ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Shelly Company | R2Shelly & Sands INC | R3S.t.a.r.t., LLC | R4Rmi Cement LLC | R5Stanley Miller Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 26,928 SF | $5.70 | $5.50 | $8.26 | $5.55 | $7.40 | 24% |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 1,191 SY | $78.00 | $99.00 | $98.92 | $70.50 | $92.00 | 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $55,000 | $52,000 | $82,250 | $32,750 | $34,000 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $20,000 | $29,200 | $67,540 | $52,000 | 6% |
| 608E52000 CURB RAMP | 1,839 SF | $21.00 | $32.00 | $33.03 | $16.00 | $29.70 | 6% |
| 202E23000 PAVEMENT REMOVED | 1,096 SY | $35.00 |
| Item | Quantity | R1Shelly Company | R2Shelly & Sands INC | R3S.t.a.r.t., LLC | R4Rmi Cement LLC | R5Stanley Miller Construction Company |
|---|---|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 69 FT | $15.00 | $54.00 | $36.60 | $16.50 | $18.50 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $650 | $655 | $714 | $715 | $1,270 |
| 202E98100 REMOVAL MISC.:EXISTING METAL POLE AND FOUNDATION | 1 EACH | $1,750 | $420 | $839 | $1,925 | $3,277 |
| 203E20000 EMBANKMENT | 17 CY | $70.00 | $50.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $20.00 |
| $11.26 |
| $24.75 |
| $16.80 |
| 6% |
| 202E30000 WALK REMOVED | 8,399 SF | $4.50 | $3.00 | $1.40 | $2.75 | $1.49 | 6% |
| 203E10000 EXCAVATION | 592 CY | $40.00 | $82.00 | $32.84 | $18.70 | $70.00 | 4% |
| 630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA | 2 EACH | $11,300 | $7,560 | $8,300 | $10,780 | $27,656 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $5,400 | $11,233 | $11,000 | $8,750 | 3% |
| 608E13000 6" CONCRETE WALK | 2,282 SF | $8.30 | $10.00 | $13.46 | $8.40 | $12.90 | 3% |
| 832E30000 EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 659E00300 TOPSOIL | 109 CY | $128 | $125 | $57.67 | $150 | $55.00 | 2% |
| 452E12050 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 100 SY | $116 | $141 | $124 | $89.70 | $170 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $3,835 | $11,600 | $71,737 | $15,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $7,000 | $9,880 | $3,300 | $36,000 | 2% |
| 611E99574 MANHOLE, NO. 3 | 3 EACH | $3,200 | $4,400 | $5,092 | $3,520 | $4,600 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 5 MNTH | $1,900 | $2,900 | $3,000 | $22,600 | $2,000 | 1% |
| 611E98470 CATCH BASIN, NO. 2-2B | 3 EACH | $2,325 | $2,575 | $1,846 | $2,558 | $3,900 | 1% |
| 644E00620 CROSSWALK LINE, 12" | 1,062 FT | $5.75 | $4.70 | $6.00 | $6.32 | $15.62 | 1% |
| $89.94 |
| $46.20 |
| $98.00 |
| 204E10000 SUBGRADE COMPACTION | 1,291 SY | $3.00 | $2.40 | $2.54 | $4.23 | $1.00 |
| 638E10500 FIRE HYDRANT REMOVED AND RESET | 2 EACH | $2,600 | $1,340 | $3,917 | $2,860 | $5,500 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 7 EACH | $40.00 | $226 | $495 | $950 | $350 |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 14 EACH | $40.00 | $234 | $432 | $400 | $400 |
| 638E98000 WATER WORK, MISC.:WATER MANHOLE ADJUTED TO GRADE | 1 EACH | $250 | $715 | $727 | $1,500 | $1,500 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET, AS PER PLAN | 16 EACH | $285 | $307 | $148 | $300 | $425 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 973 SY | $2.00 | $5.70 | $3.02 | $5.50 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 49 SY | $4.00 | $1.00 | $2.49 | $1.10 | $2.00 |
| 659E15000 INTER-SEEDING | 49 SY | $0.50 | $1.00 | $2.36 | $0.01 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $1,500 | $938 | $1,324 | $1,650 | $800 |
| 659E31000 LIME | 0.21 ACRE | $0.52 | $168 | $735 | $220 | $150 |
| 659E35000 WATER | 6 MGAL | $60.00 | $1.00 | $1.67 | $1.10 | $1.00 |
| 611E00200 4" CONDUIT, TYPE C | 5 FT | $100 | $69.00 | $84.05 | $110 | $100 |
| 611E04600 12" CONDUIT, TYPE C | 36 FT | $135 | $83.00 | $93.51 | $149 | $70.00 |
| 611E06100 15" CONDUIT, TYPE C | 20 FT | $150 | $124 | $123 | $165 | $120 |
| 611E07600 18" CONDUIT, TYPE C | 10 FT | $175 | $127 | $206 | $193 | $200 |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN, DESCRIPTION NE | 3 EACH | $825 | $2,700 | $2,500 | $908 | $573 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 38 FT | $45.00 | $49.00 | $25.00 | $27.50 | $45.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $85.00 | $92.00 | $85.00 | $110 | $150 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $25.00 | $27.00 | $50.00 | $16.50 | $30.00 |
| 644E20800 YIELD LINE | 25 FT | $13.50 | $13.00 | $14.00 | $14.85 | $62.50 |
| 625E32000 GROUND ROD | 2 EACH | $180 | $325 | $350 | $198 | $5,000 |
| 632E64020 PEDESTAL FOUNDATION | 2 EACH | $1,000 | $1,620 | $1,200 | $1,100 | $3,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 26,928 SF | $5.7 | $153k | 23% |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 1,191 SY | $78 | $93k | 14% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $55,000 | $55k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 6% |
| 608E52000 CURB RAMP | 1,839 SF | $21 | $39k | 6% |
| 202E23000 PAVEMENT REMOVED | 1,096 SY | $35 | $38k | 6% |
| 202E30000 WALK REMOVED | 8,399 SF | $4.5 | $38k | 6% |
| 203E10000 EXCAVATION | 592 CY | $40 | $24k | 4% |
| 630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA | 2 EACH | $11,300 | $23k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $20k | 3% |