DEF-US 24-04.73
DEF County · est $1.1M
Bid dateThursday, March 21—
DEF County · est $1.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 40 more items below.
| Item | Quantity | R1Miller Bros Const INC | R2Ruhlin Company | R3Miller Contracting Group INC | % of bid |
|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 15,694 CY | $12.00 | $19.00 | $19.75 | 24% |
| 690E98300 SPECIAL - PLATE PILES | 1,727 SY | $95.00 | $167 | $113 | 21% |
| 203E10000 EXCAVATION | 10,584 CY | $12.00 | $10.00 | $20.35 | 16% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $49,000 | $20,245 | $21,452 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $42,000 | $40,000 | $60,205 | 5% |
| 611E13600 30" CONDUIT, TYPE C | 303 FT | $110 | $125 | $96.00 | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,000 FT | $30.00 | $35.00 | $34.40 |
| Item | Quantity | R1Miller Bros Const INC | R2Ruhlin Company | R3Miller Contracting Group INC |
|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 47 SY | $60.00 | $60.00 | $41.00 |
| 202E32000 CURB REMOVED | 25 FT | $9.00 | $2.50 | $14.40 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 44 FT | $15.00 | $889 | $11.25 |
| 202E38000 GUARDRAIL REMOVED | 800 FT | $5.00 | $5.00 | $5.40 |
| 202E75000 FENCE REMOVED | 524 FT | $2.50 | $7.00 | $3.00 |
| 204E10000 SUBGRADE COMPACTION |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 609E23000 COMBINATION CURB AND GUTTER, TYPE 4 | 748 FT | $36.50 | $30.00 | $27.00 | 3% |
| 606E15101 GUARDRAIL, TYPE MGS WITH LONG POSTS, AS PER PLAN | 800 FT | $27.75 | $27.75 | $29.90 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $7,900 | $10,755 | 3% |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 607E15000 FENCE, TYPE 47 | 517 FT | $27.75 | $40.00 | $43.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $5,200 | $13,500 | 1% |
| 611E06700 15" CONDUIT, TYPE F, 707.05 TYPE C OR 707.21 | 80 FT | $110 | $100 | $104 | 1% |
| 651E10000 TOPSOIL STOCKPILED | 870 CY | $10.00 | $4.00 | $5.70 | 1% |
| 652E10000 PLACING STOCKPILED TOPSOIL | 870 CY | $10.00 | $6.25 | $7.30 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,930 | $19,000 | $8,538 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,220 | $7,707 | $7,773 | 1% |
| 659E10000 SEEDING AND MULCHING | 7,835 SY | $0.80 | $0.92 | $1.91 | 1% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1 CY | $4,900 | $3,267 | $4,310 | 1% |
| 291 SY |
| $3.50 |
| $4.00 |
| $1.60 |
| 209E10000 DITCH CLEANOUT | 47 FT | $6.00 | $25.00 | $9.80 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 1 EACH | $750 | $750 | $808 |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 2 EACH | $910 | $150 | $1,102 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $2,840 | $625 | $2,584 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,840 | $625 | $2,584 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 51 SY | $55.00 | $126 | $72.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $50.00 | $54.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 392 SY | $0.50 | $0.60 | $1.35 |
| 659E20000 COMMERCIAL FERTILIZER | 1.1 TON | $800 | $800 | $862 |
| 659E31000 LIME | 1.7 ACRE | $5.00 | $10.00 | $5.40 |
| 659E35000 WATER | 43 MGAL | $5.00 | $5.00 | $36.60 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $700 | $3,750 | $754 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,310 | $3,680 | $4,285 |
| 602E20000 CONCRETE MASONRY | 0.3 CY | $5,000 | $5,500 | $4,831 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 44 FT | $40.00 | $35.00 | $46.54 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $2,650 | $4,500 | $3,105 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,000 | $2,500 | $2,595 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $4,600 | $4,000 | $4,864 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $350 | $500 | $607 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 10 CY | $195 | $230 | $242 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 2" DEPTH | 2 SY | $100 | $3,400 | $244 |
| 304E20000 AGGREGATE BASE | 48 CY | $85.00 | $85.00 | $79.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE-WAY | 16 EACH | $11.00 | $11.00 | $12.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $100 | $95.00 | $103 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 1 EACH | $200 | $145 | $157 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 30 HOUR | $80.00 | $77.00 | $83.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,162 | $2,162 | $2,328 |
| 614E12600 REPLACEMENT DRUM | 10 EACH | $55.00 | $55.00 | $59.25 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 20 EACH | $12.68 | $12.68 | $13.75 |
| 614E13350 OBJECT MARKER, ONE WAY | 20 EACH | $21.62 | $21.62 | $23.30 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.46 MILE | $9,780 | $9,780 | $10,529 |
| 614E24402 WORK ZONE DOTTED LINE, CLASS I, 6", 740.06, TYPE I | 780 FT | $0.98 | $0.98 | $1.10 |
| 616E10000 WATER | 53 MGAL | $35.00 | $3.65 | $11.75 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,500 | $2,580 | $1,535 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E20000 EMBANKMENT | 15,694 CY | $12 | $188k | 22% |
| 690E98300 SPECIAL - PLATE PILES | 1,727 SY | $95 | $164k | 19% |
| 203E10000 EXCAVATION | 10,584 CY | $12 | $127k | 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $49,000 | $49k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $42,000 | $42k | 5% |
| 611E13600 30" CONDUIT, TYPE C | 303 FT | $110 | $33k | 4% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,000 FT | $30 | $30k | 3% |
| 609E23000 COMBINATION CURB AND GUTTER, TYPE 4 | 748 FT | $36.5 | $27k | 3% |
| 606E15101 GUARDRAIL, TYPE MGS WITH LONG POSTS, AS PER PLAN | 800 FT | $27.75 | $22k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $20k | 2% |