BUT-SR 122-00.00
BUT County · est $2.2M
Bid dateThursday, January 15—
Awarded toBARRETT PAVING MATERIALS INC$2.59M
BUT County · est $2.2M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (3136 CY | $335 | $1.05M | 41% |
| 253E02000 PAVEMENT REPAIR | 650 CY | $405 | $263k | 10% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 112,885 SY | $1.8 | $203k | 8% |
| 624E10000 MOBILIZATION Section 9 - INCIDENTALS - Totals Awd $194,899.15 2 $492,549.55 | 1 LS | $98,000 | $98k | 4% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 79 FT | $1,000 | $79k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $70k | 3% |
| 617E10100 COMPACTED AGGREGATE | 363 CY | $170 | $62k | 2% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $60,000 | $60k | 2% |
| 407E20000 NON-TRACKING TACK COAT | 10,160 GAL | $4.5 | $46k | 2% |
| 644E00104 EDGE LINE, 6" | 11.21 MILE | $3,890 | $44k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 63 more items below.
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company | % of bid |
|---|---|---|---|---|
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (3136 CY | $335 | $325 | 46% |
| 253E02000 PAVEMENT REPAIR | 650 CY | $405 | $536 | 11% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 112,885 SY | $1.80 | $1.96 | 9% |
| 624E10000 MOBILIZATION Section 9 - INCIDENTALS - Totals Awd $194,899.15 2 $492,549.55 | 1 LS | $98,000 | $137,500 | 4% |
| 516E11210 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 79 FT | $1,000 | $1,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $328,490 | 3% |
| 617E10100 COMPACTED AGGREGATE | 363 CY | $170 | $161 | 3% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $60,000 | $60,000 | 3% |
| 407E20000 NON-TRACKING TACK COAT | 10,160 GAL | $4.50 | $4.00 | 2% |
| 644E00104 EDGE LINE, 6" | 11.21 MILE | $3,890 | $4,464 | 2% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 225 SF | $179 | $179 | 2% |
| 511E34410 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 10 CY | $3,800 | $3,800 | 2% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A Section 7 - STRUCTURE REPAIR (BUT-122-0297 SFN090212 - Totals Awd $347,846.25 2 $347,846.25 | 1 LS | $38,000 | $38,000 | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 227 SY | $165 | $149 | 2% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 1,325 FT | $25.50 | $22.20 | 1% |
| 644E00300 CENTER LINE | 6.1 MILE | $5,275 | $5,412 | 1% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $30,500 | $25,657 | 1% |
| 614E18002 MAINTAINING TRAFFIC, MISC.: PORTABLE TRAFFIC SIGNA | 1 LS | $30,000 | $26,510 | 1% |
| 513E10200 STRUCTURAL STEEL MEMBERS, LEVEL UF | 1,757 LB | $15.00 | $15.00 | 1% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 225 SF | $102 | $102 | 1% |
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company |
|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 1,725 FT | $2.00 | $2.00 |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN | 3 EACH | $500 | $295 |
| 202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E | 2 EACH | $200 | $150 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 5 EACH | $2,500 | $2,480 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN Section 1 - ROADWAY - Totals Awd $66,637.50 2 $61,912.02 | 1 LS | $15,000 | $15,462 |
| 611E99654 MANHOLE ADJUSTED TO GRADE Section 2 - DRAINAGE - Totals Awd $3,750.00 2 $3,671.28 | 2 EACH | $1,875 | $1,836 |
| 617E20000 SHOULDER PREPARATION | 6,653 SY | $2.70 | $2.37 |
| 617E25000 WATER | 7 MGAL | $100 | $8.37 |
| 897E02000 PATCHING PLANED SURFACE Section 3 - PAVEMENT - Totals Awd $1,656,764.10 2 $1,710,026.09 | 1,139 SY | $12.00 | $4.73 |
| 621E00100 RPM | 572 EACH | $32.35 | $32.35 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 572 EACH | $12.00 | $13.28 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 19 EACH | $12.00 | $15.00 |
| 644E00204 LANE LINE, 6" | 0.8 MILE | $2,060 | $2,232 |
| 644E00404 CHANNELIZING LINE, 12" | 906 FT | $2.15 | $1.48 |
