PRE-Hueston Wds SP Resfce FY19
PRE County · est $0.7M
Bid dateThursday, November 8—
PRE County · est $0.7M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 14 more items below.
| Item | Quantity | R1Roberts Paving INC | R2Barrett Paving Materials INC | R3John R Jurgensen Company | % of bid |
|---|---|---|---|---|---|
| AA2 823E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | 1,680 CY | $184 | $205 | $208 | 43% |
| 253E02000 PAVEMENT REPAIR | 802 CY | $189 | $275 | $571 | 21% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (0.25" | 38,490 SY | $1.68 | $2.15 | $2.35 | 9% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (1.00" | 19,219 SY | $1.78 | $3.75 | $2.14 | 5% |
| 407E10000 TACK COAT | 5,443 GAL | $5.80 | $3.00 | $5.69 |
| Item | Quantity | R1Roberts Paving INC | R2Barrett Paving Materials INC | R3John R Jurgensen Company |
|---|---|---|---|---|
| 202E30800 TRAFFIC ISLAND REMOVED | 12 SY | $199 | $65.00 | $95.00 |
| 202E32000 CURB REMOVED | 56 FT | $45.00 | $16.00 | $35.00 |
| 608E10000 4" CONCRETE WALK | 100 SF | $22.00 | $11.00 | $16.61 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 153 FT | $16.45 | $14.45 | $14.45 |
| 630E80100 SIGN, FLAT SHEET | 34 SF | $27.75 | $24.75 | $24.75 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,500 | $35,000 | $42,890 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $16,250 | $20,000 | $40,000 | 2% |
| 644E01200 PARKING LOT STALL MARKING | 7,807 FT | $1.52 | $1.55 | $1.50 | 2% |
| 644E00100 EDGE LINE, 4" | 4.49 MILE | $2,585 | $2,475 | $2,460 | 2% |
| 644E00300 CENTER LINE | 2.06 MILE | $5,149 | $5,000 | $4,920 | 1% |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 6 MILE | $1,401 | $2,000 | $1,785 | 1% |
| 254E01600 PATCHING PLANED SURFACE | 589 SY | $13.29 | $1.00 | $3.06 | 1% |
| 608E52001 CURB RAMP, AS PER PLAN | 257 SF | $28.75 | $24.00 | $37.61 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,200 | $10,500 | $3,332 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,520 | $12,000 | $6,432 | 1% |
| 644E00701 TRANSVERSE/DIAGONAL LINE, AS PER PLAN | 755 FT | $8.62 | $8.00 | $7.50 | 1% |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 4.49 MILE | $1,015 | $1,100 | $1,000 | 1% |
| 202E53010 SPECIAL - PARKING BLOCK REMOVED AND RESET | 30 EACH | $135 | $90.00 | $131 | 1% |
| 202E30000 WALK REMOVED | 357 SF | $11.00 | $8.00 | $7.00 | 1% |
| 609E54001 6" CONCRETE TRAFFIC ISLAND, AS PER PLAN | 12 SY | $272 | $245 | $600 | 0% |
| 4 EACH |
| $24.00 |
| $12.00 |
| $12.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $24.00 | $12.00 | $12.00 |
| 644E00400 CHANNELIZING LINE, 8" | 43 FT | $2.65 | $2.50 | $2.25 |
| 644E00500 STOP LINE | 211 FT | $7.92 | $8.00 | $7.50 |
| 644E01300 LANE ARROW | 2 EACH | $125 | $125 | $120 |
| 644E01600 HANDICAP SYMBOL MARKING | 18 EACH | $108 | $100 | $95.00 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 2.06 MILE | $1,582 | $1,600 | $1,500 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 211 FT | $6.00 | $5.00 | $4.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 2 EACH | $75.00 | $65.00 | $60.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| AA2 823E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | 1,680 CY | $183.55 | $308k | 42% |
| 253E02000 PAVEMENT REPAIR | 802 CY | $189 | $152k | 20% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (0.25" | 38,490 SY | $1.68 | $65k | 9% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (1.00" | 19,219 SY | $1.78 | $34k | 5% |
| 407E10000 TACK COAT | 5,443 GAL | $5.8 | $32k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,500 | $23k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $16,250 | $16k | 2% |
| 644E01200 PARKING LOT STALL MARKING | 7,807 FT | $1.52 | $12k | 2% |
| 644E00100 EDGE LINE, 4" | 4.49 MILE | $2,585 | $12k | 2% |
| 644E00300 CENTER LINE | 2.06 MILE | $5,149 | $11k | 1% |