BID #260086 · ODOTRESULT · awarded Feb 19

HAR-SR 235-02.39

HAR County · est $1.9M

Bid dateThursday, February 19
Awarded toSHELLY COMPANY$1.55M
read → connected → answeredcassandri

Project scope

Bid form · ODOT

21ITEMS
  • Maintaining Traffic24%
  • Pavement Marking19%
  • Removal & Demolition10%
  • Asphalt Paving10%
  • Aggregate & Base10%
  • Structures / Bridge10%
  • Other19%

Top items by winning bid

ItemQtyUnit priceExtended%
441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG4,899 CY$204$999k64%
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, T=1.25"144,768 SY$0.95$138k9%
253E02000 PAVEMENT REPAIR300 CY$275$83k5%
617E10101 COMPACTED AGGREGATE, AS PER PLAN Section 2 - PAVEMENT - Totals Awd $1,381,182.10 2 $1,408,354.801,302 CY$59$77k5%
441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG128 CY$325$42k3%
614E11000 MAINTAINING TRAFFIC1 LS$40,000$40k3%
407E20000 NON-TRACKING TACK COAT12,306 GAL$2.5$31k2%
624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $75,750.00 2 $67,050.001 LS$25,000$25k2%
621E00100 RPM659 EACH$36.5$24k2%
202E23500 WEARING COURSE REMOVED Section 1 - ROADWAY - Totals Awd $20,797.65 2 $20,797.653,681 SY$5.65$21k1%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 1 more items below.

Rank 1Shelly Company$1.55MRank 2Bluffton Paving INC$1.57M
ItemQuantityR1Shelly CompanyR2Bluffton Paving INC
441E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG4,899 CY$204$200
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, T=1.25"144,768 SY$0.95$1.35
253E02000 PAVEMENT REPAIR300 CY$275$286
617E10101 COMPACTED AGGREGATE, AS PER PLAN Section 2 - PAVEMENT - Totals Awd $1,381,182.10 2 $1,408,354.801,302 CY$59.00$52.00
441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG128 CY$325$380
614E11000 MAINTAINING TRAFFIC1 LS$40,000$36,800
407E20000 NON-TRACKING TACK COAT12,306 GAL$2.50$2.00
624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $75,750.00 2 $67,050.001 LS$25,000$20,000
621E00100 RPM659 EACH$36.50$36.50
202E23500 WEARING COURSE REMOVED Section 1 - ROADWAY - Totals Awd $20,797.65 2 $20,797.653,681 SY$5.65$5.65
642E00104 EDGE LINE, 6", TYPE 120.81 MILE$800$800
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$10,000$9,500
254E01600 PATCHING PLANED SURFACE2,821 SY$3.50$2.00
642E00300 CENTER LINE, TYPE 110.4 MILE$900$900
614E21000 WORK ZONE CENTER LINE, CLASS I10.2 MILE$900$900
614E21400 WORK ZONE CENTER LINE, CLASS II Section 4 - MAINTENANCE OF TRAFFIC - Totals Awd $18,870.00 2 $21,930.0020.4 MILE$350$500
304E20000 AGGREGATE BASE36 CY$75.00$20.00
621E54000 RAISED PAVEMENT MARKER REMOVED659 EACH$4.00$4.00
614E12460 WORK ZONE MARKING SIGN30 EACH$85.00$85.00
623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE5 EACH$150$150
Show all 21 line items
ItemQuantityR1Shelly CompanyR2Bluffton Paving INC
644E00500 STOP LINE Section 3 - TRAFFIC CONTROL - Totals Awd $53,072.50 2 $53,072.5015 FT$25.00$25.00

Project details

Description
HAR-SR 235-02.39
Type of work
Pavement

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →