ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 117 more items below.
| Item | Quantity | R1Great Lakes Demolition Company | R2Smith Paving & Excavating INC | R3Karvo Companies INC | R4Fechko Excavating LLC | R5Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,289 CY | $190 | $175 | $199 | $190 | $175 | 19% |
| 304E20000 AGGREGATE BASE | 1,679 CY | $70.00 | $62.00 | $69.00 | $64.00 | $73.50 | 9% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 456 CY | $210 | $225 | $256 | $235 | $225 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $97,000 | $100,000 | $47,250 | $96,000 | 7% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 326 CY | $230 | $248 | $277 | $240 | $248 | 6% |
| 832E30000 EROSION CONTROL |
| Item | Quantity | R1Great Lakes Demolition Company | R2Smith Paving & Excavating INC | R3Karvo Companies INC | R4Fechko Excavating LLC | R5Eclipse CO LLC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $38,000 | $40,000 | $1,750 | $6,500 |
| 202E38000 GUARDRAIL REMOVED | 113 FT | $2.00 | $2.00 | $2.00 | $2.00 | $3.00 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 1 EACH | $100 | $95.00 | $100 | $95.00 | $105 |
| 202E42050 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 69,000 EACH |
| $1.00 |
| $1.00 |
| $1.00 |
| $1.00 |
| $1.00 |
| 5% |
| 611E52304 19" X 30" CONDUIT, TYPE C, 706.04 | 456 FT | $140 | $136 | $190 | $117 | $162 | 5% |
| 203E10000 EXCAVATION | 4,027 CY | $15.00 | $22.50 | $24.50 | $38.00 | $31.00 | 5% |
| 611E16600 36" CONDUIT, TYPE C | 503 FT | $110 | $132 | $125 | $127 | $155 | 4% |
| 659E00300 TOPSOIL | 1,029 CY | $50.00 | $30.00 | $27.00 | $38.00 | $59.00 | 4% |
| 609E54001 6" CONCRETE TRAFFIC ISLAND, AS PER PLAN | 656 SY | $75.00 | $78.00 | $83.00 | $118 | $75.00 | 4% |
| 205E10550 CEMENT | 252 TON | $185 | $200 | $200 | $185 | $190 | 4% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.:12.25" TRU | 443 SY | $98.00 | $137 | $115 | $169 | $98.00 | 3% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 3,611 FT | $10.00 | $11.00 | $9.25 | $13.00 | $24.00 | 3% |
| 202E23000 PAVEMENT REMOVED | 7,074 SY | $5.00 | $8.00 | $11.00 | $10.50 | $16.00 | 3% |
| 615E10001 ROADS FOR MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $35,000 | $46,000 | $50,000 | $25,000 | $85,000 | 3% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 1,791 FT | $18.00 | $22.25 | $29.00 | $33.00 | $18.00 | 3% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 66 CF | $465 | $519 | $500 | $1,200 | $481 | 2% |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 2,448 FT | $12.00 | $3.00 | $14.00 | $29.00 | $25.00 | 2% |
| 625E10490 LIGHT POLE, CONVENTIONAL (AT08B40) | 7 EACH | $3,900 | $3,650 | $3,000 | $3,100 | $3,700 | 2% |
| 1 EACH |
| $100 |
| $145 |
| $100 |
| $145 |
| $158 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 2 EACH | $100 | $75.00 | $100 | $75.00 | $79.00 |
| 202E58100 CATCH BASIN REMOVED | 9 EACH | $450 | $550 | $195 | $850 | $565 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 15" | 20 FT | $50.00 | $50.00 | $33.00 | $29.00 | $98.00 |
| 202E98100 REMOVAL MISC.: CONCRETE BIN BLOCKS | 12 EACH | $100 | $50.00 | $38.00 | $260 | $110 |
| 203E20000 EMBANKMENT | 1,672 CY | $12.00 | $19.00 | $20.00 | $11.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 783 SY | $2.00 | $2.00 | $1.90 | $4.00 | $1.00 |
| 204E45000 PROOF ROLLING | 5 HOUR | $200 | $100 | $255 | $420 | $979 |
| 206E11000 CURING COAT | 8,320 SY | $1.60 | $1.15 | $1.15 | $1.30 | $1.40 |
| 206E15020 CEMENT STABILIZED SUBGRADE, 14 INCHES DEEP | 8,320 SY | $3.15 | $3.65 | $3.20 | $4.85 | $5.00 |
| 209E15000 RESHAPING UNDER GUARDRAIL | 3 STA | $55.00 | $50.00 | $45.00 | $50.00 | $150 |
| 606E13000 GUARDRAIL, TYPE 5 | 50 FT | $16.00 | $25.60 | $16.00 | $25.60 | $26.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 175 FT | $18.00 | $26.40 | $18.00 | $26.40 | $29.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 1 EACH | $2,300 | $2,720 | $2,300 | $2,720 | $2,984 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,150 | $1,440 | $1,150 | $1,440 | $1,639 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 2 EACH | $1,100 | $1,250 | $1,100 | $1,250 | $1,450 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 2 EACH | $11.00 | $14.50 | $11.00 | $14.50 | $14.00 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $3,000 | $3,000 | $2,980 | $4,000 | $3,940 |
| 690E12060 SPECIAL - PAVEMENT OVERLAY FABRIC COMPOSITE | 179 SY | $54.00 | $58.00 | $5.00 | $53.75 | $40.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $200 | $340 | $145 | $340 | $163 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 9 SY | $120 | $150 | $195 | $84.00 | $201 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 77 SY | $60.00 | $100 | $110 | $86.00 | $140 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 3 CY | $350 | $215 | $585 | $125 | $300 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $200 | $300 | $150 | $210 |
| 659E10000 SEEDING AND MULCHING | 8,209 SY | $2.00 | $1.55 | $0.89 | $2.00 | $2.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 411 SY | $1.00 | $2.50 | $3.00 | $2.00 | $1.00 |
| 659E15000 INTER-SEEDING | 411 SY | $1.00 | $2.50 | $0.10 | $2.00 | $0.11 |
| 659E20000 COMMERCIAL FERTILIZER | 1.15 TON | $1,000 | $1,500 | $1,500 | $1,650 | $736 |
| 659E31000 LIME | 1.7 ACRE | $800 | $600 | $0.10 | $200 | $92.00 |
| 659E35000 WATER | 45 MGAL | $1.00 | $10.00 | $0.10 | $50.00 | $1.00 |
| 659E40000 MOWING | 19 MSF | $100 | $50.00 | $0.10 | $36.00 | $58.00 |
| 670E00700 DITCH EROSION PROTECTION | 1,061 SY | $3.00 | $2.50 | $2.50 | $4.00 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,500 | $1,100 | $3,475 | $3,475 | $3,652 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,500 | $3,300 | $6,720 | $14,280 | $10,719 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $12,500 | $12,600 | $7,500 | $12,820 | $13,467 |
| 602E20000 CONCRETE MASONRY | 1.03 CY | $1,800 | $4,000 | $3,100 | $2,000 | $2,436 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 708 FT | $10.00 | $11.00 | $12.00 | $23.00 | $24.00 |
| 605E13301 6" UNCLASSIFIED PIPE UNDERDRAINS, AS PER PLAN | 100 FT | $12.00 | $11.00 | $15.00 | $23.00 | $38.00 |
| 605E31100 AGGREGATE DRAINS | 50 FT | $20.00 | $9.00 | $25.00 | $25.00 | $19.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 186 FT | $25.00 | $10.50 | $19.00 | $10.00 | $45.00 |
| 611E01501 6" CONDUIT, TYPE F, AS PER PLAN | 100 FT | $25.00 | $10.50 | $18.00 | $15.00 | $38.00 |
| 611E04400 12" CONDUIT, TYPE B, 706.02 | 91 FT | $70.00 | $87.70 | $108 | $73.00 | $122 |
| 611E04900 12" CONDUIT, TYPE D | 74 FT | $40.00 | $41.80 | $70.00 | $35.00 | $92.00 |
| 611E06100 15" CONDUIT, TYPE C | 438 FT | $40.00 | $52.50 | $80.00 | $70.00 | $99.00 |
| 611E07600 18" CONDUIT, TYPE C | 84 FT | $55.00 | $70.20 | $75.00 | $73.00 | $109 |
| 611E10400 24" CONDUIT, TYPE B | 67 FT | $75.00 | $121 | $150 | $115 | $141 |
| 611E10600 24" CONDUIT, TYPE C | 190 FT | $90.00 | $91.70 | $115 | $99.00 | $121 |
