WYA-US 23-06.63
WYA County · est $0.3M
Bid dateThursday, July 25—
WYA County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Rietschlin Construction INC | R3D L Smith Concrete LLC | R4Shelly & Sands INC | R5Fenson Contracting LLC | R6R G Zachrich Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 304E20000 AGGREGATE BASE | 263 CY | $110 | $75.00 | $75.00 | $85.00 | $70.00 | $72.00 | 12% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, | 119 CY | $220 | $244 | $250 | $350 | $390 | $425 | 11% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $17,000 | $20,000 | $30,000 |
| Item | Quantity | R1Eagle Bridge CO | R2Rietschlin Construction INC | R3D L Smith Concrete LLC | R4Shelly & Sands INC | R5Fenson Contracting LLC | R6R G Zachrich Construction INC |
|---|---|---|---|---|---|---|---|
| 202E32600 GUTTER REMOVED | 15 FT | $35.00 | $30.00 | $100 | $36.00 | $22.00 | $16.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 16 FT | $15.00 | $25.00 | $20.00 | $34.00 | $35.00 | $24.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 74 FT | $25.00 | $50.00 | $25.00 | $15.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $32,500 |
| $30,000 |
| 8% |
| 204E30010 GRANULAR MATERIAL, TYPE B, 12" | 372 CY | $50.00 | $58.00 | $75.00 | $52.00 | $52.00 | $63.00 | 8% |
| 203E10000 EXCAVATION | 637 CY | $27.00 | $23.00 | $20.00 | $20.00 | $40.00 | $21.00 | 7% |
| 202E23000 PAVEMENT REMOVED | 1,600 SY | $10.00 | $14.00 | $20.00 | $12.00 | $16.00 | $13.75 | 7% |
| 204E13000 EXCAVATION OF SUBGRADE, 12" | 372 CY | $35.00 | $28.00 | $20.00 | $22.00 | $30.00 | $28.00 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $12,500 | $16,300 | $10,000 | $38,000 | $30,000 | $55,000 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $12,500 | $25,000 | $27,550 | $10,000 | $10,000 | $65,000 | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, | 36 CY | $315 | $504 | $550 | $500 | $550 | $575 | 5% |
| 203E20000 EMBANKMENT | 508 CY | $20.00 | $15.00 | $25.00 | $20.00 | $20.00 | $22.00 | 4% |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I, | 0.98 MILE | $8,500 | $13,200 | $13,000 | $11,000 | $13,500 | $12,000 | 3% |
| 607E15000 FENCE, TYPE 47 | 173 FT | $46.50 | $51.50 | $50.00 | $50.00 | $50.00 | $46.50 | 3% |
| 832E30000 EROSION CONTROL | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,500 | $4,500 | $1,500 | $8,000 | $8,500 | $20,000 | 3% |
| 618E40100 RUMBLE STRIPS, SHOULDER | 1,400 FT | $4.50 | $5.00 | $5.00 | $4.50 | $6.00 | $5.25 | 3% |
| 619E16000 FIELD OFFICE, TYPE A | 4 MNTH | $1,500 | $1,400 | $1,000 | $4,600 | $2,500 | $1,200 | 2% |
| 659E10000 SEEDING AND MULCHING | 2,647 SY | $2.00 | $2.00 | $4.00 | $1.90 | $2.25 | $1.90 | 2% |
| 202E75000 FENCE REMOVED | 2,493 FT | $2.00 | $4.00 | $4.00 | $3.50 | $3.40 | $3.50 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $121 | $88.00 | $90.00 | $90.00 | $125 | $95.00 | 2% |
| $35.00 |
| $40.00 |
| 204E10000 SUBGRADE COMPACTION | 1,114 SY | $3.00 | $2.50 | $1.50 | $2.00 | $3.00 | $2.50 |
| 204E45000 PROOF ROLLING | 1 HOUR | $150 | $350 | $120 | $250 | $125 | $310 |
| 204E50000 GEOTEXTILE FABRIC | 1,114 SY | $1.25 | $2.50 | $3.00 | $1.00 | $2.25 | $2.50 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $3,000 | $800 | $2,000 | $1,900 | $1,900 | $3,500 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $3,000 | $800 | $2,000 | $1,900 | $1,900 | $3,500 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $138 | $150 | $130 | $150 | $150 |
| 659E00300 TOPSOIL | 294 CY | $5.00 | $45.00 | $50.00 | $25.00 | $40.00 | $35.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 132 SY | $3.00 | $4.25 | $0.50 | $4.00 | $0.20 | $0.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.37 TON | $1,500 | $1,100 | $550 | $1,000 | $770 | $700 |
| 659E31000 LIME | 0.55 ACRE | $1.00 | $200 | $90.00 | $160 | $2.20 | $2.00 |
| 659E35000 WATER | 15 MGAL | $10.00 | $1.00 | $1.00 | $1.00 | $2.20 | $2.00 |
| 605E31100 AGGREGATE DRAINS | 90 FT | $15.00 | $16.00 | $25.00 | $20.00 | $20.00 | $20.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 1,047 FT | $1.10 | $4.00 | $2.00 | $3.80 | $3.00 | $3.20 |
| 407E20000 NON-TRACKING TACK COAT | 58 GAL | $15.00 | $3.25 | $2.75 | $3.25 | $3.55 | $1.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 131 FT | $24.00 | $32.00 | $30.00 | $31.00 | $17.00 | $29.00 |
| 630E08600 SIGN POST REFLECTOR | 5 EACH | $60.00 | $50.00 | $45.00 | $48.00 | $62.00 | $45.00 |
| 630E80100 SIGN, FLAT SHEET | 43 SF | $25.00 | $36.00 | $32.00 | $34.00 | $35.00 | $32.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 16 EACH | $11.00 | $16.50 | $15.00 | $16.00 | $25.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 19 EACH | $13.00 | $22.00 | $20.00 | $21.00 | $25.00 | $20.00 |
| 643E30000 REMOVAL OF PAVEMENT MARKING | 100 FT | $17.78 | $42.50 | $20.00 | $41.00 | $45.00 | $38.50 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $1,000 | $1,100 | $1,000 | $1,200 | $1,150 | $1,000 |
| 614E24402 WORK ZONE DOTTED LINE, CLASS I, 6", 740.06, TYPE I | 2,340 FT | $1.00 | $2.20 | $2.00 | $1.10 | $2.35 | $2.00 |
| 616E10000 WATER | 3 MGAL | $25.00 | $11.00 | $10.00 | $180 | $30.00 | $60.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $4,000 | $7,500 | $3,000 | $10,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 304E20000 AGGREGATE BASE | 263 CY | $110 | $29k | 10% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, | 119 CY | $220 | $26k | 9% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $20k | 7% |
| 204E30010 GRANULAR MATERIAL, TYPE B, 12" | 372 CY | $50 | $19k | 7% |
| 203E10000 EXCAVATION | 637 CY | $27 | $17k | 6% |
| 202E23000 PAVEMENT REMOVED | 1,600 SY | $10 | $16k | 6% |
| 204E13000 EXCAVATION OF SUBGRADE, 12" | 372 CY | $35 | $13k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $12,500 | $13k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $12,500 | $13k | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, | 36 CY | $315 | $11k | 4% |