 FT | $13.00 | $21.00 | $34.00 | $33.00 | $27.00 |
| 611E01500 6" CONDUIT, TYPE F, 707.41 (PERFORATED) | 2,881 FT | $6.00 | $13.00 | $29.00 | $4.00 | $15.00 |
| 611E20700 48" CONDUIT, TYPE A, 706.02 | 34 FT | $400 | $461 | $530 | $417 | $700 |
| 611E22200 54" CONDUIT, TYPE A, 707.01 | 16 FT | $500 | $456 | $630 | $368 | $850 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 7 EACH | $250 | $397 | $500 | $375 | $400 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 4 CY | $400 | $404 | $550 | $537 | $1,000 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 1,663 FT | $0.50 | $1.65 | $3.00 | $2.00 | $2.00 |
| 407E20000 NON-TRACKING TACK COAT | 325 GAL | $4.00 | $4.00 | $4.40 | $3.00 | $3.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 1,182 GAL | $5.00 | $5.00 | $4.40 | $4.00 | $2.00 |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 198 CY | $100 | $100 | $100 | $97.00 | $160 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 1,607 FT | $4.00 | $3.75 | $6.15 | $4.00 | $3.25 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (ONE-WAY) | 20 EACH | $9.00 | $12.00 | $13.20 | $13.00 | $12.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 30 FT | $17.00 | $22.95 | $20.35 | $20.00 | $17.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 4 SF | $35.00 | $47.25 | $24.75 | $24.00 | $35.00 |
| 642E00104 EDGE LINE, 6", TYPE 1, WHITE | 2.84 MILE | $4,710 | $6,359 | $5,181 | $5,000 | $4,710 |
| 621E00100 RPM | 63 EACH | $58.00 | $78.30 | $100 | $62.00 | $58.00 |
| 642E00204 LANE LINE, 6", TYPE 1 | 1.42 MILE | $1,055 | $1,424 | $1,165 | $1,132 | $1,055 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $75.00 | $67.00 | $80.00 | $91.00 | $75.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 180 FT | $3.50 | $4.73 | $3.85 | $2.00 | $3.50 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,250 | $2,620 | $3,225 | $2,800 | $2,240 |
| 614E12801 WORK ZONE RAISED PAVEMENT MARKER, AS PER PLAN | 652 EACH | $6.00 | $8.10 | $6.60 | $7.00 | $6.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $175 | $250 | $220 | $431 | $350 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 49 EACH | $13.00 | $17.55 | $14.30 | $12.00 | $13.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 49 EACH | $18.00 | $24.30 | $19.80 | $18.00 | $18.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $500 | $1,418 | $1,255 | $845 | $1,050 |
| 614E20010 WORK ZONE LANE LINE, CLASS I, 6" | 0.6 MILE | $3,210 | $4,334 | $3,531 | $3,445 | $3,210 |
| 614E20210 WORK ZONE LANE LINE, CLASS I, 6", 740.06, TYPE I | 0.05 MILE | $4,700 | $6,345 | $5,170 | $5,045 | $4,700 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.23 MILE | $9,200 | $12,420 | $10,120 | $9,900 | $9,200 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 2.6 MILE | $1,479 | $1,997 | $1,627 | $1,600 | $1,479 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 3,713 FT | $0.60 | $0.81 | $0.66 | $1.00 | $0.60 |
| 614E23410 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 740.06, | 372 FT | $3.50 | $4.73 | $3.85 | $4.00 | $3.50 |
| 616E10000 WATER | 360 MGAL | $8.00 | $3.00 | $2.00 | $36.00 | $50.00 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 10 SNMT | $500 | $1,148 | $1,035 | $912 | $850 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (POR-76-2009) | 1 LS | $10,000 | $5,653 | $1,250 | $16,000 | $40,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (POR-76-2033) | 1 LS | $20,000 | $24,084 | $6,050 | $12,300 | $60,000 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $1,800 | $683 | $1,700 | $3,200 | $3,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $16,000 | $8,118 | $10,000 | $28,000 | $35,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 204E30020 GRANULAR MATERIAL, TYPE C | 9,981 CY | $40 | $399k | 16% |
| 203E20000 EMBANKMENT | 40,476 CY | $7 | $283k | 12% |
| 203E10000 EXCAVATION | 37,843 CY | $7 | $265k | 11% |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 2,365 SY | $85 | $201k | 8% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $150,000 | $150k | 6% |
| 203E35000 GRANULAR EMBANKMENT, (NO. 57 STONE) | 2,220 CY | $65 | $144k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 417 CY | $230 | $96k | 4% |
| 832E30000 EROSION CONTROL | 83,000 EACH | $1 | $83k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $70k | 3% |