| 611E13400 30" CONDUIT, TYPE B | 153 FT | $110 | $166 | $190 | $158 | $156 |
| 611E13600 30" CONDUIT, TYPE C | 79 FT | $100 | $110 | $140 | $121 | $140 |
| 611E98150 CATCH BASIN, NO. 3 | 1 EACH | $2,850 | $4,950 | $3,400 | $3,500 | $5,462 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $2,750 | $3,325 | $2,400 | $2,500 | $4,876 |
| 611E98410 CATCH BASIN, NO. 8 | 3 EACH | $4,850 | $6,250 | $3,500 | $3,100 | $8,783 |
| 611E98434 CATCH BASIN, NO. 8A | 1 EACH | $8,850 | $10,400 | $6,000 | $6,600 | $10,383 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,850 | $2,675 | $1,700 | $2,000 | $4,059 |
| 611E98510 CATCH BASIN, NO. 2-3 | 4 EACH | $2,800 | $4,725 | $2,400 | $3,500 | $4,839 |
| 611E98540 CATCH BASIN, NO. 2-4 | 1 EACH | $3,000 | $4,175 | $2,400 | $3,600 | $4,938 |
| 611E99574 MANHOLE, NO. 3 | 3 EACH | $5,650 | $7,650 | $4,500 | $5,800 | $7,466 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $500 | $400 | $465 | $300 | $532 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3.25" | 1,866 SY | $6.00 | $7.00 | $5.50 | $6.00 | $4.20 |
| 407E10000 TACK COAT | 1,190 GAL | $3.00 | $2.60 | $2.75 | $3.25 | $3.00 |
| 442E22120 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 12 CY | $300 | $450 | $480 | $400 | $450 |
| 442E22320 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 14 CY | $300 | $400 | $510 | $400 | $400 |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 80 FT | $18.00 | $26.00 | $32.00 | $55.00 | $18.00 |
| 609E14000 CURB, TYPE 2-A | 365 FT | $10.00 | $13.25 | $13.25 | $14.00 | $10.00 |
| 609E18001 COMBINATION CURB AND GUTTER, TYPE 3, AS PER PLAN | 443 FT | $18.00 | $30.50 | $21.00 | $33.00 | $18.00 |
| 609E26000 CURB, TYPE 6 | 1,537 FT | $11.00 | $15.50 | $21.00 | $23.00 | $11.00 |
| 611E00401 4" CONDUIT, TYPE E, AS PER PLAN | 50 FT | $2.00 | $12.00 | $5.00 | $15.00 | $14.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $500 | $400 | $350 | $650 | $381 |
| 625E00450 CONNECTION, FUSED PULL APART | 16 EACH | $140 | $110 | $120 | $145 | $111 |
| 625E00481 CONNECTION, UNFUSED PERMANENT, AS PER PLAN | 12 EACH | $120 | $110 | $120 | $145 | $111 |
| 625E10490 LIGHT POLE, CONVENTIONAL (AT12B40) | 1 EACH | $4,100 | $3,850 | $3,500 | $3,100 | $3,900 |
| 625E14100 LIGHT POLE FOUNDATION, 24" X 8' DEEP | 8 EACH | $1,600 | $1,900 | $1,250 | $1,800 | $1,910 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 4,539 FT | $3.50 | $3.80 | $2.50 | $4.05 | $4.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,164 FT | $2.00 | $2.00 | $1.25 | $2.10 | $2.00 |
| 625E25502 CONDUIT, 3", 725.05 | 952 FT | $6.00 | $10.50 | $10.00 | $9.50 | $11.00 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 3" | 119 FT | $55.00 | $47.00 | $65.00 | $105 | $50.00 |
| 625E26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), TYPE I | 8 EACH | $450 | $425 | $500 | $700 | $450 |
| 625E29002 TRENCH, 24" DEEP | 952 FT | $12.00 | $13.00 | $12.00 | $14.00 | $13.00 |
| 625E30707 PULL BOX, 725.08, 24", AS PER PLAN | 5 EACH | $1,600 | $1,400 | $2,000 | $1,250 | $1,400 |
| 625E32000 GROUND ROD | 8 EACH | $300 | $265 | $200 | $350 | $270 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $8,000 | $8,450 | $10,000 | $6,800 | $8,500 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 952 FT | $2.00 | $3.40 | $2.00 | $3.50 | $4.00 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL, LIGHTING CONTROL | 1 EACH | $3,200 | $3,500 | $500 | $2,200 | $3,600 |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 1 EACH | $500 | $536 | $1,250 | $900 | $540 |
| 621E00100 RPM | 166 EACH | $52.00 | $53.50 | $51.00 | $53.50 | $39.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 320.7 FT | $10.00 | $10.00 | $10.00 | $12.00 | $16.00 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 59.6 FT | $10.00 | $10.00 | $10.00 | $13.00 | $20.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 116.4 FT | $10.00 | $10.00 | $10.00 | $14.00 | $20.00 |
| 630E08600 SIGN POST REFLECTOR | 4 EACH | $25.00 | $25.00 | $25.00 | $65.00 | $47.00 |
| 630E80100 SIGN, FLAT SHEET | 333.4 SF | $16.00 | $15.50 | $15.50 | $16.00 | $20.50 |
| 630E85000 REMOVAL OF GROUND MOUNTED SIGN AND STORAGE | 41 EACH | $20.00 | $20.00 | $20.00 | $55.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 32 EACH | $15.00 | $15.00 | $15.00 | $55.00 | $16.00 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 1 EACH | $5,000 | $3,000 | $3,000 | $2,800 | $2,630 |
| 644E00100 EDGE LINE, 4", (WHITE) | 0.83 MILE | $4,000 | $4,000 | $4,000 | $3,200 | $4,834 |
| 644E00100 EDGE LINE, 4", (YELLOW) | 0.53 MILE | $4,000 | $4,000 | $4,000 | $3,200 | $4,834 |
| 644E00300 CENTER LINE | 0.41 MILE | $5,000 | $5,000 | $5,000 | $8,500 | $5,570 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 106 FT | $6.00 | $6.00 | $6.00 | $8.00 | $8.00 |
| 644E01500 DOTTED LINE, 4" | 176 FT | $1.00 | $0.70 | $0.70 | $3.00 | $3.00 |
| 644E20800 YIELD LINE | 71 FT | $15.00 | $15.00 | $15.00 | $15.00 | $7.00 |
| 204E50000 GEOTEXTILE FABRIC | 416 SY | $3.00 | $4.15 | $4.02 | $4.00 | $3.00 |
| 657E10001 RIPRAP FOR TREE PROTECTION, AS PER PLAN | 416 SY | $45.00 | $32.00 | $28.68 | $40.00 | $37.00 |
| 661E19000 DECIDUOUS SHRUB, 12" HEIGHT, RHUS AROMATICA, 3 GAL | 20 EACH | $120 | $150 | $95.49 | $180 | $126 |
| 661E50040 EVERGREEN TREE, 2' HEIGHT, PINUS MUGO, 5 GAL | 5 EACH | $300 | $200 | $130 | $400 | $315 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $180 | $95.00 | $125 | $75.00 | $68.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $8,500 | $7,200 | $7,200 | $25,200 | $11,750 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $400 | $400 | $280 | $240 | $410 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $900 | $800 | $800 | $900 | $631 |
| 614E40050 BUSINESS ENTRANCE SIGN | 2 EACH | $200 | $100 | $100 | $400 | $420 |
| 616E10000 WATER | 15 MGAL | $1.00 | $10.00 | $100 | $50.00 | $57.00 |
| 202E98200 REMOVAL MISC.:POLYMER MODIFIED ASPHALT EXPANSION J | 80 FT | $30.00 | $55.46 | $75.00 | $160 | $49.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,000 | $21,500 | $20,000 | $19,500 | $35,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $12,000 | $11,000 | $45,000 | $24,000 | $45,000 |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $1,500 | $1,000 | $2,700 | $1,850 | $683 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $38,500 | $29,840 | $29,750 | $24,268 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 1,289 CY | $190 | $245k | 13% |
| 304E20000 AGGREGATE BASE | 1,679 CY | $70 | $118k | 6% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 456 CY | $210 | $96k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $84,000 | $84k | 4% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 326 CY | $230 | $75k | 4% |
| 832E30000 EROSION CONTROL | 69,000 EACH | $1 | $69k | 4% |
| 611E52304 19" X 30" CONDUIT, TYPE C, 706.04 | 456 FT | $140 | $64k | 3% |
| 203E10000 EXCAVATION | 4,027 CY | $15 | $60k | 3% |
| 611E16600 36" CONDUIT, TYPE C | 503 FT | $110 | $55k | 3% |
| 659E00300 TOPSOIL | 1,029 CY | $50 | $51k | 3% |