HAM-CR 91-01.05 Poole Rd Sidewalk
HAM County · est $0.4M
Bid dateThursday, May 8—
HAM County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 32 more items below.
| Item | Quantity | R1Barrett Paving Materials INC | R2Sunesis Construction CO | R3Prus Construction Company | % of bid |
|---|---|---|---|---|---|
| 608E12000 5" CONCRETE WALK | 9,252 SF | $9.85 | $10.02 | $9.50 | 22% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 68 CY | $695 | $527 | $335 | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $35,000 | $43,782 | $80,000 | 8% |
| 452E11010 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 158 SY | $195 | $114 | $115 | 7% |
| 659E00300 TOPSOIL | 345 CY | $74.00 | $65.00 | $72.00 | 6% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 111 SY | $225 | $119 | $145 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $35,888 |
| Item | Quantity | R1Barrett Paving Materials INC | R2Sunesis Construction CO | R3Prus Construction Company |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,000 | $6,542 | $6,500 |
| 202E23000 PAVEMENT REMOVED, (CONCRETE) | 20 SY | $42.50 | $57.36 | $72.00 |
| 202E30000 WALK REMOVED | 155 SF | $10.00 | $4.49 | $9.50 |
| 202E32000 CURB REMOVED | 40 FT | $5.00 | $17.41 | $38.50 |
| 202E58100 CATCH BASIN REMOVED | 6 EACH | $250 | $730 | $1,150 |
| 608E52000 CURB RAMP |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $15,000 |
| 5% |
| 611E04900 12" CONDUIT, TYPE D | 206 FT | $95.00 | $93.84 | $75.00 | 5% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 110 CY | $155 | $174 | $132 | 4% |
| 203E10000 EXCAVATION | 286 CY | $55.00 | $128 | $48.00 | 4% |
| 611E04600 12" CONDUIT, TYPE C | 125 FT | $115 | $130 | $110 | 3% |
| 441E70700 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (5 CY | $2,500 | $1,384 | $1,375 | 3% |
| 611E04901 12" CONDUIT, TYPE D, AS PER PLAN | 104 FT | $115 | $119 | $118 | 3% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 304E20000 AGGREGATE BASE | 13 CY | $650 | $218 | $155 | 2% |
| 611E98470 CATCH BASIN, NO. 2-2B | 5 EACH | $1,500 | $2,215 | $3,650 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,500 | $15,850 | $10,000 | 2% |
| 203E20000 EMBANKMENT | 148 CY | $50.00 | $32.30 | $45.00 | 2% |
| 202E23000 PAVEMENT REMOVED, (ASPHALT) | 305 SY | $22.50 | $35.37 | $40.00 | 2% |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 449 FT | $15.00 | $15.43 | $28.50 | 2% |
| 198 SF |
| $20.00 |
| $26.80 |
| $40.00 |
| 690E98000 SPECIAL - MAILBOX AND SUPPORT SYSTEM, SINGLE | 16 EACH | $350 | $507 | $570 |
| 690E98400 SPECIAL -CONSULTANT FOR CONCRETE QUALITY CONTROL I | 1 LS | $6,500 | $3,750 | $13,500 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 3,110 SY | $1.84 | $7.11 | $2.20 |
| 659E14000 REPAIR SEEDING AND MULCHING | 156 SY | $1.84 | $1.95 | $2.20 |
| 659E15000 INTER-SEEDING | 156 SY | $1.00 | $1.95 | $2.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.43 TON | $925 | $760 | $840 |
| 659E31000 LIME | 0.64 ACRE | $100 | $50.00 | $55.00 |
| 659E35000 WATER | 17.2 MGAL | $1.00 | $50.00 | $55.00 |
| 611E04400 12" CONDUIT, TYPE B, 706.02 | 5 FT | $245 | $649 | $650 |
| 611E04400 12" CONDUIT, TYPE B, 707.33 | 10 FT | $185 | $401 | $385 |
| 611E98150 CATCH BASIN, NO. 3 | 1 EACH | $4,500 | $5,328 | $5,500 |
| 611E98471 CATCH BASIN, NO. 2-2B, AS PER PLAN | 1 EACH | $2,500 | $4,899 | $8,500 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $4,250 | $4,985 | $8,000 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 3 EACH | $1,250 | $575 | $950 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 3 EACH | $1,950 | $2,087 | $3,350 |
| 407E20000 NON-TRACKING TACK COAT | 4 GAL | $3.75 | $8.00 | $11.00 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $3,000 | $1,632 | $3,250 |
| 609E26000 CURB, TYPE 6 | 21 FT | $105 | $77.54 | $77.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 5 EACH | $350 | $150 | $725 |
| 638E98000 WATER WORK, MISC.: ROADWAY BOX PER GCWW STANDARD D | 3 EACH | $750 | $367 | $1,050 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 39 FT | $15.50 | $15.50 | $18.00 |
| 630E80100 SIGN, FLAT SHEET | 17 SF | $16.00 | $16.00 | $18.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $20.00 | $20.00 | $22.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $25.00 | $25.00 | $28.00 |
| 644E00100 EDGE LINE, 4" | 0.06 MILE | $47,666 | $47,666 | $53,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,534 | $3,771 | $6,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E12000 5" CONCRETE WALK | 9,252 SF | $9.85 | $91k | 18% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 68 CY | $695 | $47k | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $35,000 | $35k | 7% |
| 452E11010 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 158 SY | $195 | $31k | 6% |
| 659E00300 TOPSOIL | 345 CY | $74 | $26k | 5% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 111 SY | $225 | $25k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 4% |
| 611E04900 12" CONDUIT, TYPE D | 206 FT | $95 | $20k | 4% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 110 CY | $155 | $17k | 3% |
| 203E10000 EXCAVATION | 286 CY | $55 | $16k | 3% |