MAR-US 23-16.75/18.15
MAR County · est $1.6M
Bid dateThursday, July 12—
MAR County · est $1.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 114 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Shelly & Sands INC | R3Mosser Construction INC | R4Complete General Construction Company | R5Rietschlin Construction INC | % of bid |
|---|---|---|---|---|---|---|---|
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 233 CY | $950 | $885 | $875 | $950 | $870 | 19% |
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 233 CY | $950 | $885 | $875 | $950 | $870 | 19% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22, 9.0" DEPTH | 354 CY | $251 | $300 | $250 | $300 | $253 | 7% |
| 202E11203 |
| Item | Quantity | R1Eagle Bridge CO | R2Shelly & Sands INC | R3Mosser Construction INC | R4Complete General Construction Company | R5Rietschlin Construction INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,000 | $1,000 | $8,500 | $7,000 | $10,000 |
| 202E38000 GUARDRAIL REMOVED | 1,390 FT | $1.60 | $1.60 | $1.60 | $1.60 | $2.75 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 4 EACH | $216 | $110 | $215 | $215 | $313 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $62,500 |
| $38,000 |
| $88,000 |
| $90,000 |
| $54,800 |
| 5% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $62,500 | $38,003 | $88,000 | $95,000 | $54,800 | 5% |
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 171 CY | $336 | $440 | $335 | $440 | $380 | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 54,183 LB | $1.00 | $1.10 | $1.25 | $0.95 | $1.00 | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 54,165 LB | $1.00 | $1.10 | $1.25 | $0.95 | $1.00 | 5% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $50,000 | $80,000 | $95,000 | $42,000 | $75,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $40,000 | $40,000 | $100,000 | 3% |
| 614E18002 MAINTAINING TRAFFIC, MISC.: RUMBLE STRIP MILLED/FI | 1 LS | $35,000 | $20,500 | $27,000 | $15,000 | $37,400 | 3% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 16 EACH | $2,050 | $2,050 | $2,045 | $2,045 | $2,250 | 3% |
| 526E10010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 130 SY | $230 | $311 | $225 | $270 | $220 | 3% |
| 526E10010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 130 SY | $230 | $311 | $225 | $270 | $220 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 1,507 FT | $16.84 | $18.00 | $16.80 | $16.80 | $18.50 | 2% |
| 511E43210 CLASS QC1 CONCRETE, PIER | 25 CY | $1,000 | $1,020 | $950 | $800 | $700 | 2% |
| 511E43210 CLASS QC1 CONCRETE, PIER | 25 CY | $1,000 | $1,020 | $950 | $800 | $700 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $25,000 | $10,000 | $14,000 | $14,000 | $20,000 | 2% |
| 202E23000 PAVEMENT REMOVED, (FULL-DEPTH) | 996 SY | $25.00 | $15.00 | $24.00 | $11.00 | $11.50 | 2% |
| 304E20000 AGGREGATE BASE, 6.0" DEPTH | 238 CY | $100 | $65.00 | $80.00 | $80.00 | $64.00 | 2% |
| 16 EACH |
| $75.17 |
| $150 |
| $75.00 |
| $75.00 |
| $313 |
| 202E47800 IMPACT ATTENUATOR REMOVED | 2 EACH | $351 | $480 | $350 | $350 | $350 |
| 202E75000 FENCE REMOVED | 200 FT | $2.21 | $5.50 | $2.00 | $2.20 | $2.50 |
| 203E10000 EXCAVATION | 287.1 CY | $40.00 | $21.00 | $16.00 | $24.00 | $25.00 |
| 203E20000 EMBANKMENT | 75.8 CY | $40.00 | $12.00 | $22.00 | $26.00 | $36.00 |
| 209E60500 LINEAR GRADING | 0.45 MILE | $2,506 | $13,500 | $3,500 | $7,000 | $6,500 |
| 601E21060 TIED CONCRETE BLOCK MAT, TYPE 2 | 40 SY | $55.00 | $65.00 | $70.00 | $100 | $65.00 |
| 605E31100 AGGREGATE DRAINS | 110 FT | $10.00 | $13.00 | $22.00 | $17.00 | $14.00 |
| 606E15550 GUARDRAIL, BARRIER DESIGN, TYPE MGS | 88 FT | $29.87 | $21.00 | $29.80 | $29.80 | $33.00 |
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 4 EACH | $2,125 | $2,200 | $2,120 | $2,120 | $2,332 |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 8 EACH | $797 | $1,000 | $795 | $795 | $875 |
| 606E60012 IMPACT ATTENUATOR, TYPE 1 (BIDIRECTIONAL) | 4 EACH | $4,285 | $2,600 | $4,725 | $4,275 | $4,703 |
| 607E15100 FENCE, TYPE 47RA | 200 FT | $21.65 | $21.19 | $21.60 | $21.60 | $23.75 |
| 609E24510 CURB, TYPE 4-C | 120 FT | $50.00 | $37.00 | $24.00 | $33.00 | $27.50 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 4 EACH | $67.66 | $52.99 | $67.50 | $67.50 | $74.25 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE-WAY | 24 EACH | $7.27 | $8.00 | $7.25 | $7.25 | $8.00 |
| 659E00300 TOPSOIL | 475 CY | $5.00 | $35.00 | $22.00 | $35.00 | $21.00 |
| 659E10000 SEEDING AND MULCHING | 3,757 SY | $2.50 | $0.90 | $1.60 | $1.89 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.56 TON | $1,250 | $725 | $390 | $650 | $700 |
| 659E31000 LIME | 0.9 ACRE | $10.00 | $165 | $111 | $100 | $110 |
| 659E35000 WATER | 0.05 MGAL | $100 | $1.00 | $10.00 | $1.00 | $25.00 |
| 832E30000 EROSION CONTROL | 4,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 76 FT | $17.50 | $25.00 | $22.00 | $21.00 | $22.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 4 EACH | $275 | $430 | $275 | $250 | $380 |
| 204E10000 SUBGRADE COMPACTION | 1,396 SY | $10.00 | $2.25 | $6.00 | $2.75 | $1.50 |
| 204E45000 PROOF ROLLING | 16 HOUR | $75.00 | $165 | $175 | $100 | $200 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" DEPTH | 813 SY | $10.02 | $12.00 | $10.00 | $12.00 | $9.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3.0" DEPTH | 603 SY | $10.02 | $15.00 | $10.00 | $15.00 | $15.50 |
| 407E10000 TACK COAT | 721 GAL | $1.00 | $1.95 | $1.00 | $1.95 | $2.25 |
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 36 CY | $336 | $440 | $335 | $440 | $440 |
| 617E10100 COMPACTED AGGREGATE, TYPE A | 120 CY | $75.00 | $50.00 | $75.00 | $50.00 | $70.00 |
| 618E40100 RUMBLE STRIPS, (ASPHALT CONCRETE) | 3,091 FT | $5.00 | $1.50 | $1.45 | $2.00 | $2.00 |
| 621E00100 RPM | 81 EACH | $43.10 | $40.00 | $38.00 | $58.00 | $59.00 |
| 621E00300 RPM REFLECTOR | 81 EACH | $5.01 | $5.30 | $5.00 | $16.00 | $7.25 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 81 EACH | $10.00 | $12.00 | $15.00 | $16.00 | $22.00 |
| 644E00104 EDGE LINE, 6", (WHITE) | 0.52 MILE | $8,500 | $4,400 | $5,500 | $5,500 | $4,900 |
| 644E00104 EDGE LINE, 6", (YELLOW) | 0.04 MILE | $8,500 | $4,400 | $15,000 | $15,000 | $4,900 |
| 644E00200 LANE LINE, 4", (WHITE) | 1.62 MILE | $5,500 | $2,000 | $3,245 | $3,245 | $2,200 |
| 646E10010 EDGE LINE, 6", (WHITE) | 0.14 MILE | $70,000 | $16,500 | $35,000 | $35,000 | $18,000 |
| 646E10010 EDGE LINE, 6", (YELLOW) | 0.06 MILE | $70,000 | $16,500 | $35,000 | $35,000 | $18,000 |
| 646E10100 LANE LINE, 4", (WHITE) | 0.14 MILE | $47,500 | $9,000 | $47,950 | $47,950 | $9,900 |
| 646E20710 SPECIAL - AIR SPEED ZONE MARKING | 4 EACH | $250 | $230 | $900 | $900 | $250 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 12 HOUR | $100 | $72.00 | $60.00 | $65.00 | $72.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 960 FT | $2.00 | $0.95 | $5.00 | $2.00 | $1.00 |
| 614E12350 WORK ZONE IMPACT ATTENUATOR | 4 EACH | $1,804 | $2,100 | $1,965 | $1,800 | $2,090 |
| 614E12500 REPLACEMENT SIGN | 4 EACH | $150 | $120 | $150 | $155 | $128 |
| 614E12600 REPLACEMENT DRUM | 12 EACH | $50.00 | $38.00 | $40.00 | $55.00 | $41.25 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 34 EACH | $6.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 34 EACH | $10.00 | $18.00 | $11.00 | $11.00 | $15.25 |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 12 SNMT | $1,250 | $1,100 | $1,050 | $1,050 | $990 |
| 614E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 12 SNMT | $1,000 | $750 | $850 | $850 | $770 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 5.46 MILE | $1,108 | $750 | $1,105 | $1,105 | $814 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 6,240 FT | $0.75 | $0.85 | $0.75 | $0.75 | $0.88 |
| 622E41000 PORTABLE BARRIER, 32" | 1,680 FT | $14.00 | $12.50 | $14.00 | $15.00 | $17.50 |
| 202E22900 APPROACH SLAB REMOVED | 133 SY | $50.00 | $27.87 | $56.00 | $40.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED | 133 SY | $10.00 | $29.00 | $48.00 | $17.00 | $10.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $20,000 | $11,600 | $9,000 | $20,000 | $30,500 |
| 503E21100 UNCLASSIFIED EXCAVATION | 20 CY | $250 | $105 | $35.00 | $225 | $900 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 340 EACH | $15.00 | $22.00 | $25.00 | $15.00 | $20.00 |
| 511E40510 CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS | 1 CY | $4,500 | $6,800 | $4,000 | $3,800 | $2,600 |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 11 CY | $1,250 | $2,400 | $900 | $1,200 | $1,100 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 444 SY | $9.02 | $9.50 | $14.00 | $9.00 | $10.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 65 SF | $5.00 | $6.00 | $6.00 | $9.00 | $7.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 89 SF | $7.00 | $6.00 | $7.00 | $10.00 | $6.00 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 331 SF | $9.00 | $9.00 | $16.00 | $13.00 | $10.50 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 25 CY | $95.00 | $133 | $85.00 | $100 | $105 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 97 FT | $8.00 | $8.00 | $10.00 | $9.00 | $12.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 30 FT | $15.00 | $8.00 | $11.00 | $18.00 | $24.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 6 SF | $250 | $370 | $350 | $140 | $153 |
| 526E90010 TYPE A INSTALLATION | 78 FT | $110 | $206 | $140 | $146 | $130 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 6 EACH | $7.27 | $8.00 | $7.25 | $7.25 | $8.00 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 32 CF | $350 | $328 | $320 | $321 | $396 |
| 518E12500 SCUPPER, MISC.:PVC DECK DRAIN | 7 EACH | $200 | $418 | $200 | $195 | $232 |
| 202E22900 APPROACH SLAB REMOVED | 133 SY | $50.00 | $26.50 | $56.00 | $40.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED | 133 SY | $10.00 | $28.00 | $48.00 | $17.00 | $10.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $20,000 | $10,509 | $9,000 | $26,000 | $30,500 |
| 503E21100 UNCLASSIFIED EXCAVATION | 20 CY | $250 | $105 | $35.00 | $225 | $900 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 340 EACH | $15.00 | $21.00 | $25.00 | $15.00 | $20.00 |
| 511E40510 CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS | 1 CY | $4,500 | $6,800 | $4,000 | $3,800 | $2,600 |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 11 CY | $1,250 | $2,500 | $900 | $1,200 | $1,100 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 444 SY | $9.02 | $9.50 | $14.00 | $9.00 | $10.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 65 SF | $5.00 | $5.00 | $6.00 | $9.00 | $7.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 80 SF | $7.00 | $7.00 | $7.00 | $10.00 | $7.00 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 331 SF | $9.00 | $9.00 | $16.00 | $13.00 | $12.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 25 CY | $95.00 | $133 | $85.00 | $100 | $105 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 97 FT | $8.00 | $8.00 | $10.00 | $9.00 | $12.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 30 FT | $15.00 | $8.00 | $11.00 | $18.00 | $24.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 14 SF | $250 | $355 | $200 | $125 | $135 |
