MAD-IR 70-08.62 Major Rehab
MAD County · est $52M
Bid dateThursday, August 30—
MAD County · est $52M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 27 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3John R Jurgensen Company | R4Anthony Allega Cement Contractor INC | % of bid |
|---|---|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT (OPTION A) | 1 LS | $23,580,000 | $23,200,000 | $19,989,814 | $25,844,247 | 49% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $8,200,000 | $9,000,000 | $16,675,260 | $10,093,795 | 17% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $4,500,000 | $7,525,000 | $7,500,183 | $7,383,364 | 9% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $3,460,000 | $3,850,000 | $3,828,708 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3John R Jurgensen Company | R4Anthony Allega Cement Contractor INC |
|---|---|---|---|---|---|
| 832E15001 STORM WATER POLLUTION PREVENTION PLAN, AS PER PLAN | 1 LS | $30,000 | $30,000 | $30,000 | $30,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $21,000 | $32,000 | $15,152 | $32,612 |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT (COMPLETE) FOR INTERSE | 1 LS | $25,200 | $35,500 | $25,180 | $87,144 |
| 630E99000 SPECIAL - SIGNS AND SUPPORTS | 1 LS | $100,000 | $150,000 | $72,479 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $4,402,607 |
| 7% |
| 255E10501 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 5,000 SY | $325 | $255 | $210 | $281 | 3% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $1,533,000 | $760,000 | $709,000 | $1,214,525 | 3% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $1,200,000 | $1,200,000 | $1,200,000 | $1,200,000 | 2% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $1,000,000 | $508,000 | $472,700 | $738,913 | 2% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 600,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $500,000 | $315,000 | $118,100 | $86,445 | 1% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $300,000 | $335,000 | $434,732 | $783,811 | 1% |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $300,000 | $295,000 | $212,950 | $307,642 | 1% |
| 809E99000 SPECIAL - ITS INSTALL 3 ITS CAMERAS, COMPLETE | 1 LS | $280,000 | $290,000 | $224,530 | $275,441 | 1% |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $275,000 | $510,000 | $273,581 | $272,277 | 1% |
| 530E99040 SPECIAL - STRUCTURES (MAD-70-1556L) | 1 LS | $260,000 | $500,000 | $310,000 | $467,820 | 1% |
| 530E99040 SPECIAL - STRUCTURES(MAD-70-1556R) | 1 LS | $260,000 | $500,000 | $310,000 | $467,820 | 1% |
| 619E16020 FIELD OFFICE, TYPE C | 26 MNTH | $9,000 | $3,200 | $2,479 | $6,333 | 0% |
| 640E99000 SPECIAL - PAVEMENT MARKING | 1 LS | $207,000 | $210,000 | $297,506 | $195,795 | 0% |
| 530E99040 SPECIAL - STRUCTURES (MAD-70-1217L) | 1 LS | $150,000 | $350,000 | $155,000 | $273,460 | 0% |
| 530E99040 SPECIAL - STRUCTURES(MAD-70-1217R) | 1 LS | $150,000 | $300,000 | $157,000 | $273,460 | 0% |
| $453,605 |
| 809E99000 SPECIAL - ITS ATR, SIGNAL ADJUSTMENTS | 1 LS | $1,000 | $500 | $12,516 | $1,896 |
| 517E76300 RAILING, MISC.:PARAPET REPAIR | 20 FT | $350 | $463 | $605 | $311 |
| 530E99040 SPECIAL - STRUCTURES (MAD-70-1263) | 1 LS | $50,000 | $75,000 | $75,000 | $67,800 |
| 530E99040 SPECIAL - STRUCTURES (MAD-70-1386) | 1 LS | $40,000 | $75,000 | $60,000 | $54,240 |
| 530E00400 SPECIAL - STRUCTURES (BRIDGE DECK PATCHING MAD-70 | 125,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 517E76300 RAILING, MISC.:PARAPET REPAIR | 40 FT | $350 | $245 | $460 | $311 |
| 848E50000 HAND CHIPPING | 15.5 SY | $300 | $65.00 | $75.00 | $294 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 152.5 SY | $350 | $45.00 | $50.00 | $141 |
| 848E50200 FULL-DEPTH REPAIR | 0.5 CY | $4,300 | $975 | $2,000 | $3,390 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 8.5 CY | $230 | $160 | $200 | $220 |
| 530E00400 SPECIAL - STRUCTURES (BRIDGE DECK PATCHING MAD-70 | 125,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 848E50000 HAND CHIPPING | 15.5 SY | $300 | $65.00 | $75.00 | $294 |
| 848E50340 REMOVAL OF DEBONDED OR DETERIORATED EXISTING VARIA | 152.5 SY | $350 | $45.00 | $50.00 | $141 |
| 848E50200 FULL-DEPTH REPAIR | 0.5 CY | $4,300 | $975 | $2,000 | $3,390 |
| 848E30200 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 8.5 CY | $230 | $160 | $200 | $220 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $10,000 | $27,500 | $36,300 | $48,828 |
| 690E20020 SPECIAL - FIELD SURVEYS | 1 LS | $40,000 | $101,000 | $88,800 | $73,242 |
| 690E20030 SPECIAL - UTILITY COORDINATION AND RELOCATION | 1 LS | $50,000 | $60,000 | $58,600 | $4,068 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $73,000 | $85,000 | $250,000 | $146,484 |
| 100E99010 SPECIAL - PROFESSIONAL LIABILITY INSURANCE | 1 LS | $1,000 | $31,500 | $1,097 | $5,000 |
| 107E99000 SPECIAL - UTILITY COORDINATION | 1 LS | $10,000 | $31,000 | $5,487 | $9,922 |
| 108E99000 SPECIAL - CPM PROGRESS SCHEDULE | 1 LS | $10,100 | $45,000 | $25,601 | $7,978 |
| 111E10000 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 1 LS | $6,500 | $6,500 | $6,500 | $6,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT (OPTION A) | 1 LS | $23,580,000 | $23.6M | 48% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $8,200,000 | $8.20M | 17% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $4,500,000 | $4.50M | 9% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $3,460,000 | $3.46M | 7% |
| 255E10501 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 5,000 SY | $325 | $1.63M | 3% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $1,533,000 | $1.53M | 3% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $1,200,000 | $1.20M | 2% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $1,000,000 | $1.00M | 2% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 600,000 EACH | $1 | $600k | 1% |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $500,000 | $500k | 1% |