| 644E00500 STOP LINE | 12 FT | $5.15 | $6.75 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 1,883 FT | $4.90 | $4.75 |
| 644E00720 CHEVRON MARKING | 28 FT | $4.90 | $5.75 |
| 644E00900 ISLAND MARKING | 273 SF | $4.65 | $4.40 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $410 | $550 |
| 644E01110 SCHOOL SYMBOL MARKING, 96" | 2 EACH | $435 | $550 |
| 644E01300 LANE ARROW | 11 EACH | $125 | $101 |
| 644E01501 DOTTED LINE, 4", AS PER PLAN | 50 FT | $2.00 | $1.35 |
| 646E10010 EDGE LINE, 6" | 0.12 MILE | $23,270 | $35,244 |
| 646E10200 CENTER LINE Section 4 - TRAFFIC CONTROL - Totals Awd $123,493.85 2 $133,381.23 | 0.06 MILE | $31,080 | $46,992 |
| 202E23000 PAVEMENT REMOVED | 167 SY | $23.00 | $21.13 |
| 202E34900 PIPE REMOVED | 80 FT | $20.00 | $36.15 |
| 611E02400 8" CONDUIT, TYPE D CORRIGATE PLASTIC PIPE | 40 FT | $50.00 | $122 |
| 611E04900 12" CONDUIT, TYPE D, CORRIGATE PLASTIC PIPE | 40 FT | $53.00 | $159 |
| 614E11630 INCREASED BARRIER DELINEATION | 961 FT | $1.81 | $1.81 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,986 | $1,986 |
| 614E12800 WORK ZONE RAISED PAVEMENT MARKER | 35 EACH | $8.84 | $46.80 |
| 614E13312 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 22 EACH | $10.83 | $10.83 |
| 614E13318 BARRIER REFLECTOR, TYPE 5 (BIDIRECTIONAL) | 22 EACH | $10.83 | $10.83 |
| 614E13360 OBJECT MARKER, TWO WAY | 44 EACH | $18.47 | $18.47 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.8 MILE | $140 | $750 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.2 MILE | $6,545 | $7,000 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 6.1 MILE | $515 | $1,440 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.5 MILE | $5,520 | $5,540 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 11.21 MILE | $375 | $1,008 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 906 FT | $0.75 | $0.50 |
| 614E25620 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS III, 642 | 1,883 FT | $3.00 | $2.20 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 44 FT | $3.50 | $10.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 12 FT | $3.40 | $5.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 11 EACH | $75.00 | $35.00 |
| 614E31750 WORK ZONE SCHOOL SYMBOL MARKING, 96", CLASS III, 6 | 2 EACH | $350 | $225 |
| 614E32210 WORK ZONE RAILROAD SYMBOL MARKING, CLASS III, 642 | 2 EACH | $325 | $225 |
| 614E32800 WORK ZONE ISLAND MARKING, CLASS III, 642 PAINT | 273 SF | $3.25 | $2.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED Section 5 - MAINTENANCE OF TRAFFIC - Totals Awd $160,469.65 2 $168,568.14 | 780 FT | $26.36 | $26.36 |
| 202E11202 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $4,500 | $4,500 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM Section 6 - STRUCTURE REPAIR (BUT-122-0076 SFN 09020 - Totals Awd $24,750.00 2 $24,750.00 | 27 CF | $750 | $750 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 714 LB | $6.00 | $6.00 |
| 509E20000 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 100 LB | $2.00 | $2.00 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 10 EACH | $40.00 | $40.00 |
| 511E81300 CONCRETE, MISC.: EMBEDDED GALVANIC ANODES (EGA) | 160 EACH | $50.00 | $50.00 |
| 512E44450 TYPE E WATERPROOFING | 12 SY | $50.00 | $50.00 |
| 516E10000 PREFORMED ELASTOMERIC COMPRESSION JOINT SEAL | 79 FT | $30.00 | $30.00 |
| 516E44201 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 5 EACH | $2,500 | $2,500 |
| 516E44401 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 5 EACH | $3,000 | $3,000 |
| 517E75501 BRIDGE RAILING REBUILT, AS PER PLAN | 350 FT | $12.00 | $17.40 |
| 517E75600 DEEP BEAM BRIDGE RETROFIT RAILING Section 8 - STRUCTURE REPAIR (BUT-122-0311 SFN 09021 - Totals Awd $11,387.50 2 $13,840.00 | 62.5 FT | $115 | $124 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $15,000 | $5,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,899 | $13,728 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $5,000 | $7,832 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →