SUM-SR 261-00.00/VAR
SUM County · est $4.4M
Bid dateThursday, April 23—
Awarded toKENMORE CONSTRUCTION CO INC$3.56M
SUM County · est $4.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (4032 CY | $245 | $988k | 28% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (3838 CY | $190 | $729k | 20% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2") | 138,100 SY | $1.5 | $207k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $150,000 | $150k | 4% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 57 EACH | $2,000 | $114k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 20,589 GAL | $5 | $103k | 3% |
| 253E01000 PAVEMENT REPAIR (T = 12") | 470 SY | $200 | $94k | 3% |
| 624E10000 MOBILIZATION Section 15 - INCIDENTALS - Totals Awd $281,000.00 2 $549,000.00 3 $504,341.21 4 $383,596.98 5 $735,745.00 | 1 LS | $90,000 | $90k | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 3,646 SF | $20 | $73k | 2% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,000 SY | $35 | $70k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 124 more items below.
| Item | Quantity | R1Kenmore Construction CO INC | R2Shelly Company | R3Karvo Companies INC | R4Shelly & Sands INC | R5Kokosing Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (4032 CY | $245 | $235 | $250 | $265 | $310 | 34% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (3838 CY | $190 | $180 | $215 | $206 | $240 | 25% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2") | 138,100 SY | $1.50 | $1.40 | $2.00 | $1.10 | $1.65 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $150,000 | $400,000 | $225,000 | $244,097 | $460,950 | 5% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 57 EACH | $2,000 | $1,500 | $1,500 | $1,500 | $1,225 | 4% |
| 407E20000 NON-TRACKING TACK COAT | 20,589 GAL | $5.00 | $3.00 | $2.40 | $3.05 | $2.50 | 4% |
| 253E01000 PAVEMENT REPAIR (T = 12") | 470 SY | $200 | $195 | $125 | $300 | $300 | 3% |
| 624E10000 MOBILIZATION Section 15 - INCIDENTALS - Totals Awd $281,000.00 2 $549,000.00 3 $504,341.21 4 $383,596.98 5 $735,745.00 | 1 LS | $90,000 | $100,000 | $235,341 | $100,000 | $227,770 | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 3,646 SF | $20.00 | $25.00 | $15.00 | $37.00 | $15.50 | 3% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,000 SY | $35.00 | $46.00 | $35.00 | $50.00 | $78.00 | 2% |
| 646E10000 EDGE LINE, 4" | 11.28 MILE | $3,118 | $2,500 | $2,500 | $2,500 | $2,500 | 1% |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 19 EACH | $1,800 | $1,300 | $1,300 | $1,300 | $1,225 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN Section 7 - TRAFFIC SIGNALS - Totals Awd $31,000.00 2 $34,500.00 3 $34,500.00 4 $33,000.00 5 $33,000.00 | 20 EACH | $1,550 | $1,725 | $1,725 | $1,650 | $1,650 | 1% |
| 519E12304 PATCHING CONCRETE BRIDGE DECK - TYPE C | 49 SY | $600 | $750 | $806 | $750 | $750 | 1% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 430 FT | $60.00 | $50.00 | $75.00 | $83.00 | $29.15 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 4,894 GAL | $5.00 | $4.00 | $5.25 | $3.50 | $4.00 | 1% |
| 646E10200 CENTER LINE | 5.64 MILE | $3,900 | $4,000 | $4,000 | $4,000 | $4,000 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,500 | $4,000 | $3,000 | $4,000 | $4,300 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 8 EACH | $2,550 | $2,920 | $2,920 | $2,920 | $2,950 | 1% |
| 608E13000 6" CONCRETE WALK | 1,633 SF | $12.00 | $22.00 | $12.00 | $20.00 | $14.50 | 1% |
| Item | Quantity | R1Kenmore Construction CO INC | R2Shelly Company | R3Karvo Companies INC | R4Shelly & Sands INC | R5Kokosing Construction Company INC |
|---|---|---|---|---|---|---|
| 202E23500 WEARING COURSE REMOVED | 683 SY | $8.00 | $16.00 | $1.00 | $15.00 | $4.00 |
| 202E30000 WALK REMOVED | 5,279 SF | $3.00 | $6.30 | $8.00 | $4.40 | $2.50 |
| 202E32000 CURB REMOVED | 88 FT | $5.00 | $20.50 | $35.00 | $25.00 | $24.25 |
| 202E32500 CURB AND GUTTER REMOVED | 430 FT | $6.00 | $23.50 | $45.00 | $20.00 | $16.25 |
| 202E38000 GUARDRAIL REMOVED | 887.5 FT | $2.40 | $2.40 | $2.40 | $2.40 | $2.00 |
| 202E98100 REMOVAL MISC.: BARRIER REFLECTOR | 15 EACH | $8.00 | $5.00 | $5.00 | $5.00 | $12.19 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 28 CY | $30.00 | $28.00 | $25.00 | $100 | $66.87 |
