D12-Noise Barrier Repair
D12 County · est $0.4M
Bid dateThursday, May 8—
D12 County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 12 more items below.
| Item | Quantity | R1Great Lakes Construction CO | R2Madex Construction CO | R3Perk Company INC | % of bid |
|---|---|---|---|---|---|
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS | 2,808 SF | $67.00 | $71.44 | $61.60 | 29% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS, CONCRE | 1,782 SF | $71.00 | $78.97 | $60.00 | 20% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS, FIBERG | 1,152 SF | $36.00 | $42.03 | $38.50 | 6% |
| 202E98400 REMOVAL MISC.: NOISE BARRIER PANEL REMOVAL AND DIS | 3,012 SF | $13.00 | $14.20 | $11.75 | 6% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 8 MNTH | $4,500 | $941 | $2,200 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $32,250 | $54,123 | $22,900 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 |
| Item | Quantity | R1Great Lakes Construction CO | R2Madex Construction CO | R3Perk Company INC |
|---|---|---|---|---|
| 202E75000 FENCE REMOVED | 24 FT | $33.00 | $57.89 | $55.80 |
| 606E10810 SPECIAL - NOISE BARRIER: CONCRETE POST CAP | 4 EACH | $1,000 | $2,520 | $575 |
| 606E10810 SPECIAL - NOISE BARRIER' HYDRANT ACCESS HOLE | 1 EACH | $500 | $2,895 | $500 |
| 659E00100 SOIL ANALYSIS TEST | 1 EACH | $50.00 | $289 | $500 |
| 659E14000 REPAIR SEEDING AND MULCHING | 110 SY | $1.00 | $5.79 | $2.00 |
| 659E15000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $41,879 |
| $125,000 |
| 5% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS WITH IN | 306 SF | $82.00 | $92.18 | $76.25 | 4% |
| 606E10810 SPECIAL - NOISE BARRIER: STEEL POST INSTALLATION | 2 EACH | $10,000 | $10,150 | $25,625 | 3% |
| 202E98400 REMOVAL MISC.: FIBERGLASS PANEL REMOVAL AND DELIVE | 588 SF | $30.00 | $33.60 | $31.40 | 3% |
| 606E10920 SPECIAL - NOISE BARRIER: REMOVAL AND REUSE | 720 SF | $20.00 | $18.17 | $18.70 | 2% |
| 659E00300 TOPSOIL | 245 CY | $50.00 | $56.84 | $65.00 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $100 | $116 | $100 | 2% |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 1 LS | $9,000 | $12,323 | $20,000 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $7,500 | $26,962 | $50,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $29,902 | $8,800 | 1% |
| 202E98100 REMOVAL MISC.: NOISE BARRIER POST REMOVAL | 4 EACH | $1,500 | $3,304 | $3,320 | 1% |
| 659E10000 SEEDING AND MULCHING | 2,209 SY | $2.50 | $5.79 | $2.00 | 1% |
| 202E11500 PORTIONS OF STRUCTURE REMOVED' Noise Barrier Found | 2 EACH | $2,500 | $1,033 | $6,690 | 1% |
| 832E30000 EROSION CONTROL | 4,750 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 110 SY |
| $1.00 |
| $5.79 |
| $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.3 TON | $500 | $1,737 | $1,000 |
| 659E31000 LIME | 0.46 ACRE | $100 | $1,158 | $1,000 |
| 659E35000 WATER | 11.9 MGAL | $2.00 | $28.95 | $50.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $750 | $1,737 | $1,500 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $100 | $13,920 | $8,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,300 | $6,895 | $6,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS | 2,808 SF | $67 | $188k | 29% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS, CONCRE | 1,782 SF | $71 | $127k | 20% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS, FIBERG | 1,152 SF | $36 | $41k | 6% |
| 202E98400 REMOVAL MISC.: NOISE BARRIER PANEL REMOVAL AND DIS | 3,012 SF | $13 | $39k | 6% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 8 MNTH | $4,500 | $36k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $32,250 | $32k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 5% |
| 606E10920 SPECIAL - NOISE BARRIER: REFLECTIVE PANELS WITH IN | 306 SF | $82 | $25k | 4% |
| 606E10810 SPECIAL - NOISE BARRIER: STEEL POST INSTALLATION | 2 EACH | $10,000 | $20k | 3% |
| 202E98400 REMOVAL MISC.: FIBERGLASS PANEL REMOVAL AND DELIVE | 588 SF | $30 | $18k | 3% |