| 526E90010 TYPE A INSTALLATION | 78 FT | $110 | $206 | $140 | $146 | $130 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, ONE-WAY | 6 EACH | $7.27 | $8.00 | $7.25 | $7.25 | $8.00 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 32 CF | $350 | $328 | $320 | $321 | $396 |
| 518E12500 SCUPPER, MISC.:PVC DECK DRAIN | 7 EACH | $200 | $418 | $200 | $195 | $232 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $20,000 | $23,000 | $20,000 | $20,000 | $17,500 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $6,500 | $6,200 | $5,000 | $2,800 | $10,700 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,648 LB | $1.80 | $1.05 | $1.25 | $1.03 | $2.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 919 SY | $9.02 | $9.50 | $15.00 | $9.00 | $10.00 |
| 513E90000 STRUCTURAL STEEL, MISC.:REPAIRS UNDER 50 POUNDS | 751 LB | $18.00 | $13.00 | $10.00 | $16.50 | $17.50 |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 236 SF | $60.00 | $101 | $60.00 | $100 | $132 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 236 SF | $40.00 | $92.00 | $60.00 | $90.00 | $55.00 |
| 530E01300 SPECIAL - STRUCTURES: BRIDGE JOINT CLEANING | 84 FT | $12.03 | $12.50 | $30.00 | $12.00 | $13.25 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 347 SY | $25.06 | $25.50 | $9.00 | $25.00 | $27.50 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $20,000 | $23,000 | $20,000 | $20,000 | $17,500 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $6,500 | $6,200 | $5,000 | $2,800 | $10,700 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,648 LB | $1.80 | $1.05 | $1.25 | $1.03 | $2.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 919 SY | $9.02 | $9.50 | $15.00 | $9.00 | $10.00 |
| 513E90000 STRUCTURAL STEEL, MISC.:REPAIRS UNDER 50 POUNDS | 603 LB | $18.00 | $15.00 | $10.00 | $18.50 | $17.50 |
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 236 SF | $60.00 | $101 | $60.00 | $100 | $132 |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 236 SF | $40.00 | $92.00 | $60.00 | $90.00 | $55.00 |
| 530E01300 SPECIAL - STRUCTURES: BRIDGE JOINT CLEANING | 84 FT | $12.03 | $12.50 | $30.00 | $12.00 | $13.25 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 347 SY | $25.06 | $25.50 | $9.00 | $25.00 | $27.50 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,500 | $17,000 | $17,000 | $4,000 | $6,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 233 CY | $950 | $221k | 12% |
| 511E32212 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 233 CY | $950 | $221k | 12% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22, 9.0" DEPTH | 354 CY | $250.58 | $89k | 5% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $62,500 | $63k | 3% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $62,500 | $63k | 3% |
| 442E20000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 171 CY | $335.77 | $57k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 54,183 LB | $1 | $54k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 54,165 LB | $1 | $54k | 3% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $50,000 | $50k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 2% |