| 209E60200 LINEAR GRADING | 154 STA | $60.00 | $55.00 | $45.00 | $80.00 | $30.00 |
| 209E72000 PREPARING SUBGRADE FOR SHOULDER PAVING | 285 STA | $30.00 | $55.00 | $12.00 | $30.00 | $65.00 |
| 606E13000 GUARDRAIL, TYPE 5 | 400 FT | $20.20 | $21.40 | $21.40 | $21.40 | $22.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 150 FT | $21.40 | $22.80 | $22.80 | $22.80 | $22.00 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 275 FT | $23.60 | $28.60 | $28.60 | $28.60 | $29.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 8 EACH | $1,345 | $1,380 | $1,380 | $1,380 | $1,650 |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 16 EACH | $980 | $1,175 | $1,175 | $1,175 | $1,375 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS Section 1 - ROADWAY - Totals Awd $238,537.00 2 $314,549.70 3 $251,631.00 4 $337,454.60 5 $236,867.71 | 1 LS | $2,000 | $6,500 | $1,000 | $2,000 | $2,500 |
| 659E10000 SEEDING AND MULCHING | 199 SY | $5.00 | $30.00 | $15.00 | $15.00 | $4.00 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $3,995.00 2 $8,970.00 3 $5,985.00 4 $5,985.00 5 $3,796.00 | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 5 EACH | $440 | $2,000 | $2,000 | $2,000 | $1,085 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL Section 3 - DRAINAGE - Totals Awd $117,400.00 2 $97,100.00 3 $97,100.00 4 $97,100.00 5 $76,226.90 | 400 LB | $3.00 | $4.00 | $4.00 | $4.00 | $2.45 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 2,341 FT | $3.85 | $3.00 | $2.50 | $3.60 | $4.24 |
| 253E01000 PAVEMENT REPAIR (T = 10") | 30 SY | $140 | $175 | $100 | $185 | $295 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 28 CY | $60.00 | $60.00 | $25.00 | $100 | $100 |
| 609E26000 CURB, TYPE 6 | 88 FT | $60.00 | $55.00 | $65.00 | $118 | $37.50 |
| 617E10100 COMPACTED AGGREGATE Section 4 - PAVEMENT - Totals Awd $2,280,902.85 2 $2,165,066.00 3 $2,395,849.60 4 $2,424,630.05 5 $2,818,403.84 | 351 CY | $55.00 | $80.00 | $100 | $85.00 | $40.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 5 - WATER WORK - Totals Awd $16,000.00 2 $8,800.00 3 $8,800.00 4 $8,800.00 5 $4,759.60 | 8 EACH | $2,000 | $1,100 | $1,100 | $1,100 | $595 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 4 EACH | $12.00 | $12.50 | $12.50 | $12.50 | $13.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 30 EACH | $12.90 | $15.00 | $15.00 | $15.00 | $13.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 90 FT | $38.98 | $12.50 | $12.50 | $20.00 | $12.50 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 24 SF | $42.61 | $40.00 | $40.00 | $27.50 | $40.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 12 EACH | $16.68 | $25.00 | $25.00 | $15.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 12 EACH | $22.24 | $25.00 | $25.00 | $20.00 | $25.00 |
| 644E00100 EDGE LINE, 4" | 3.17 MILE | $4,600 | $3,500 | $3,500 | $3,500 | $3,500 |
| 644E00200 LANE LINE, 4" | 0.13 MILE | $2,300 | $1,500 | $1,500 | $1,500 | $1,500 |
| 644E00300 CENTER LINE | 2.42 MILE | $5,200 | $4,950 | $4,950 | $4,950 | $4,950 |
| 644E00400 CHANNELIZING LINE, 8" | 2,527 FT | $1.70 | $1.75 | $1.75 | $1.75 | $1.75 |
| 644E00500 STOP LINE | 404 FT | $8.00 | $6.75 | $6.75 | $6.75 | $6.75 |
| 644E00630 CROSSWALK LINE, 24" | 2,940 FT | $5.00 | $6.75 | $6.75 | $6.75 | $6.75 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 343 FT | $8.00 | $6.75 | $6.75 | $6.75 | $6.75 |
| 644E00900 ISLAND MARKING | 456 SF | $7.00 | $6.75 | $6.75 | $6.75 | $6.75 |
| 644E01300 LANE ARROW | 63 EACH | $120 | $100 | $100 | $100 | $100 |
| 644E60000 GREEN COLORED PAVEMENT FOR BIKE LANES | 1,440 SF | $11.00 | $12.50 | $12.50 | $12.50 | $12.50 |
| 646E10300 CHANNELIZING LINE, 8" | 514 FT | $1.60 | $1.75 | $1.75 | $1.75 | $1.75 |
| 646E10400 STOP LINE | 108 FT | $11.00 | $12.50 | $12.50 | $12.50 | $12.50 |
| 646E10520 CROSSWALK LINE, 24" | 100 FT | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 160 FT | $8.00 | $12.50 | $12.50 | $12.50 | $12.50 |
| 646E20300 LANE ARROW | 13 EACH | $160 | $200 | $200 | $200 | $200 |
| 690E98000 SPECIAL - BICYCLE LANE ARROW MARKING, 647 PAINT | 63 EACH | $220 | $165 | $165 | $165 | $165 |
| 690E98000 SPECIAL - BICYCLE LANE BIKE SYMBOL, 647 PAINT Section 6 - TRAFFIC CONTROL - Totals Awd $181,639.22 2 $168,146.00 3 $168,146.00 4 $168,341.00 5 $168,088.00 | 63 EACH | $310 | $250 | $250 | $250 | $250 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $100 | $120 | $125 | $92.00 | $130 |
| 614E12460 WORK ZONE MARKING SIGN | 26 EACH | $58.15 | $65.00 | $65.00 | $65.00 | $65.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $200 | $125 | $300 | $450 | $125 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $800 | $875 | $875 | $875 | $800 |
| 614E20100 WORK ZONE LANE LINE, CLASS I, 4", 642 PAINT | 0.26 MILE | $700 | $1,000 | $1,000 | $1,000 | $1,000 |
| 614E20550 WORK ZONE LANE LINE, CLASS III, 4", 642 PAINT | 0.13 MILE | $675 | $1,000 | $1,000 | $1,000 | $1,000 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 16.82 MILE | $900 | $1,250 | $1,250 | $1,250 | $1,250 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 8.41 MILE | $875 | $1,250 | $1,250 | $1,250 | $1,250 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 14.45 MILE | $600 | $425 | $425 | $425 | $425 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 6,082 FT | $0.60 | $0.75 | $0.75 | $0.75 | $0.75 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 3,041 FT | $0.55 | $0.75 | $0.75 | $0.75 | $0.75 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 1,024 FT | $3.20 | $3.50 | $3.50 | $3.50 | $3.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT Section 8 - MAINTENANCE OF TRAFFIC - Totals Awd $64,682.95 2 $74,577.00 3 $78,477.00 4 $78,837.00 5 $74,477.00 | 512 FT | $3.00 | $3.50 | $3.50 | $3.50 | $3.50 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $3,000 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 3.00") | 245 SY | $20.00 | $30.00 | $2.00 | $50.00 | $35.00 |
| 407E13900 TACK COAT, 702.13 | 20 GAL | $10.00 | $6.00 | $2.40 | $5.00 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 15 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $2.50 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 60 FT | $40.00 | $50.00 | $30.00 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (9 CY | $325 | $280 | $250 | $250 | $310 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (15 CY | $330 | $560 | $215 | $250 | $240 |
| 512E33010 TYPE 3 WATERPROOFING | 225 SY | $50.00 | $50.00 | $52.58 | $50.00 | $50.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 83 FT | $10.00 | $10.00 | $21.09 | $10.00 | $10.00 |
| 519E12304 PATCHING CONCRETE BRIDGE DECK - TYPE C | 15 SY | $1,000 | $1,000 | $806 | $1,000 | $1,000 |
| 530E00800 SPECIAL - STRUCTURES: CONCRETE SPALL REMOVAL WITH Section 9 - STRUCTURE REPAIR (SUM-261-0.070) - Totals Awd $60,605.00 2 $66,515.00 3 $38,585.47 4 $66,475.75 5 $63,150.50 | 10 SY | $1,500 | $1,500 | $378 | $1,500 | $1,500 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $3,000 | $3,000 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE(T=2.00?) | 105 SY | $12.00 | $3.00 | $2.00 | $13.00 | $1.75 |
| 407E20000 NON-TRACKING TACK COAT | 17 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $2.50 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 70 FT | $40.00 | $50.00 | $28.95 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (3 CY | $500 | $280 | $250 | $250 | $310 |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 Section 10 - STRUCTURE REPAIR (SUM-261-2.205) - Totals Awd $10,080.00 2 $8,396.00 3 $4,962.30 4 $9,251.85 5 $8,376.25 | 448 (3 CY | $450 | $230 | $215 | $195 | $240 |
| 202E23500 WEARING COURSE REMOVED (T = 5.00") | 650 SY | $20.00 | $12.00 | $5.00 | $30.00 | $55.00 |
| 407E13900 TACK COAT, 702.13 | 54 GAL | $10.00 | $6.00 | $2.40 | $5.00 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 39 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $2.50 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 76 FT | $30.00 | $50.00 | $28.95 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (19 CY | $300 | $280 | $250 | $250 | $310 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (74 CY | $220 | $205 | $215 | $250 | $240 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 11 SY | $50.00 | $50.00 | $67.35 | $50.00 | $50.00 |
| 512E33010 TYPE 3 WATERPROOFING | 650 SY | $30.00 | $30.00 | $52.58 | $30.00 | $30.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 263 FT | $10.00 | $10.00 | $21.06 | $10.00 | $10.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN Section 11 - STRUCTURE REPAIR (SUM-261-4.185) - Totals Awd $75,745.00 2 $70,086.00 3 $79,211.08 4 $84,493.95 5 $101,036.10 | 85 SF | $175 | $175 | $146 | $175 | $175 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $3,000 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 5.00") | 396 SY | $20.00 | $20.00 | $5.00 | $30.00 | $35.00 |
| 407E13900 TACK COAT, 702.13 | 33 GAL | $10.00 | $6.00 | $2.40 | $5.00 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 24 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $2.50 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 56 FT | $45.00 | $50.00 | $28.95 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (12 CY | $320 | $280 | $250 | $250 | $310 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (46 CY | $200 | $260 | $215 | $250 | $240 |
| 512E33010 TYPE 3 WATERPROOFING | 396 SY | $40.00 | $40.00 | $52.58 | $40.00 | $40.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 141 FT | $10.00 | $10.00 | $21.06 | $10.00 | $10.00 |
| 519E12304 PATCHING CONCRETE BRIDGE DECK - TYPE C | 18 SY | $1,000 | $1,000 | $806 | $1,000 | $1,000 |
| 530E00800 SPECIAL - STRUCTURES: CONCRETE SPALL REMOVAL WITH Section 12 - STRUCTURE REPAIR (SUM-261-4.567) - Totals Awd $69,800.00 2 $72,060.00 3 $58,099.64 4 $75,168.20 5 $77,342.20 | 5 SY | $1,500 | $1,500 | $378 | $1,500 | $1,500 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $3,000 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 3.50") | 262 SY | $20.00 | $20.00 | $5.00 | $30.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED (T = 5.00") | 134 SY | $20.00 | $25.00 | $5.00 | $30.00 | $55.00 |
| 407E13900 TACK COAT, 702.13 | 33 GAL | $10.00 | $6.00 | $2.48 | $5.00 | $3.72 |
| 407E20000 NON-TRACKING TACK COAT | 24 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $3.72 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 54 FT | $45.00 | $50.00 | $28.95 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (12 CY | $300 | $280 | $250 | $250 | $310 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (35 CY | $200 | $305 | $215 | $250 | $240 |
| 512E33010 TYPE 3 WATERPROOFING | 396 SY | $40.00 | $40.00 | $52.58 | $40.00 | $40.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 165 FT | $10.00 | $10.00 | $21.06 | $10.00 | $10.00 |
| 530E00800 SPECIAL - STRUCTURES: CONCRETE SPALL REMOVAL WITH Section 13 - STRUCTURE REPAIR (SUM-261-4.746) - Totals Awd $86,410.00 2 $97,835.00 3 $83,046.82 4 $98,808.20 5 $103,812.04 | 10 SY | $1,500 | $1,500 | $378 | $1,500 | $1,500 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $3,000 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 3.50") | 191 SY | $20.00 | $20.00 | $5.00 | $30.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED (T = 5.00") | 117 SY | $20.00 | $30.00 | $5.00 | $30.00 | $55.00 |
| 407E13900 TACK COAT, 702.13 | 26 GAL | $10.00 | $6.00 | $2.40 | $5.00 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 20 GAL | $10.00 | $3.00 | $2.40 | $3.05 | $2.50 |
| 409E30000 SAWING AND SEALING ASPHALT CONCRETE PAVEMENT JOINT | 62 FT | $40.00 | $50.00 | $28.95 | $50.00 | $50.00 |
| 424E14000 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B | 448 (11 CY | $300 | $280 | $250 | $250 | $310 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (28 CY | $200 | $355 | $215 | $250 | $240 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 4 SY | $100 | $100 | $67.35 | $100 | $100 |
| 512E33010 TYPE 3 WATERPROOFING | 308 SY | $45.00 | $45.00 | $52.58 | $45.00 | $45.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 97 FT | $10.00 | $10.00 | $21.06 | $10.00 | $10.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN Section 14 - STRUCTURE REPAIR (SUM-261-4.922) - Totals Awd $42,230.00 2 $47,896.00 3 $36,396.06 4 $46,511.00 5 $50,718.40 | 30 SF | $200 | $200 | $146 | $200 | $200 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $15,000 | $21,000 | $12,000 | $18,225 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $10,000 | $5,000 | $3,500 | $3,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →