BID #260135 · ODOTRESULT · awarded Mar 12

SHE-PAVE-FY26

SHE County · est $5.7M

Bid dateThursday, March 12
Awarded toBARRETT PAVING MATERIALS INC$5.00M
read → connected → answeredcassandri

Project scope

Bid form · ODOT

50ITEMS
  • Maintaining Traffic24%
  • Pavement Marking22%
  • Curb, Walk & Ramp10%
  • Asphalt Paving10%
  • Erosion & Landscaping6%
  • Removal & Demolition4%
  • Other24%

Top items by winning bid

ItemQtyUnit priceExtended%
441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG15,214 CY$210$3.19M64%
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" DEPTH364,180 SY$1.9$692k14%
251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA4,127 SY$60$248k5%
617E10100 COMPACTED AGGREGATE, 1" AVERAGE THICKNESS1,273 CY$100$127k3%
614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT76.5 MILE$1,100$84k2%
614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT41.44 MILE$1,729$72k1%
614E11000 MAINTAINING TRAFFIC1 LS$65,000$65k1%
407E20000 NON-TRACKING TACK COAT, 0.085 GAL/SY30,989 GAL$2$62k1%
624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $133,593.89 2 $450,000.001 LS$55,000$55k1%
874E21000 LONGITUDINAL JOINT PREPARATION Section 4 - PAVEMENT - Totals Awd $4,439,780.00 2 $5,250,221.4011.42 MILE$4,500$51k1%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.

Rank 1Barrett Paving Materials INC$5.00MRank 2Shelly Company$6.09M
ItemQuantityR1Barrett Paving Materials INCR2Shelly Company
441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG15,214 CY$210$250
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" DEPTH364,180 SY$1.90$2.25
251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA4,127 SY$60.00$60.00
617E10100 COMPACTED AGGREGATE, 1" AVERAGE THICKNESS1,273 CY$100$110
614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT76.5 MILE$1,100$695
614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT41.44 MILE$1,729$950
614E11000 MAINTAINING TRAFFIC1 LS$65,000$200,000
407E20000 NON-TRACKING TACK COAT, 0.085 GAL/SY30,989 GAL$2.00$3.00
624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $133,593.89 2 $450,000.001 LS$55,000$200,000
874E21000 LONGITUDINAL JOINT PREPARATION Section 4 - PAVEMENT - Totals Awd $4,439,780.00 2 $5,250,221.4011.42 MILE$4,500$6,000
690E98300 SPECIAL - ASPHALT PAVEMENT INTERLAYER MATTING Section 1 - ROADWAY - Totals Awd $108,371.91 2 $101,980.9111,399 SY$4.09$4.09
621E00100 RPM1,351 EACH$34.50$34.50
642E00104 EDGE LINE, 6", TYPE 138.25 MILE$894$800
618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE)22.84 MILE$800$1,160
618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE)11.42 MILE$1,600$1,200
608E52000 CURB RAMP889 SF$20.00$25.00
642E00300 CENTER LINE, TYPE 120.72 MILE$777$900
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$13,594$50,000
608E53020 DETECTABLE WARNING225 SF$60.00$42.00
638E10800 VALVE BOX ADJUSTED TO GRADE Section 5 - WATER WORK - Totals Awd $12,300.00 2 $31,775.0041 EACH$300$775
Show all 50 line items
ItemQuantityR1Barrett Paving Materials INCR2Shelly Company
202E30000 WALK REMOVED1,043 SF$10.00$6.00
202E32500 CURB AND GUTTER REMOVED136 FT$20.00$16.00
608E10000 4" CONCRETE WALK448 SF$20.00$25.00
623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE8 EACH$800$200
690E50350 SPECIAL - MAILBOX REMOVED AND RESET7 EACH$280$350
659E00300 TOPSOIL, 4"1 CY$250$250
659E00500 SEEDING AND MULCHING, CLASS 140 SY$10.00$10.00
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $1,650.00 2 $1,650.001,000 EACH$1.00$1.00
611E99654 MANHOLE ADJUSTED TO GRADE Section 3 - DRAINAGE - Totals Awd $10,400.00 2 $15,600.0013 EACH$800$1,200
253E01001 PAVEMENT REPAIR, AS PER PLAN111 SY$82.00$130
254E01601 PATCHING PLANED SURFACE, AS PER PLAN375 SY$10.00$25.00
301E56001 ASPHALT CONCRETE BASE, (449), AS PER PLAN, PG 64-214 CY$650$350
407E20000 NON-TRACKING TACK COAT, 0.26 GAL/SY2,967 GAL$2.00$3.00
609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN3 FT$60.00$125
621E54000 RAISED PAVEMENT MARKER REMOVED1,351 EACH$6.00$7.00
644E00500 STOP LINE234 FT$7.00$5.00
644E00620 CROSSWALK LINE, 12"970 FT$3.50$6.00
644E00630 CROSSWALK LINE, 24"72 FT$7.00$9.00
644E01110 SCHOOL SYMBOL MARKING, 96"3 EACH$550$500
644E01200 PARKING LOT STALL MARKING128 FT$5.00$1.20
644E01300 LANE ARROW, LEFT AND THRU1 EACH$275$120
644E01300 LANE ARROW, RIGHT Section 6 - TRAFFIC CONTROL - Totals Awd $113,406.44 2 $114,966.102 EACH$147$120
614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST40 HOUR$80.00$120
614E12460 WORK ZONE MARKING SIGN96 EACH$110$102
614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT468 FT$3.00$5.00
614E27250 WORK ZONE CROSSWALK LINE, CLASS III, 12", 642 PAIN1,940 FT$1.50$4.00
614E27260 WORK ZONE CROSSWALK LINE, CLASS III, 24", 642 PAIN144 FT$3.00$5.00
614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT, LEFT AND TH2 EACH$77.00$60.00
614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT, RIGHT4 EACH$50.00$60.00
614E31750 WORK ZONE SCHOOL SYMBOL MARKING, 96", CLASS III, 6 Section 7 - MAINTENANCE OF TRAFFIC - Totals Awd $175,997.76 2 $120,060.466 EACH$223$300

Project details

Description
SHE-PAVE-FY26
Type of work
Pavement

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →