MOE-SR 556-04.15
MOE County · est $0.5M
Bid dateThursday, September 13—
MOE County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 25 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Suburban Maintenance & Construction | R5Great Lakes Construction CO | R6Dennison Bridge INC | R7R C Construction Company And Son | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X176 | 1,240 FT | $118 | $97.00 | $107 | $98.00 | $120 | $120 | $140 | 29% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,220 FT | $63.00 | $86.00 | $75.00 | $50.00 | $70.00 | $105 | $140 | 15% |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Suburban Maintenance & Construction | R5Great Lakes Construction CO | R6Dennison Bridge INC | R7R C Construction Company And Son |
|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,800 | $2,500 | $4,000 | $12,000 | $4,000 | $5,000 | $15,000 |
| 202E53100 MAILBOX REMOVED | 1 EACH | $65.00 | $75.00 | $73.00 | $50.00 | $50.00 | $100 | $200 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER |
| 610 FT |
| $94.00 |
| $105 |
| $112 |
| $130 |
| $50.00 |
| $125 |
| $140 |
| 11% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $43,000 | $15,310 | $30,000 | $25,000 | $30,000 | $55,000 | $50,000 | 9% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 133 CY | $205 | $241 | $253 | $290 | $290 | $325 | $250 | 5% |
| 511E81300 CONCRETE, MISC.:8"X24"X66" PRECAST CONCRETE LAGGIN | 90 EACH | $300 | $275 | $283 | $300 | $350 | $350 | $375 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $18,226 | $20,000 | $25,000 | $35,000 | $115,000 | $20,000 | $30,000 | 4% |
| 304E20000 AGGREGATE BASE | 177 CY | $90.00 | $95.00 | $101 | $65.00 | $75.00 | $120 | $85.00 | 3% |
| 622E41000 PORTABLE BARRIER, 32" | 1,080 FT | $10.00 | $14.00 | $13.00 | $16.00 | $12.00 | $16.00 | $25.00 | 2% |
| 518E21100 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 102 CY | $105 | $175 | $120 | $65.00 | $100 | $120 | $75.00 | 2% |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 778 SY | $13.00 | $17.50 | $9.50 | $10.00 | $30.00 | $28.00 | $20.00 | 2% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 26 CY | $375 | $425 | $400 | $350 | $275 | $450 | $750 | 2% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (38 CY | $235 | $281 | $295 | $300 | $300 | $425 | $300 | 2% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 4 EACH | $2,000 | $1,900 | $1,900 | $2,100 | $1,875 | $2,200 | $2,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $3,793 | $3,500 | $10,000 | $6,000 | $7,000 | $30,000 | 1% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 27 CY | $265 | $461 | $484 | $450 | $450 | $525 | $460 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 250 FT | $25.00 | $25.00 | $27.00 | $24.00 | $26.90 | $26.00 | $30.00 | 1% |
| 203E20000 EMBANKMENT | 274 CY | $18.00 | $20.00 | $15.00 | $15.00 | $20.00 | $25.00 | $25.00 | 1% |
| 203E10000 EXCAVATION | 246 CY | $20.00 | $30.00 | $21.00 | $15.00 | $40.00 | $25.00 | $25.00 | 1% |
| 204E10000 SUBGRADE COMPACTION | 862 SY | $5.00 | $4.00 | $2.50 | $4.00 | $2.00 | $4.00 | $2.00 | 1% |
| 1 LS |
| $1,200 |
| $2,000 |
| $4,500 |
| $8,000 |
| $3,000 |
| $5,000 |
| $25,000 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,025 | $1,000 | $1,050 | $1,500 | $925 | $950 | $1,500 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $100 | $120 | $126 | $250 | $150 | $300 | $300 |
| 601E21050 TIED CONCRETE BLOCK MAT, TYPE 1 | 2 SY | $150 | $115 | $248 | $500 | $265 | $250 | $750 |
| 659E10000 SEEDING AND MULCHING | 1,141 SY | $3.00 | $1.80 | $1.50 | $3.00 | $2.90 | $4.00 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.1 TON | $500 | $830 | $2,772 | $500 | $461 | $1,000 | $1,200 |
| 659E31000 LIME | 0.24 ACRE | $105 | $150 | $735 | $100 | $100 | $250 | $800 |
| 659E35000 WATER | 6 MGAL | $1.00 | $1.00 | $3.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $200 | $250 | $321 | $150 | $350 | $300 | $250 |
| 407E20000 NON-TRACKING TACK COAT | 109 GAL | $7.00 | $3.00 | $3.50 | $4.00 | $4.00 | $4.00 | $20.00 |
| 621E00100 RPM | 9 EACH | $300 | $90.00 | $270 | $400 | $335 | $350 | $550 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 9 EACH | $15.00 | $20.00 | $5.00 | $50.00 | $9.70 | $5.00 | $50.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BI-DIRECTIONAL | 5 EACH | $25.00 | $7.00 | $7.50 | $50.00 | $12.00 | $10.00 | $10.00 |
| 642E00094 EDGE LINE, 6" | 0.1 MILE | $8,000 | $5,000 | $5,000 | $5,000 | $5,000 | $7,500 | $12,500 |
| 642E00290 CENTER LINE | 0.05 MILE | $20,000 | $10,000 | $10,000 | $10,000 | $10,000 | $12,500 | $35,000 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $2,500 | $17,500 | $5,500 | $25,000 | $5,500 | $5,000 | $10,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 24 EACH | $12.00 | $6.00 | $53.00 | $50.00 | $50.00 | $10.00 | $20.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 24 EACH | $20.00 | $10.00 | $53.00 | $50.00 | $50.00 | $20.00 | $20.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 157 FT | $8.00 | $3.00 | $7.50 | $8.00 | $15.00 | $10.00 | $20.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 35 FT | $8.00 | $20.00 | $16.00 | $8.00 | $25.00 | $25.00 | $20.00 |
| 524E95200 DRILLED SHAFTS, MISC.EXTENSION | 1 LS | $4,000 | $2,750 | $758 | $5,000 | $5,000 | $2,500 | $4,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,500 | $6,400 | $5,000 | $5,000 | $10,000 | $7,000 | $20,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:SOLDIER PILES, W24X176 | 1,240 FT | $118 | $146k | 27% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,220 FT | $63 | $77k | 14% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 610 FT | $94 | $57k | 11% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $43,000 | $43k | 8% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 133 CY | $205 | $27k | 5% |
| 511E81300 CONCRETE, MISC.:8"X24"X66" PRECAST CONCRETE LAGGIN | 90 EACH | $300 | $27k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $18,226 | $18k | 3% |
| 304E20000 AGGREGATE BASE | 177 CY | $90 | $16k | 3% |
| 622E41000 PORTABLE BARRIER, 32" | 1,080 FT | $10 | $11k | 2% |
| 518E21100 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 102 CY | $105 | $11k | 2% |