MOT-US 40-16.98
MOT County · est $0.5M
Bid dateThursday, July 12—
MOT County · est $0.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 9.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 36 more items below.
| Item | Quantity | R1Complete General Construction Company | R2Bridge Specialists INC | R3Eagle Bridge CO | % of bid |
|---|---|---|---|---|---|
| 848E20001 SURFACE PREPARATION USING HYDRODEMOLITION, AS PER | 2,204 SY | $75.00 | $61.00 | $105 | 38% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 1,762 SY | $45.00 | $43.85 | $20.00 | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $31,000 | $21,450 | $50,000 | 7% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 442 SY | $45.00 | $43.85 | $20.00 | 5% |
| 848E50000 HAND CHIPPING | 202 SY | $70.00 | $65.00 |
| Item | Quantity | R1Complete General Construction Company | R2Bridge Specialists INC | R3Eagle Bridge CO |
|---|---|---|---|---|
| 203E20000 EMBANKMENT | 4 CY | $75.00 | $100 | $250 |
| 659E14000 REPAIR SEEDING AND MULCHING | 173 SY | $1.00 | $0.45 | $1.50 |
| 659E15000 INTER-SEEDING | 173 SY | $0.01 | $0.10 | $1.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.78 TON | $750 | $505 | $1,250 |
| 659E31000 LIME | 0.72 ACRE | $200 | $100 | $10.00 |
| 659E35000 WATER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $100 |
| 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 902 SY | $15.00 | $4.00 | $12.00 | 3% |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 1,762 SY | $6.25 | $10.40 | $8.00 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 38 CY | $286 | $300 | $287 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $47,000 | $40,000 | 2% |
| 848E30201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 51 CY | $189 | $260 | $200 | 2% |
| 516E31011 2" DEEP JOINT SEALER, AS PER PLAN | 319 FT | $25.50 | $26.00 | $15.00 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $8,000 | $22,800 | $35,000 | 2% |
| 659E00300 TOPSOIL | 384 CY | $20.00 | $50.00 | $5.00 | 2% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 381 SY | $20.00 | $31.20 | $20.00 | 2% |
| 514E27700 FIELD PAINTING, MISC.: ZINC RICH PRIMER | 99 SF | $75.00 | $13.00 | $85.00 | 2% |
| 518E12500 SCUPPER, MISC.: CLEANOUT | 14 EACH | $500 | $65.00 | $50.00 | 2% |
| 530E01100 SPECIAL - STRUCTURES: APPROACH SLAB VOID REPAIR | 3 CY | $2,000 | $1,300 | $1,750 | 1% |
| 659E10000 SEEDING AND MULCHING | 3,463 SY | $1.45 | $1.65 | $1.50 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $31,499 | $12,500 | 1% |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $1,500 | $2,000 | $1,500 | 1% |
| 20 MGAL |
| $1.00 |
| $1.00 |
| $10.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,795 | $2,000 | $2,500 |
| 832E30000 EROSION CONTROL | 1,300 EACH | $1.00 | $1.00 | $1.00 |
| 407E10000 TACK COAT | 78 GAL | $4.75 | $2.00 | $4.76 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 4 EACH | $130 | $135 | $135 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 534 FT | $4.75 | $3.50 | $3.46 |
| 625E25400 CONDUIT, 2", 725.04 | 53 FT | $40.00 | $33.50 | $33.53 |
| 625E25920 CONDUIT, MISC.: REMOVAL OF EXISTING LIGHTING CONDU | 53 FT | $6.00 | $38.00 | $37.79 |
| 625E29000 TRENCH | 53 FT | $10.00 | $16.00 | $15.84 |
| 625E36000 PLASTIC CAUTION TAPE | 53 FT | $1.50 | $0.15 | $0.14 |
| 625E39520 PULL BOX CLEANED | 2 EACH | $100 | $110 | $110 |
| 625E75550 DISTRIBUTION CABLE REMOVED | 534 FT | $1.50 | $1.25 | $1.25 |
| 625E75801 DISCONNECT CIRCUIT, AS PER PLAN | 2 EACH | $150 | $404 | $404 |
| 646E10000 EDGE LINE, 4" | 0.13 MILE | $17,000 | $17,530 | $17,570 |
| 646E10100 LANE LINE, 4" | 0.13 MILE | $9,500 | $16,850 | $16,889 |
| 646E10200 CENTER LINE | 0.07 MILE | $30,000 | $19,135 | $19,179 |
| 646E10300 CHANNELIZING LINE, 8" | 97 FT | $9.00 | $5.00 | $5.01 |
| 646E20300 LANE ARROW | 2 EACH | $505 | $500 | $501 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $85.00 | $75.00 | $125 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 1 SNMT | $1,000 | $2,400 | $2,406 |
| 614E20550 WORK ZONE LANE LINE, CLASS III, 4", 642 PAINT | 0.13 MILE | $5,155 | $5,155 | $5,167 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.07 MILE | $5,415 | $5,415 | $5,427 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 0.13 MILE | $5,270 | $5,270 | $5,282 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 97 FT | $0.50 | $5.00 | $0.50 |
| 614E30400 WORK ZONE ARROW, CLASS I, 740.06, TYPE I | 1 EACH | $200 | $200 | $200 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $1,500 | $1,300 | $2,500 |
| 513E95030 STRUCTURAL STEEL, MISC.: REPLACE FIELD SPLICE BOLT | 1 EACH | $1,000 | $2,925 | $250 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 10 SF | $150 | $130 | $375 |
| 848E50100 TEST SLAB | 1 LS | $500 | $1,300 | $2,250 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 50 SY | $50.00 | $32.50 | $100 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $1,000 | $6,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 848E20001 SURFACE PREPARATION USING HYDRODEMOLITION, AS PER | 2,204 SY | $75 | $165k | 36% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 1,762 SY | $45 | $79k | 17% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $31,000 | $31k | 7% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 442 SY | $45 | $20k | 4% |
| 848E50000 HAND CHIPPING | 202 SY | $70 | $14k | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 902 SY | $15 | $14k | 3% |
| 848E50320 EXISTING CONCRETE OVERLAY REMOVED, 1 3/4" THICK | 1,762 SY | $6.25 | $11k | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 38 CY | $286 | $11k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 2% |
| 848E30201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 51 CY | $189 | $10k | 2% |