PUT-Ottawa Ped. Improvements
PUT County · est $0.3M
Bid dateThursday, June 26—
PUT County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 21 more items below.
| Item | Quantity | R1Ward Construction CO | R2Fenson Contracting LLC | R3D L Smith Concrete LLC | R4Madex Construction CO | % of bid |
|---|---|---|---|---|---|---|
| 630E97700 SIGNING, MISC.: RECTANGULAR RAPID FLASHING BEACON | 6 EACH | $7,250 | $10,500 | $9,135 | $11,579 | 26% |
| 608E10000 4" CONCRETE WALK | 1,552 SF | $14.50 | $16.50 | $25.00 | $22.55 | 13% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 225 FT | $60.00 | $85.00 | $65.00 | $149 | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $13,500 | $25,000 | $20,000 | $14,088 | 8% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 18 CY | $500 | $750 | $800 | $579 | 5% |
| 608E52000 CURB RAMP | 340 SF | $22.50 | $30.00 | $35.00 | $65.71 |
| Item | Quantity | R1Ward Construction CO | R2Fenson Contracting LLC | R3D L Smith Concrete LLC | R4Madex Construction CO |
|---|---|---|---|---|---|
| 202E32500 CURB AND GUTTER REMOVED | 220 FT | $8.50 | $25.00 | $11.50 | $49.55 |
| 203E10000 EXCAVATION | 55 CY | $45.00 | $90.00 | $70.00 | $157 |
| 204E10000 SUBGRADE COMPACTION | 181 SY | $1.10 | $15.00 | $2.50 | $11.58 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E00101 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 624E10000 MOBILIZATION | 1 LS | $6,500 | $10,000 | $25,750 | $30,431 | 4% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 6 EACH | $1,000 | $1,750 | $2,500 | $1,737 | 4% |
| 304E20000 AGGREGATE BASE | 39 CY | $145 | $180 | $80.00 | $235 | 3% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (9 CY | $500 | $875 | $800 | $579 | 3% |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 29 CY | $150 | $250 | $45.00 | $196 | 3% |
| 202E23000 PAVEMENT REMOVED | 181 SY | $23.00 | $90.00 | $24.00 | $56.50 | 2% |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $4,000 | $1,000 | $2,500 | $2,895 | 2% |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $4,000 | $1,000 | $2,500 | $2,895 | 2% |
| 202E30000 WALK REMOVED | 1,594 SF | $2.50 | $8.00 | $15.00 | $5.47 | 2% |
| 659E00501 SEEDING AND MULCHING, CLASS 1, AS PER PLAN | 243 SY | $13.50 | $10.00 | $12.00 | $26.63 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $4,500 | $7,500 | $18,784 | 2% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 21 CY | $140 | $180 | $86.00 | $274 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1-1/2" | 264 SY | $10.00 | $10.00 | $42.00 | $11.58 | 2% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $2,500 | $2,500 | $10,000 | $10,421 | 1% |
| 25 FT |
| $10.00 |
| $25.00 |
| $35.00 |
| $25.26 |
| 611E00901 6" CONDUIT, TYPE B, AS PER PLAN, 707.45, STORM REP | 25 FT | $15.00 | $30.00 | $40.00 | $36.84 |
| 611E01801 8" CONDUIT, TYPE B, AS PER PLAN, 707.45, STORM REP | 25 FT | $20.00 | $35.00 | $48.00 | $48.42 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $1,400 | $2,500 | $2,350 | $1,902 |
| 407E20000 NON-TRACKING TACK COAT, 0.06 GAL/S.Y. | 8 GAL | $8.00 | $1.00 | $7.00 | $9.26 |
| 407E20000 NON-TRACKING TACK COAT, 0.09 GAL/S.Y. | 24 GAL | $8.00 | $1.00 | $7.00 | $5.79 |
| 625E32000 GROUND ROD | 6 EACH | $250 | $315 | $315 | $578 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 161 FT | $12.00 | $16.00 | $15.25 | $28.95 |
| 630E80100 SIGN, FLAT SHEET | 58.5 SF | $20.00 | $30.00 | $25.25 | $31.26 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 11 EACH | $30.00 | $68.00 | $38.00 | $68.42 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 5 EACH | $20.00 | $95.00 | $25.25 | $60.21 |
| 630E97700 SIGNING, MISC.: RECTANGULAR RAPID FLASHING BEACON | 2 EACH | $200 | $2,000 | $25.25 | $2,372 |
| 644E00300 CENTER LINE | 0.03 MILE | $15,000 | $19,500 | $19,000 | $26,632 |
| 644E00620 CROSSWALK LINE, 12" | 167 FT | $4.00 | $5.00 | $5.05 | $12.74 |
| 644E00630 CROSSWALK LINE, 24" | 110 FT | $8.00 | $10.00 | $10.15 | $12.74 |
| 644E01200 PARKING LOT STALL MARKING | 4 FT | $25.00 | $30.00 | $1.50 | $11.58 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 10 FT | $150 | $175 | $190 | $318 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E97700 SIGNING, MISC.: RECTANGULAR RAPID FLASHING BEACON | 6 EACH | $7,250 | $44k | 23% |
| 608E10000 4" CONCRETE WALK | 1,552 SF | $14.5 | $23k | 12% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 225 FT | $60 | $14k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $13,500 | $14k | 7% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 18 CY | $500 | $9k | 5% |
| 608E52000 CURB RAMP | 340 SF | $22.5 | $8k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $6,500 | $7k | 4% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 6 EACH | $1,000 | $6k | 3% |
| 304E20000 AGGREGATE BASE | 39 CY | $145 | $6k | 3% |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (9 CY | $500 | $5k | 2% |