KNO-SR 3-25.94
KNO County · est $0.2M
Bid dateThursday, December 18—
KNO County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 13 more items below.
| Item | Quantity | R1Crawford Construction Company INC | R2Rietschlin Construction INC | R3Madex Construction CO | % of bid |
|---|---|---|---|---|---|
| 608E13000 6" CONCRETE WALK | 1,896 SF | $20.00 | $12.00 | $19.51 | 25% |
| 624E10000 MOBILIZATION | 1 LS | $20,300 | $11,000 | $19,974 | 14% |
| 609E24001 CURB, TYPE 4-A, AS PER PLAN | 552 FT | $33.00 | $60.00 | $81.05 | 12% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $9,100 | $20,000 | $12,113 | 6% |
| 203E10000 EXCAVATION | 109 CY | $70.00 | $64.00 | $81.80 | 5% |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 67 SY | $110 | $136 | $156 | 5% |
| 202E30000 WALK REMOVED | 1,896 SF | $3.62 | $2.50 |
| Item | Quantity | R1Crawford Construction Company INC | R2Rietschlin Construction INC | R3Madex Construction CO |
|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 20 FT | $20.00 | $50.00 | $35.85 |
| 202E53100 MAILBOX REMOVED | 7 EACH | $100 | $50.00 | $140 |
| 204E10000 SUBGRADE COMPACTION | 220 SY | $3.30 | $12.00 | $10.42 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 3 EACH | $230 | $655 | $695 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 2 EACH | $383 | $798 | $926 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $7.26 |
| 5% |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 552 FT | $10.00 | $3.00 | $5.79 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,400 | $2,600 | $9,947 | 4% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 125 SY | $42.00 | $40.00 | $53.62 | 3% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | 3% |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 26 CY | $178 | $210 | $184 | 3% |
| 653E10001 TOPSOIL FURNISHED AND PLACED, AS PER PLAN | 60 CY | $70.00 | $103 | $86.84 | 3% |
| 304E20000 AGGREGATE BASE | 25 CY | $138 | $220 | $184 | 2% |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 535 SY | $5.90 | $7.00 | $8.11 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,800 | $2,000 | $8,095 | 2% |
| 608E53020 DETECTABLE WARNING | 16 SF | $57.00 | $61.00 | $57.89 | 1% |
| 611E00300 4" CONDUIT, TYPE D | 20 FT | $45.00 | $61.00 | $47.89 | 1% |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $835 | $860 | $8,105 | 1% |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $835 | $860 | $5,789 | 1% |
| 2 EACH |
| $100 |
| $110 |
| $89.47 |
| 659E14000 REPAIR SEEDING AND MULCHING | 27 SY | $1.00 | $7.00 | $1.16 |
| 659E15000 INTER-SEEDING | 27 SY | $1.00 | $7.00 | $1.16 |
| 659E20000 COMMERCIAL FERTILIZER | 0.07 TON | $660 | $1,300 | $2,857 |
| 659E31000 LIME | 0.11 ACRE | $2,500 | $150 | $568 |
| 659E35000 WATER | 3 MGAL | $18.00 | $22.00 | $7.53 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 10.5 FT | $26.00 | $80.00 | $86.84 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $115 | $105 | $116 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E13000 6" CONCRETE WALK | 1,896 SF | $20 | $38k | 25% |
| 624E10000 MOBILIZATION | 1 LS | $20,300 | $20k | 13% |
| 609E24001 CURB, TYPE 4-A, AS PER PLAN | 552 FT | $33 | $18k | 12% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $9,100 | $9k | 6% |
| 203E10000 EXCAVATION | 109 CY | $70 | $8k | 5% |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 67 SY | $110 | $7k | 5% |
| 202E30000 WALK REMOVED | 1,896 SF | $3.62 | $7k | 4% |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 552 FT | $10 | $6k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,400 | $5k | 3% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 125 SY | $42 | $5k | 3% |