Figure 0.1 · BRIEFING
BID #260196 · ODOTRESULT · awarded Apr 23

BEL-SR 7-00.94

BEL County · est $0.2M

Bid dateThursday, April 23
Awarded toDOUBLE B EXCAVATING LLC$199,388.08
read → connected → answeredcassandri

Project scope

Bid form · ODOT

34ITEMS
  • Drainage24%
  • Earthwork18%
  • Erosion & Landscaping15%
  • Signs12%
  • Maintaining Traffic12%
  • Aggregate & Base9%
  • Other12%

Top items by winning bid

ItemQtyUnit priceExtended%
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $69,400.00 2 $37,650.00 3 $57,400.00 4 $76,000.001 LS$40,000$40k20%
611E07601 18" CONDUIT, TYPE C, AS PER PLAN284 FT$96.5$27k14%
611E13400 30" CONDUIT, TYPE B126 FT$150$19k9%
611E10401 24" CONDUIT, TYPE B, AS PER PLAN163 FT$112.73$18k9%
614E11001 MAINTAINING TRAFFIC, AS PER PLAN1 LS$15,750$16k8%
204E10000 SUBGRADE COMPACTION Section 1 - ROADWAY - Totals Awd $22,835.52 2 $23,058.00 3 $52,230.00 4 $45,782.00266 SY$31.58$8k4%
203E20000 EMBANKMENT254 CY$31$8k4%
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $21,156.58 2 $13,817.00 3 $14,755.50 4 $22,938.206,300 EACH$1$6k3%
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$6,300$6k3%
659E00300 TOPSOIL58 CY$99.57$6k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 14 more items below.

Rank 1Double B Excavating LLC$199kRank 2Ohio-west Virginia Excavating CO$219kRank 3Mason Dixon Energy Services LLC$257kRank 4R C Construction Company And Son INC$382k
ItemQuantityR1Double B Excavating LLCR2Ohio-west Virginia Excavating COR3Mason Dixon Energy Services LLCR4R C Construction Company And Son INC
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $69,400.00 2 $37,650.00 3 $57,400.00 4 $76,000.001 LS$40,000$14,750$12,900$15,000
611E07601 18" CONDUIT, TYPE C, AS PER PLAN284 FT$96.50$142$160$300
611E13400 30" CONDUIT, TYPE B126 FT$150$222$210$400
611E10401 24" CONDUIT, TYPE B, AS PER PLAN163 FT$113$272$170$350
614E11001 MAINTAINING TRAFFIC, AS PER PLAN1 LS$15,750$9,000$28,000$25,000
204E10000 SUBGRADE COMPACTION Section 1 - ROADWAY - Totals Awd $22,835.52 2 $23,058.00 3 $52,230.00 4 $45,782.00266 SY$31.58$3.00$50.00$2.00
203E20000 EMBANKMENT254 CY$31.00$35.00$70.00$75.00
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $21,156.58 2 $13,817.00 3 $14,755.50 4 $22,938.206,300 EACH$1.00$1.00$1.00$1.00
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$6,300$5,000$4,000$16,500
659E00300 TOPSOIL58 CY$99.57$40.00$70.00$75.00
304E20000 AGGREGATE BASE Section 4 - PAVEMENT - Totals Awd $5,459.86 2 $5,605.00 3 $10,620.00 4 $11,800.0059 CY$92.54$95.00$180$200
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$5,250$6,500$6,500$18,500
659E10000 SEEDING AND MULCHING522 SY$9.05$6.00$6.00$20.00
611E99575 MANHOLE, NO. 3, AS PER PLAN Section 3 - DRAINAGE - Totals Awd $73,868.61 2 $133,836.00 3 $118,075.00 4 $222,600.002 EACH$2,126$5,000$4,500$7,500
202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER294 FT$10.71$30.00$50.00$50.00
201E11000 CLEARING AND GRUBBING1 LS$2,625$1,500$5,000$7,500
614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC10 CY$263$300$200$100
611E04400 12" CONDUIT, TYPE B33 FT$63.64$160$105$250
619E16000 FIELD OFFICE, TYPE A2 MNTH$1,050$1,200$3,000$500
601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL3 CY$525$500$250$500
Show all 34 line items
ItemQuantityR1Double B Excavating LLCR2Ohio-west Virginia Excavating COR3Mason Dixon Energy Services LLCR4R C Construction Company And Son INC
202E58100 CATCH BASIN REMOVED2 EACH$131$1,225$450$1,500
202E98100 REMOVAL MISC.: PRIVATE SIGN REMOVED1 EACH$263$300$100$500
202E98100 REMOVAL MISC.: SIGN FOUNDATION REMOVED1 EACH$263$300$450$500
659E00100 SOIL ANALYSIS TEST2 EACH$315$150$100$20.00
659E14000 REPAIR SEEDING AND MULCHING26 SY$18.17$6.00$2.00$0.20
659E20000 COMMERCIAL FERTILIZER0.07 TON$15,000$1,250$650$1,900
659E31000 LIME0.11 ACRE$4,773$150$600$1,500
659E35000 WATER5 MGAL$21.00$1.00$30.00$1.00
602E20000 CONCRETE MASONRY0.6 CY$2,100$4,200$2,500$4,500
611E98504 CATCH BASIN, NO. 2-2C1 EACH$1,575$3,400$4,500$4,000
630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST25.6 FT$51.27$35.00$30.00$25.00
630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION3 EACH$525$260$80.00$275
630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA Section 5 - TRAFFIC CONTROL - Totals Awd $3,937.51 2 $2,196.00 3 $1,328.00 4 $1,865.004 EACH$263$130$80.00$100
616E10000 WATER Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $2,730.00 2 $3,005.00 3 $2,150.00 4 $1,005.005 MGAL$21.00$1.00$30.00$1.00

Project details

Description
BEL-SR 7-00.94
Type of work
Drainage

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →