MAH-IR 76/IR 80-08.50/00.00
MAH County · est $19M
Bid dateThursday, March 26—
Awarded toKARVO COMPANIES INC$21.1M
MAH County · est $19M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 24,472 CY | $232 | $5.68M | 27% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 14,753 CY | $230 | $3.39M | 16% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 12,645 CY | $268 | $3.39M | 16% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $2,659,860.65 2 $3,335,450.69 3 $3,870,000.00 | 1 LS | $1,250,000 | $1.25M | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,100,000 | $1.10M | 5% |
| 606E55010 SPECIAL - CABLE BARRIER WITH CONCRETE LINE POST FO | 16,425 FT | $42 | $690k | 3% |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (1382 CY | $330 | $456k | 2% |
| 321E17501 CRACKING AND SEATING NON-REINFORCED CONCRETE PAVEM | 297,673 SY | $1.5 | $447k | 2% |
| 209E70000 BORROW | 12,642 CY | $35 | $442k | 2% |
| 442E00100 ANTI-SEGREGATION EQUIPMENT | 32,344 CY | $13 | $420k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 85 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Shelly & Sands INC | R3Shelly Company | % of bid |
|---|---|---|---|---|---|
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 24,472 CY | $232 | $215 | $248 | 30% |
| 442E10080 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 14,753 CY | $230 | $215 | $238 | 18% |
| 442E10300 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 12,645 CY | $268 | $247 | $260 | 18% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $2,659,860.65 2 $3,335,450.69 3 $3,870,000.00 | 1 LS | $1,250,000 | $1,000,000 | $800,000 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,100,000 | $2,123,451 | $2,700,000 | 6% |
| 606E55010 SPECIAL - CABLE BARRIER WITH CONCRETE LINE POST FO | 16,425 FT | $42.00 | $45.00 | $41.50 | 4% |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (1382 CY | $330 | $310 | $353 | 2% |
| 321E17501 CRACKING AND SEATING NON-REINFORCED CONCRETE PAVEM | 297,673 SY | $1.50 | $1.50 | $1.00 | 2% |
| 209E70000 BORROW | 12,642 CY | $35.00 | $60.00 | $43.50 | 2% |
| 442E00100 ANTI-SEGREGATION EQUIPMENT | 32,344 CY | $13.00 | $15.00 | $7.75 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 15,987.5 FT | $19.60 | $19.60 | $19.60 | 2% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 10,725 FT | $24.40 | $23.80 | $23.80 | 1% |
| 605E31100 AGGREGATE DRAINS | 28,590 FT | $7.50 | $15.00 | $12.50 | 1% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $465,019.70 2 $690,195.70 3 $1,031,628.20 | 210,000 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $180,000 | $90,000 | $175,000 | 1% |
| 451E34000 SPECIAL - PRESSURE RELIEF JOINT, TYPE A, AS PER PL | 1,172 FT | $152 | $160 | $150 | 1% |
| 614E22056 WORK ZONE EDGE LINE, CLASS I, 6", 807 PAINT | 60 MILE | $2,415 | $2,415 | $2,415 | 1% |
| 254E01010 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE [T = 3. | 9,274 SY | $15.00 | $35.00 | $25.00 | 1% |
| 659E00300 TOPSOIL | 14,398 CY | $8.00 | $25.00 | $45.00 | 1% |
| 606E55150 SPECIAL - CABLE BARRIER, ANCHOR ASSEMBLY | 28 EACH | $3,950 | $3,950 | $3,950 | 1% |
| Item | Quantity | R1Karvo Companies INC | R2Shelly & Sands INC | R3Shelly Company |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $50,000 | $210,000 | $5,000 |
| 202E38000 GUARDRAIL REMOVED | 29,538 FT | $2.00 | $2.00 | $2.00 |
| 202E48000 CABLE BARRIER REMOVED | 17,504 FT | $2.50 | $7.00 | $6.00 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 10 CY | $25.00 | $600 | $50.00 |
| 209E60500 LINEAR GRADING | 11.09 MILE | $4,000 | $7,000 | $4,550 |
| 209E60501 LINEAR GRADING, AS PER PLAN | 5.62 MILE | $2,500 | $7,800 | $20,000 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 5 EACH | $2,475 | $2,475 | $2,475 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 39 EACH | $2,440 | $2,440 | $2,440 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 39 EACH | $1,360 | $1,360 | $1,360 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 29 EACH | $2,450 | $2,450 | $2,450 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 22 EACH | $595 | $595 | $595 |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 4 EACH | $9,340 | $9,340 | $9,340 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 340 FT | $18.00 | $25.00 | $75.00 |
| 622E90000 BARRIER, MISC.: PORTABLE CONCRETE BARRIER REMOVED | 405 FT | $15.00 | $20.00 | $12.50 |
| 622E90200 BARRIER, MISC.: TAPERED END SECTION | 8 EACH | $375 | $1,500 | $1,000 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $5,000 | $5,000 | $20,000 |
| 690E98000 SPECIAL - VERTICAL CLEARANCE | 24 EACH | $780 | $750 | $780 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION Section 1 - ROADWAY - Totals Awd $2,353,431.00 2 $3,044,600.00 3 $2,617,591.50 | 1 LS | $2,980 | $15,000 | $15,000 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $25.00 | $25.00 | $400 |
| 659E10000 SEEDING AND MULCHING | 129,714 SY | $0.65 | $0.65 | $0.80 |
| 659E20000 COMMERCIAL FERTILIZER | 17.51 TON | $250 | $250 | $1,200 |
| 659E31000 LIME | 26.8 ACRE | $25.00 | $25.00 | $5.00 |
| 659E35000 WATER | 700 MGAL | $0.01 | $1.00 | $15.00 |
| 670E00500 SLOPE EROSION PROTECTION | 4,167 SY | $1.30 | $1.30 | $3.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $15,000 | $6,200 | $7,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $15,000 | $8,560 | $7,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $15,000 | $9,957 | $10,000 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 35 EACH | $500 | $1,600 | $2,000 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 11 EACH | $5,750 | $4,000 | $5,750 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 4 EACH | $1,000 | $1,400 | $1,850 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL Section 3 - DRAINAGE - Totals Awd $307,175.00 2 $538,450.00 3 $506,025.00 | 2,000 LB | $4.00 | $2.00 | $4.00 |
| 253E01000 PAVEMENT REPAIR | 180 SY | $300 | $340 | $420 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 10 CY | $50.00 | $200 | $50.00 |
| 407E13900 TACK COAT, 702.13 | 27,053 GAL | $2.50 | $2.75 | $5.00 |
| 407E20000 NON-TRACKING TACK COAT | 33,073 GAL | $2.50 | $3.05 | $3.10 |
| 408E10001 PRIME COAT, AS PER PLAN | 2,597 GAL | $6.00 | $3.50 | $6.00 |
| 451E34000 SPECIAL - PRESSURE RELIEF JOINT, TYPE A, AS PER PL | 61 FT | $280 | $250 | $270 |
| 609E24510 CURB, TYPE 4-C | 231 FT | $62.00 | $73.00 | $95.00 |
| 617E10100 COMPACTED AGGREGATE | 397 CY | $150 | $200 | $165 |
| 618E40600 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) Section 4 - PAVEMENT - Totals Awd $14,425,266.00 2 $13,812,785.40 3 $14,755,375.80 | 16.55 MILE | $850 | $1,500 | $1,800 |
| 621E00100 RPM | 436 EACH | $34.10 | $34.10 | $34.10 |
| 621E00101 RPM, AS PER PLAN | 1,170 EACH | $34.10 | $34.10 | $34.10 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,606 EACH | $20.00 | $20.00 | $5.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, (ONE-WAY) | 144 EACH | $11.50 | $11.50 | $11.50 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, (BIDIRECTIONAL) | 16 EACH | $13.00 | $13.00 | $13.00 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, (ONE-WAY) | 393 EACH | $13.00 | $13.00 | $13.00 |
| 626E00118 BARRIER REFLECTOR, TYPE 6 | 198 EACH | $17.00 | $17.00 | $17.00 |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 5 EACH | $1,625 | $1,625 | $1,625 |
| 630E87100 REMOVAL OF OVERHEAD MOUNTED SIGN AND REERECTION | 1 EACH | $2,420 | $2,420 | $2,420 |
| 646E10620 CHEVRON MARKING | 1,000 FT | $11.00 | $11.00 | $11.00 |
| 807E12010 WET REFLECTIVE EPOXY PAVEMENT MARKING, EDGE LINE, | 19.94 MILE | $3,450 | $3,450 | $3,450 |
| 807E12110 WET REFLECTIVE EPOXY PAVEMENT MARKING, LANE LINE, | 17.55 MILE | $1,750 | $1,750 | $1,750 |
| 807E12310 WET REFLECTIVE EPOXY PAVEMENT MARKING, CHANNELIZIN | 11,545 FT | $2.75 | $2.75 | $2.75 |
| 807E12410 WET REFLECTIVE EPOXY PAVEMENT MARKING, DOTTED LINE | 6,065 FT | $1.25 | $1.25 | $1.25 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1,100 | $1,100 | $1,100 |
| 850E10110 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1.00 | $1.00 | $1.00 |
| 850E10130 GROOVING FOR 12" RECESSED PAVEMENT MARKING | — | $1.50 | $1.50 | $1.50 |
| 850E20010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $2,500 | $2,500 | $2,500 |
| 814E00010 INTERSTATE ELONGATED ROUTE SHIELD SYMBOL MARKING, | 4 EACH | $2,960 | $2,960 | $2,960 |
| 814E00014 STATE ROUTE SHIELD SYMBOL MARKING, TYPE B125 | 1 EACH | $2,960 | $2,960 | $2,960 |
| 814E00016 CARDINAL DIRECTION (NORTH, SOUTH, WEST & EAST) MAR Section 5 - TRAFFIC CONTROL - Totals Awd $345,846.60 2 $345,846.60 3 $321,756.60 | 1 EACH | $1,835 | $1,835 | $1,835 |
| 632E90400 SIGNALIZATION, MISC.: POLE-MOUNTED CABINET FOUNDAT | 1 EACH | $1,800 | $1,800 | $1,800 |
| 632E90400 SIGNALIZATION, MISC.: POLE-MOUNTED CABINET REMOVED | 1 EACH | $1,500 | $1,500 | $1,500 |
| 632E90400 SIGNALIZATION, MISC.: PULL BOX REMOVED Section 6 - TRAFFIC SURVEILLANCE - Totals Awd $5,700.00 2 $5,700.00 3 $5,700.00 | 4 EACH | $600 | $600 | $600 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 250 HOUR | $125 | $95.00 | $125 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 12 EACH | $250 | $250 | $250 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 74 SNMT | $1,000 | $870 | $900 |
| 614E20056 WORK ZONE LANE LINE, CLASS I, 6", 807 PAINT | 52.5 MILE | $1,365 | $1,365 | $1,365 |
| 614E23110 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 807 PAI | 34,650 FT | $2.00 | $2.00 | $2.00 |
| 614E24102 WORK ZONE DOTTED LINE, CLASS I, 6", 807 PAINT | 18,180 FT | $1.30 | $1.30 | $1.30 |
| 616E10000 WATER | 100 MGAL | $1.00 | $100 | $50.00 |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 54 SNMT | $650 | $650 | $650 |
| 614E13310 BARRIER REFLECTOR, TYPE 1ONE WAY | 250 EACH | $9.24 | $9.24 | $9.25 |
| 614E13310 BARRIER REFLECTOR, TYPE 1BIDIRECTIONAL | 250 EACH | $9.24 | $9.24 | $9.25 |
| 614E13312 BARRIER REFLECTOR, TYPE 2ONE WAY | 250 EACH | $8.89 | $8.89 | $9.00 |
| 614E13312 BARRIER REFLECTOR, TYPE 2BIDIRECTIONAL | 250 EACH | $8.89 | $8.89 | $9.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 50 EACH | $19.20 | $19.20 | $19.20 |
| 614E13360 OBJECT MARKER, TWO WAY | 50 EACH | $21.96 | $21.96 | $22.00 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 17.5 MILE | $690 | $690 | $690 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 20 MILE | $815 | $815 | $815 |
| 614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P | 11,550 FT | $1.00 | $1.00 | $1.00 |
| 614E24612 WORK ZONE DOTTED LINE, CLASS III, 6", 642 PAINT | 6,060 FT | $0.75 | $0.75 | $0.75 |
| 614E12420 DETOUR SIGNING Section 7 - MAINTENANCE OF TRAFFIC - Totals Awd $565,541.30 2 $557,385.87 3 $566,103.30 | 1 LS | $57,000 | $56,091 | $60,000 |
| 619E16020 FIELD OFFICE, TYPE C | 12 MNTH | $3,500 | $6,000 | $3,750 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $87,861 | $50,000 | $150,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →