MUS-SR 146-29.36
MUS County · est $0.8M
Bid dateThursday, October 31—
MUS County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 20 more items below.
| Item | Quantity | R1Cast & Baker Corporation | R2Tucson INC | R3J & J Bridge Company INC | R4V3 Construction Group LTD | R5George J Igel & CO INC | R6Shelly & Sands INC | R7Ohio-west Virginia Excavating CO | R8Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 22,814 CY | $14.75 | $18.15 | $21.00 | $22.26 | $25.00 | $23.00 | $27.00 | $28.50 | 51% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $24,650 | $32,000 | $33,877 | $40,000 | $45,000 |
| Item | Quantity | R1Cast & Baker Corporation | R2Tucson INC | R3J & J Bridge Company INC | R4V3 Construction Group LTD | R5George J Igel & CO INC | R6Shelly & Sands INC | R7Ohio-west Virginia Excavating CO | R8Alan Stone CO INC |
|---|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 2 EACH | $910 | $225 | $332 | $1,289 | $220 | $250 | $750 | $260 |
| 202E23000 PAVEMENT REMOVED | 81 SY | $13.00 | $11.25 | $5.00 | $27.84 | $6.00 | $15.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $25,000 |
| $40,000 |
| 13% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $64,000 | $26,000 | $40,000 | $15,763 | $30,100 | $50,000 | $30,000 | $60,000 | 10% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 5% |
| 671E15060 EROSION CONTROL MAT, TYPE G | 5,406 SY | $3.40 | $3.30 | $3.45 | $3.26 | $3.50 | $3.10 | $3.10 | $4.00 | 3% |
| 659E00540 SEEDING AND MULCHING, CLASS 3C | 8,586 SY | $2.05 | $2.40 | $0.90 | $2.00 | $4.00 | $1.90 | $2.50 | $1.00 | 3% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $16,500 | $8,465 | $2,000 | $6,831 | $20,000 | $32,000 | $3,000 | $45,000 | 2% |
| 611E10200 24" CONDUIT, TYPE A 707.01 METALLIC COATED (ALUMIN | 74 FT | $190 | $202 | $164 | $95.55 | $260 | $260 | $235 | $300 | 2% |
| 607E15000 FENCE, TYPE 47 | 450 FT | $24.00 | $23.75 | $15.00 | $23.12 | $22.00 | $22.00 | $25.00 | $22.00 | 2% |
| 203E20000 EMBANKMENT | 1,582 CY | $5.75 | $6.60 | $22.00 | $10.15 | $10.00 | $9.00 | $40.00 | $40.00 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $1,030 | $1,165 | $1,500 | $1,576 | $630 | $1,500 | $1,500 | $1,200 | 1% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 14 CY | $525 | $535 | $300 | $814 | $645 | $1,000 | $475 | $900 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,800 | $12,300 | $33,000 | $7,384 | $5,000 | $5,100 | $15,000 | $8,000 | 1% |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $6,500 | $2,595 | $1,000 | $1,051 | $3,500 | $3,000 | $1,000 | $7,000 | 1% |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $6,500 | $2,595 | $1,000 | $1,576 | $4,500 | $3,000 | $1,000 | $7,000 | 1% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 28 CY | $190 | $140 | $215 | $291 | $145 | $200 | $155 | $120 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $5,300 | $7,425 | $4,800 | $5,044 | $5,000 | $4,800 | $5,000 | $7,000 | 1% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $525 | $386 | $300 | $1,156 | $340 | $500 | $700 | $800 | 1% |
| 623E40520 RIGHT-OF-WAY MONUMENT, TYPE B | 6 EACH | $850 | $1,400 | $750 | $525 | $960 | $450 | $800 | $900 | 1% |
| 690E98400 SPECIAL - ROADWAY PRESERVATION | 1 LS | $5,000 | $16,400 | $5,000 | $5,254 | $1,000 | $47,432 | $35,000 | $25,000 | 1% |
| $35.00 |
| $28.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 48 FT | $38.00 | $13.00 | $15.00 | $29.96 | $16.00 | $13.00 | $60.00 | $30.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 2 CY | $301 | $475 | $400 | $411 | $500 | $550 | $1,000 | $1,100 |
| 659E20000 COMMERCIAL FERTILIZER | 1.16 TON | $1,360 | $1,785 | $800 | $1,314 | $916 | $1,250 | $1,300 | $1,000 |
| 659E31000 LIME | 1.77 ACRE | $165 | $141 | $150 | $158 | $156 | $150 | $150 | $200 |
| 659E35000 WATER | 47 MGAL | $1.10 | $1.00 | $1.00 | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.92 CY | $3,600 | $2,830 | $1,600 | $4,060 | $4,000 | $2,500 | $3,000 | $2,500 |
| 204E10000 SUBGRADE COMPACTION | 97 SY | $15.60 | $6.00 | $3.00 | $14.88 | $8.00 | $5.00 | $19.00 | $7.00 |
| 304E20000 AGGREGATE BASE | 15 CY | $150 | $200 | $150 | $205 | $130 | $150 | $175 | $250 |
| 407E20000 NON-TRACKING TACK COAT | 34 GAL | $11.00 | $4.35 | $5.00 | $4.10 | $10.00 | $3.50 | $5.00 | $5.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 54 GAL | $11.00 | $71.00 | $10.00 | $5.25 | $20.00 | $25.00 | $5.00 | $30.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 3 CY | $525 | $2,611 | $400 | $1,004 | $2,400 | $2,500 | $2,000 | $800 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (4 CY | $525 | $1,865 | $400 | $888 | $1,800 | $1,850 | $950 | $800 |
| 621E00100 RPM | 2 EACH | $1,630 | $1,625 | $1,500 | $1,576 | $1,500 | $1,500 | $1,500 | $1,500 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2 EACH | $60.00 | $49.00 | $25.00 | $131 | $25.00 | $50.00 | $120 | $20.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.01 MILE | $73,900 | $81,050 | $68,000 | $71,461 | $68,000 | $68,000 | $70,000 | $68,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.01 MILE | $73,900 | $81,050 | $68,000 | $71,461 | $68,000 | $68,000 | $70,000 | $68,000 |
| 616E10000 WATER | 1 MGAL | $500 | $11.00 | $10.00 | $263 | $58.00 | $100 | $5.00 | $1.00 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,200 | $9,000 | $3,200 | $9,965 | $15,000 | $15,000 | $35,000 | $18,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 22,814 CY | $14.75 | $337k | 49% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $84k | 12% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $64,000 | $64k | 9% |
| 832E30000 EROSION CONTROL | 30,000 EACH | $1 | $30k | 4% |
| 671E15060 EROSION CONTROL MAT, TYPE G | 5,406 SY | $3.4 | $18k | 3% |
| 659E00540 SEEDING AND MULCHING, CLASS 3C | 8,586 SY | $2.05 | $18k | 3% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $16,500 | $17k | 2% |
| 611E10200 24" CONDUIT, TYPE A 707.01 METALLIC COATED (ALUMIN | 74 FT | $190 | $14k | 2% |
| 607E15000 FENCE, TYPE 47 | 450 FT | $24 | $11k | 2% |
| 203E20000 EMBANKMENT | 1,582 CY | $5.75 | $9k | 1% |