| Item | Quantity | R1Axis Civil Construction LLC | R2Mc Kee Paving & Sealing LLC | R3Alan Stone CO INC | R4Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|
| 608E52000 CURB RAMP | 2,227 SF | $19.00 | $24.00 | $20.00 | $19.55 | 14% |
| 608E12000 5" CONCRETE WALK | 4,987 SF | $8.40 | $18.50 | $8.50 | $10.75 | 14% |
| 609E26000 CURB, TYPE 6 | 983 FT | $28.00 | $25.00 | $75.00 | $64.00 | 9% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 58 CY | $380 | $290 | $400 | $330 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $45,000 | $11,000 | $10,000 | 7% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $15,000 | $10,500 | $10,000 | $45,000 | 5% |
| Item | Quantity | R1Axis Civil Construction LLC | R2Mc Kee Paving & Sealing LLC | R3Alan Stone CO INC | R4Shelly & Sands INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $500 | $5,100 | $2,700 |
| 202E32500 CURB AND GUTTER REMOVED | 113 FT | $16.00 | $10.00 | $40.00 | $15.00 |
| 203E20000 EMBANKMENT | 18 CY | $40.00 | $28.00 | $90.00 | $47.00 |
| 411E10001 STABILIZED CRUSHED AGGREGATE, AS PER PLAN | 11 CY | $85.00 | $90.00 | $110 | $325 |
| 609E24510 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 611E98450 CATCH BASIN, NO. 2-2A | 3 EACH | $4,500 | $1,850 | $4,200 | $3,145 | 4% |
| 304E20000 AGGREGATE BASE | 79 CY | $170 | $90.00 | $150 | $242 | 4% |
| 452E11050 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 36 SY | $345 | $115 | $190 | $178 | 4% |
| 609E72000 CONCRETE MEDIAN | 69 SY | $175 | $145 | $170 | $177 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 28 CY | $420 | $290 | $420 | $545 | 4% |
| 611E04400 12" CONDUIT, TYPE B | 77 FT | $145 | $110 | $210 | $123 | 4% |
| 202E23000 PAVEMENT REMOVED | 410 SY | $25.00 | $22.50 | $20.00 | $34.00 | 3% |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 210 FT | $45.00 | $50.00 | $30.00 | $18.25 | 3% |
| 832E30000 EROSION CONTROL | 7,800 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 203E10000 EXCAVATION | 168 CY | $40.00 | $20.00 | $20.00 | $60.00 | 2% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 207 SY | $32.00 | $18.00 | $25.00 | $34.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,500 | $9,500 | $7,000 | $7,700 | 2% |
| 202E30000 WALK REMOVED | 1,670 SF | $3.80 | $8.00 | $3.00 | $4.00 | 2% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 15 CY | $399 | $365 | $620 | $755 | 2% |
| 60 FT |
| $50.00 |
| $31.00 |
| $140 |
| $90.50 |
| 611E99700 SPECIAL - GAS VALVE BOX ADJUSTED TO GRADE | 1 EACH | $800 | $250 | $60.00 | $286 |
| 620E60000 DELINEATOR, POST SURFACE MOUNTED | 24 EACH | $200 | $210 | $110 | $216 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET | 2 EACH | $250 | $175 | $670 | $81.01 |
| 659E00300 TOPSOIL | 27 CY | $50.00 | $65.00 | $120 | $156 |
| 659E10000 SEEDING AND MULCHING | 245 SY | $10.00 | $10.50 | $7.50 | $22.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 13 SY | $10.00 | $10.50 | $25.00 | $2.00 |
| 659E15000 INTER-SEEDING | 13 SY | $10.00 | $10.50 | $25.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $1,250 | $1,500 | $650 | $965 |
| 659E31000 LIME | 0.05 ACRE | $150 | $175 | $940 | $540 |
| 659E35000 WATER | 0.66 MGAL | $1.00 | $1.00 | $120 | $1.11 |
| 611E00900 6" CONDUIT, TYPE B | 10 FT | $29.00 | $90.00 | $15.00 | $74.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 1 EACH | $900 | $600 | $680 | $1,215 |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 1 EACH | $500 | $250 | $200 | $286 |
| 204E10000 SUBGRADE COMPACTION | 477 SY | $3.50 | $1.00 | $9.00 | $5.50 |
| 407E20000 NON-TRACKING TACK COAT | 62 GAL | $7.99 | $4.00 | $4.00 | $3.30 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 201 FT | $17.50 | $12.00 | $20.00 | $19.00 |
| 630E80100 SIGN, FLAT SHEET | 226 SF | $25.00 | $15.00 | $30.00 | $27.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 4 EACH | $125 | $100 | $150 | $135 |
| 642E30001 REMOVAL OF PAVEMENT MARKING, AS PER PLAN | 45 FT | $65.00 | $22.00 | $75.00 | $21.60 |
| 644E00100 EDGE LINE, 4" | 0.32 MILE | $11,470 | $7,500 | $13,000 | $7,410 |
| 644E00500 STOP LINE | 43 FT | $15.00 | $11.00 | $20.00 | $10.75 |
| 644E00620 CROSSWALK LINE, 12" | 446 FT | $5.50 | $5.00 | $6.50 | $4.75 |
| 644E00630 CROSSWALK LINE, 24" | 320 FT | $12.25 | $9.50 | $15.00 | $9.35 |
| 616E10000 WATER | 0.56 MGAL | $1.34 | $1.00 | $2.00 | $390 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,500 | $5,700 | $5,000 | $2,350 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E52000 CURB RAMP | 2,227 SF | $19 | $42k | 12% |
| 608E12000 5" CONCRETE WALK | 4,987 SF | $8.4 | $42k | 12% |
| 609E26000 CURB, TYPE 6 | 983 FT | $28 | $28k | 8% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 58 CY | $380 | $22k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 6% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $15,000 | $15k | 4% |
| 611E98450 CATCH BASIN, NO. 2-2A | 3 EACH | $4,500 | $14k | 4% |
| 304E20000 AGGREGATE BASE | 79 CY | $170 | $13k | 4% |
| 452E11050 7" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 36 SY | $345 | $12k | 3% |
| 609E72000 CONCRETE MEDIAN | 69 SY | $175 | $12k | 3% |