TRU-US 62-07.47
TRU County · est $2.4M
Bid dateThursday, January 26—
TRU County · est $2.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 125 more items below.
| Item | Quantity | R1A P O'horo Company | R2Kirila Contractors INC | R3Shelly & Sands INC | R4Eclipse CO LLC | R5S E T INC | % of bid |
|---|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,642 CY | $190 | $179 | $202 | $190 | $200 | 23% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 696 CY | $270 | $260 | $265 | $270 | $284 | 14% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (621 CY | $225 | $216 | $215 | $225 | $236 | 10% |
| 203E20000 EMBANKMENT | 7,384 CY | $15.00 | $13.00 | $20.00 | $14.00 | $34.00 | 8% |
| 304E20000 AGGREGATE BASE | 1,171 CY | $60.00 | $78.00 | $90.00 | $73.00 | $74.00 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS |
| Item | Quantity | R1A P O'horo Company | R2Kirila Contractors INC | R3Shelly & Sands INC | R4Eclipse CO LLC | R5S E T INC |
|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $300 | $750 | $300 | $430 | $458 |
| 202E32000 CURB REMOVED | 157 FT | $2.50 | $2.00 | $2.00 | $11.00 | $5.00 |
| 202E34900 PIPE REMOVED | 148 FT | $16.00 | $42.00 | $20.00 | $22.00 | $42.00 |
| 202E38000 GUARDRAIL REMOVED | 1,245 FT | $2.00 | $1.80 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $70,000 |
| $86,360 |
| $34,000 |
| $63,000 |
| $100,000 |
| 5% |
| 611E05900 15" CONDUIT, TYPE B | 983 FT | $65.00 | $74.00 | $85.00 | $91.00 | $104 | 5% |
| 203E10000 EXCAVATION | 4,095 CY | $12.00 | $19.00 | $20.00 | $10.00 | $22.00 | 4% |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 2,890 FT | $15.50 | $17.00 | $19.00 | $15.20 | $17.00 | 3% |
| 609E50000 4" CONCRETE TRAFFIC ISLAND | 827 SY | $52.00 | $64.00 | $70.00 | $52.00 | $47.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $63,842 | $100,000 | $54,720 | $115,000 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 6,856 FT | $5.00 | $14.00 | $8.00 | $34.00 | $32.00 | 2% |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 2,668 FT | $12.10 | $8.75 | $8.75 | $12.10 | $12.00 | 2% |
| 611E98150 CATCH BASIN, NO. 3 | 9 EACH | $3,500 | $5,500 | $4,000 | $5,285 | $5,218 | 2% |
| 625E10490 LIGHT POLE, CONVENTIONAL, DESIGN AT20B40 | 8 EACH | $3,900 | $3,800 | $3,800 | $3,900 | $4,334 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,509 | $20,243 | $12,000 | $29,000 | $20,000 | 2% |
| 202E23000 PAVEMENT REMOVED | 2,025 SY | $13.00 | $10.00 | $18.00 | $26.00 | $9.00 | 2% |
| 832E30000 EROSION CONTROL | 24,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 1,268 FT | $17.50 | $18.50 | $18.00 | $28.00 | $19.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $22,000 | $55,000 | $35,500 | $53,000 | $100,000 | 2% |
| $2.00 |
| $2.00 |
| $2.00 |
| 202E58000 MANHOLE REMOVED | 1 EACH | $300 | $700 | $1,300 | $509 | $772 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $150 | $400 | $230 | $509 | $582 |
| 202E75000 FENCE REMOVED | 491 FT | $5.00 | $2.00 | $5.00 | $2.00 | $2.00 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 2 EACH | $200 | $350 | $250 | $281 | $275 |
| 202E98200 REMOVAL MISC.: CONDUIT | 100 FT | $15.00 | $10.00 | $12.00 | $21.00 | $5.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 10 CY | $18.00 | $50.00 | $85.00 | $45.00 | $66.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 110 CY | $12.00 | $20.00 | $22.00 | $12.00 | $18.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 110 CY | $50.00 | $65.00 | $108 | $75.00 | $83.00 |
| 204E50000 GEOTEXTILE FABRIC | 329 SY | $0.75 | $1.00 | $0.60 | $1.00 | $2.00 |
| 209E60200 LINEAR GRADING | 54 STA | $60.00 | $30.00 | $150 | $1,304 | $21.00 |
| 607E23000 FENCE, TYPE CLT | 568 FT | $32.95 | $27.80 | $33.00 | $28.00 | $29.00 |
| 607E70000 FENCELINE SEEDING AND MULCHING | 568 FT | $0.75 | $1.20 | $0.80 | $1.00 | $1.00 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 3 EACH | $800 | $1,300 | $1,800 | $2,712 | $1,163 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION | 1 LS | $1,000 | $1,400 | $2,000 | $3,065 | $2,079 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $50.00 | $100 | $26.00 | $347 |
| 659E00300 TOPSOIL | 582 CY | $12.00 | $27.00 | $30.00 | $48.00 | $35.00 |
| 659E10000 SEEDING AND MULCHING | 5,238 SY | $2.00 | $2.45 | $0.75 | $2.00 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 262 SY | $1.00 | $0.35 | $0.80 | $2.00 | $0.37 |
| 659E15000 INTER-SEEDING | 262 SY | $1.00 | $0.10 | $0.80 | $0.01 | $0.11 |
| 659E20000 COMMERCIAL FERTILIZER | 1.18 TON | $750 | $495 | $840 | $306 | $520 |
| 659E31000 LIME | 1.07 ACRE | $100 | $30.00 | $160 | $26.00 | $32.00 |
| 659E35000 WATER | 30 MGAL | $1.00 | $0.80 | $1.00 | $0.26 | $1.00 |
| 659E40000 MOWING | 14 MSF | $15.00 | $1.00 | $5.00 | $20.00 | $11.00 |
| 670E00700 DITCH EROSION PROTECTION | 271 SY | $2.50 | $2.80 | $1.80 | $1.00 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $8,000 | $1,500 | $1,500 | $3,470 | $2,050 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,000 | $8,000 | $8,000 | $11,227 | $9,507 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $5,000 | $10,000 | $9,000 | $9,235 | $14,094 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 5 SY | $300 | $237 | $150 | $289 | $269 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 5 CY | $175 | $200 | $170 | $172 | $347 |
| 602E20000 CONCRETE MASONRY | 1 CY | $1,650 | $3,400 | $2,500 | $1,868 | $2,066 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS, WITH GEOTEXTILE FABRI | 1,682 FT | $9.50 | $14.00 | $18.00 | $17.00 | $20.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS, WITH GEOTEXTILE | 50 FT | $12.00 | $13.00 | $27.00 | $28.00 | $39.00 |
| 605E14000 6" BASE PIPE UNDERDRAINS, WITH GEOTEXTILE FABRIC | 2,968 FT | $7.00 | $13.00 | $15.00 | $17.00 | $15.00 |
| 605E31100 AGGREGATE DRAINS | 20 FT | $15.00 | $15.00 | $27.00 | $23.00 | $29.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 19 FT | $17.00 | $20.00 | $27.00 | $37.00 | $30.00 |
| 611E00900 6" CONDUIT, TYPE B | 100 FT | $12.00 | $30.00 | $15.00 | $20.00 | $26.00 |
| 611E01400 6" CONDUIT, TYPE E | 100 FT | $6.00 | $17.00 | $15.00 | $12.00 | $16.00 |
| 611E01500 6" CONDUIT, TYPE F | 150 FT | $6.00 | $17.00 | $15.00 | $14.00 | $16.00 |
| 611E05900 15" CONDUIT, TYPE B, 706.02, CLASS V | 66 FT | $65.00 | $107 | $99.00 | $110 | $175 |
| 611E07400 18" CONDUIT, TYPE B | 90 FT | $70.00 | $72.00 | $84.00 | $86.00 | $132 |
| 611E07400 18" CONDUIT, TYPE B, 706.02 | 20 FT | $160 | $300 | $270 | $168 | $381 |
| 611E08900 21" CONDUIT, TYPE B | 7 FT | $300 | $760 | $202 | $333 | $604 |
| 611E10400 24" CONDUIT, TYPE B | 31 FT | $110 | $207 | $159 | $96.00 | $277 |
| 611E10400 24" CONDUIT, TYPE B, 706.02 | 5 FT | $190 | $386 | $315 | $274 | $635 |
| 611E13400 30" CONDUIT, TYPE B | 30 FT | $175 | $172 | $180 | $114 | $217 |
| 611E16400 36" CONDUIT, TYPE B, 706.02 | 10 FT | $375 | $663 | $510 | $446 | $653 |
| 611E97400 CONDUIT, MISC.:TYPE B FOR DRAINAGE DISCHARGE CONTI | 100 FT | $14.00 | $32.00 | $30.00 | $44.00 | $26.00 |
| 611E97400 CONDUIT, MISC.:TYPE C FOR DRAINAGE DISCHARGE CONTI | 100 FT | $12.00 | $22.00 | $30.00 | $43.00 | $16.00 |
| 611E97400 CONDUIT, MISC.:TYPE E FOR DRAINAGE DISCHARGE CONTI | 100 FT | $9.00 | $22.00 | $30.00 | $34.00 | $16.00 |
| 611E97400 CONDUIT, MISC.:TYPE F FOR DRAINAGE DISCHARGE CONTI | 100 FT | $9.00 | $22.00 | $30.00 | $34.00 | $16.00 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $2,500 | $3,450 | $3,900 | $4,413 | $3,330 |
| 611E98410 CATCH BASIN, NO. 8 | 2 EACH | $3,600 | $3,550 | $6,000 | $7,196 | $4,398 |
| 611E99574 MANHOLE, NO. 3 | 3 EACH | $2,500 | $5,100 | $5,500 | $5,125 | $5,138 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $2,000 | $1,750 | $2,500 | $933 | $1,088 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 4 EACH | $250 | $350 | $400 | $556 | $448 |
| 611E99720 INSPECTION WELL | 2 EACH | $500 | $700 | $850 | $875 | $1,342 |
| 204E10000 SUBGRADE COMPACTION | 7,028 SY | $1.50 | $2.00 | $3.00 | $1.00 | $2.00 |
| 204E45000 PROOF ROLLING | 8 HOUR | $300 | $175 | $200 | $276 | $231 |
| 253E01000 PAVEMENT REPAIR | 13 SY | $500 | $80.00 | $615 | $900 | $945 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.25" DEPTH | 9,945 SY | $2.00 | $1.56 | $3.00 | $2.00 | $2.00 |
| 407E20000 NON-TRACKING TACK COAT | 2,490 GAL | $4.00 | $3.00 | $3.50 | $4.00 | $4.00 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 2,871 FT | $2.50 | $2.50 | $2.00 | $2.13 | $3.00 |
| 625E00450 CONNECTION, FUSED PULL APART | 20 EACH | $100 | $200 | $200 | $100 | $199 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 21 EACH | $100 | $200 | $200 | $100 | $167 |
| 625E10490 LIGHT POLE, CONVENTIONAL, DESIGN AT6B40 | 2 EACH | $3,600 | $3,250 | $3,250 | $3,600 | $3,912 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 10 EACH | $2,200 | $1,250 | $1,250 | $2,200 | $1,863 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 849 FT | $4.00 | $2.50 | $2.50 | $4.00 | $4.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,716 FT | $1.70 | $1.50 | $1.50 | $1.70 | $1.00 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 4" CONDUIT | 253 FT | $55.00 | $60.00 | $60.00 | $55.00 | $89.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 10 EACH | $450 | $450 | $450 | $450 | $734 |
| 625E29000 TRENCH | 2,510 FT | $8.00 | $6.00 | $6.00 | $8.00 | $8.00 |
| 625E30700 PULL BOX, 725.08, 18" | 5 EACH | $1,000 | $1,250 | $1,250 | $1,000 | $908 |
| 625E30706 PULL BOX, 725.08, 24" | 1 EACH | $1,300 | $1,500 | $1,500 | $1,300 | $1,410 |
| 625E32000 GROUND ROD | 10 EACH | $275 | $250 | $250 | $275 | $494 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $7,200 | $6,000 | $6,000 | $7,200 | $7,769 |
| 625E36011 UNDERGROUND WARNING/MARKING TAPE, AS PER PLAN | 2,510 FT | $0.40 | $1.00 | $1.00 | $0.41 | $0.50 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (TRU-62/BEDFORD R | 1 EACH | $2,100 | $500 | $500 | $2,100 | $2,625 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 17 EACH | $60.00 | $60.00 | $60.00 | $61.00 | $63.00 |
| 621E00100 RPM | 202 EACH | $34.00 | $42.50 | $35.00 | $41.00 | $45.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 86 EACH | $12.00 | $5.00 | $12.00 | $20.00 | $21.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST, TYPE S | 280 FT | $11.50 | $11.50 | $11.50 | $11.50 | $12.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 1,106 FT | $12.50 | $12.50 | $12.50 | $12.50 | $13.00 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 151.2 FT | $35.00 | $35.00 | $35.00 | $35.00 | $37.00 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 167.5 FT | $46.00 | $46.00 | $46.00 | $46.00 | $48.00 |
| 630E08600 SIGN POST REFLECTOR | 120 EACH | $45.00 | $45.00 | $45.00 | $45.00 | $47.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 14 EACH | $495 | $495 | $495 | $495 | $520 |
| 630E09001 BREAKAWAY STRUCTURAL BEAM CONNECTION, AS PER PLAN | 4 EACH | $595 | $595 | $595 | $595 | $625 |
| 630E80100 SIGN, FLAT SHEET | 695 SF | $14.00 | $14.00 | $14.00 | $14.00 | $15.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 428 SF | $21.00 | $21.00 | $21.00 | $21.00 | $22.00 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 18 EACH | $770 | $770 | $770 | $770 | $809 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 32 EACH | $10.00 | $10.00 | $10.00 | $10.00 | $11.00 |
| 630E85001 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE, AS PER | 2 EACH | $45.00 | $45.00 | $45.00 | $45.00 | $47.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $65.00 | $65.00 | $65.00 | $65.00 | $68.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 27 EACH | $15.00 | $15.00 | $15.00 | $15.00 | $16.00 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 2 EACH | $165 | $165 | $165 | $165 | $173 |
| 646E10010 EDGE LINE, 6" | 1.23 MILE | $2,400 | $3,000 | $2,500 | $3,240 | $3,150 |
| 646E10110 LANE LINE, 6" | 1.77 MILE | $2,970 | $2,395 | $3,000 | $4,010 | $2,515 |
| 646E10200 CENTER LINE | 0.02 MILE | $5,900 | $90,000 | $5,900 | $7,965 | $94,500 |
| 646E10310 CHANNELIZING LINE, 12" | 1,594 FT | $2.00 | $2.00 | $2.00 | $3.00 | $2.00 |
| 646E10400 STOP LINE | 55 FT | $15.00 | $11.00 | $15.00 | $21.00 | $12.00 |
| 646E10620 CHEVRON MARKING | 93 FT | $170 | $9.50 | $170 | $234 | $10.00 |
| 646E20300 LANE ARROW | 16 EACH | $185 | $170 | $185 | $255 | $179 |
| 646E20504 DOTTED LINE, 6" | 1,081 FT | $2.00 | $3.20 | $2.00 | $3.00 | $3.00 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 1 EACH | $5,000 | $2,500 | $2,600 | $1,587 | $4,283 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $75.00 | $55.00 | $90.00 | $66.00 | $63.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,250 | $3,200 | $2,400 | $2,307 | $2,373 |
| 614E12420 DETOUR SIGNING | 1 LS | $20,000 | $12,600 | $16,000 | $20,365 | $13,230 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 141 EACH | $13.00 | $10.00 | $7.00 | $18.00 | $16.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 141 EACH | $18.00 | $12.00 | $12.00 | $25.00 | $16.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 7 SNMT | $500 | $1,000 | $900 | $1,447 | $998 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 1.77 MILE | $900 | $1,000 | $900 | $1,240 | $1,276 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.02 MILE | $1,175 | $9,500 | $1,200 | $1,619 | $1,666 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 2.74 MILE | $970 | $1,000 | $1,000 | $1,336 | $1,375 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 1.23 MILE | $880 | $1,000 | $900 | $1,212 | $1,247 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 1,594 FT | $0.60 | $1.00 | $0.10 | $1.00 | $1.00 |
| 614E24202 WORK ZONE DOTTED LINE, CLASS I, 6", 642 PAINT | 3,960 FT | $0.50 | $0.75 | $0.50 | $1.00 | $1.00 |
| 614E24610 WORK ZONE DOTTED LINE, CLASS III, 4", 642 PAINT | 1,081 FT | $0.45 | $1.00 | $0.50 | $1.00 | $1.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 55 FT | $3.00 | $3.00 | $3.00 | $4.00 | $4.00 |
| 616E10000 WATER | 36 MGAL | $10.00 | $1.00 | $25.00 | $92.00 | $71.00 |
| 619E16000 FIELD OFFICE, TYPE A | 8 MNTH | $1,200 | $1,100 | $3,000 | $683 | $2,889 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $43,690 | $26,500 | $15,000 | $30,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,642 CY | $190 | $312k | 16% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 696 CY | $270 | $188k | 10% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (621 CY | $225 | $140k | 7% |
| 203E20000 EMBANKMENT | 7,384 CY | $15 | $111k | 6% |
| 304E20000 AGGREGATE BASE | 1,171 CY | $60 | $70k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $70k | 4% |
| 611E05900 15" CONDUIT, TYPE B | 983 FT | $65 | $64k | 3% |
| 203E10000 EXCAVATION | 4,095 CY | $12 | $49k | 3% |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 2,890 FT | $15.5 | $45k | 2% |
| 609E50000 4" CONCRETE TRAFFIC ISLAND | 827 SY | $52 | $43k | 2% |