WIL-SR 34-27.22 Bridge Repair
WIL County · est $0.6M
Bid dateThursday, January 29—
Awarded toVERNON NAGEL INC$576,218
WIL County · est $0.6M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 167 SY | $425 | $71k | 12% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 3,608 SF | $15 | $54k | 9% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 3,608 SF | $12 | $43k | 8% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 3,608 SF | $12 | $43k | 8% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION, 2" THIC | 344 SY | $120 | $41k | 7% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 344 SY | $110 | $38k | 7% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG Section 3 - PAVEMENT - Totals Awd $77,102.50 2 $77,712.10 | 112 CY | $305 | $34k | 6% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 3,608 SF | $9 | $32k | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $49,000.00 2 $74,108.89 | 1 LS | $30,000 | $30k | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 99 CY | $275 | $27k | 5% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Vernon Nagel INC | R2Bcc Ohio INC | % of bid |
|---|---|---|---|---|
| 526E25000 REINFORCED CONCRETE APPROACH SLABS (T=15") | 167 SY | $425 | $479 | 13% |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 3,608 SF | $15.00 | $23.10 | 10% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 3,608 SF | $12.00 | $9.45 | 8% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 3,608 SF | $12.00 | $9.45 | 8% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION, 2" THIC | 344 SY | $120 | $132 | 8% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 344 SY | $110 | $94.64 | 7% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG Section 3 - PAVEMENT - Totals Awd $77,102.50 2 $77,712.10 | 112 CY | $305 | $315 | 6% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 3,608 SF | $9.00 | $9.45 | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $49,000.00 2 $74,108.89 | 1 LS | $30,000 | $60,166 | 6% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 99 CY | $275 | $273 | 5% |
| 202E22900 APPROACH SLAB REMOVED | 134 SY | $200 | $83.00 | 5% |
| 848E50000 HAND CHIPPING | 75 SY | $225 | $201 | 3% |
| 304E20000 AGGREGATE BASE | 125 CY | $125 | $123 | 3% |
| 526E90010 TYPE A INSTALLATION | 64 FT | $175 | $392 | 2% |
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 4 EACH | $2,585 | $2,714 | 2% |
| 209E60200 LINEAR GRADING | 4 STA | $2,500 | $258 | 2% |
| 202E23000 PAVEMENT REMOVED | 250 SY | $34.00 | $14.61 | 2% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC Section 5 - MAINTENANCE OF TRAFFIC - Totals Awd $8,000.00 2 $7,875.00 | 10 CY | $800 | $788 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $7,435 | 1% |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 4 EACH | $1,380 | $1,449 | 1% |
| Item | Quantity | R1Vernon Nagel INC | R2Bcc Ohio INC |
|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 175 FT | $4.00 | $2.10 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 4 EACH | $320 | $336 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $75.00 | $78.75 |
| 204E10000 SUBGRADE COMPACTION | 352 SY | $1.00 | $1.85 |
| 606E15050 GUARDRAIL, TYPE MGS | 175 FT | $21.40 | $22.47 |
| 614E13312 BARRIER REFLECTOR, TYPE 2. | 6 EACH | $15.00 | $15.75 |
| 617E10100 COMPACTED AGGREGATE Section 1 - ROADWAY - Totals Awd $42,227.00 2 $29,068.59 | 8 CY | $175 | $128 |
| 659E14000 REPAIR SEEDING AND MULCHING | 10 SY | $4.75 | $10.50 |
| 659E15000 INTER-SEEDING | 10 SY | $4.00 | $10.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.1 TON | $850 | $1,050 |
| 659E35000 WATER | 1 MGAL | $1.00 | $2.10 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $2,173.50 2 $2,317.10 | 2,000 EACH | $1.00 | $1.00 |
| 407E20000 NON-TRACKING TACK COAT | 37 GAL | $2.50 | $1.05 |
| 621E00100 RPM | 2 EACH | $1,575 | $279 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED Section 4 - TRAFFIC CONTROL - Totals Awd $3,200.00 2 $599.28 | 2 EACH | $25.00 | $20.64 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 100 LB | $1.25 | $1.77 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 10 MNHR | $150 | $105 |
| 514E10000 FINAL INSPECTION REPAIR | 5 EACH | $100 | $158 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 146 FT | $16.00 | $23.59 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 20 SF | $250 | $151 |
| 848E30201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 8 CY | $300 | $368 |
| 848E50100 TEST SLAB | 1 LS | $3,000 | $2,592 |
| 848E50200 FULL-DEPTH REPAIR | 1 CY | $1,000 | $1,460 |
| 630E95000 SIGNING, MISC.: BRIDGE IDENTIFICATION SIGN Section 6 - STRUCTURE OVER 20 FOOT SPAN (WIL-34-27.2 - Totals Awd $394,515.00 2 $410,525.58 | 1 LS | $500 | $158 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $1,500 | $774 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $2,554 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $3,180 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →