WAR-SR 741-13.82
WAR County · est $0.9M
Bid dateThursday, February 27—
WAR County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 20 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 2,510 CY | $159 | $167 | 43% |
| 644E50200 PAVEMENT MARKING, MISC.:CROSSWALK LINE, AS PER PLA | 8,072 SF | $18.50 | $18.50 | 16% |
| 253E02000 PAVEMENT REPAIR | 400 CY | $295 | $300 | 13% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 2 | 45,065 SY | $1.93 | $1.98 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,602 | $23,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $9,000 | 2% |
| 644E19000 SHARED LANE MARKING | 32 EACH | $475 | $475 | 2% |
| 441E00100 |
| Item | Quantity | R1John R Jurgensen Company | R2Barrett Paving Materials INC |
|---|---|---|---|
| 254E01600 PATCHING PLANED SURFACE | 451 SY | $4.20 | $1.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 183 EACH | $20.15 | $10.00 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 1 EACH | $3,770 | $1,770 |
| 632E27200 LOOP DETECTOR TIE IN | 1 EACH | $125 | $125 |
| 644E00400 CHANNELIZING LINE, 8" | 592 FT | $1.15 | $1.15 |
| 644E00500 STOP LINE | 430 FT | $4.65 | $4.65 |
| 644E00600 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,870 CY |
| $6.50 |
| $12.00 |
| 1% |
| 407E20000 NON-TRACKING TACK COAT | 3,380 GAL | $3.50 | $3.25 | 1% |
| 304E20000 AGGREGATE BASE | 300 CY | $37.80 | $85.00 | 1% |
| 644E01630 BIKE LANE SYMBOL MARKING | 25 EACH | $425 | $425 | 1% |
| 644E00300 CENTER LINE | 2.4 MILE | $3,595 | $3,595 | 1% |
| 644E00104 EDGE LINE, 6" | 2.27 MILE | $3,495 | $3,495 | 1% |
| 203E10000 EXCAVATION | 300 CY | $21.65 | $40.00 | 1% |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 1,364 FT | $4.50 | $4.50 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,925 | $2,576 | 1% |
| 621E00100 RPM | 167 EACH | $32.95 | $32.95 | 1% |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 3.6 MILE | $1,480 | $1,480 | 1% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 1.8 MILE | $2,860 | $2,860 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,642 | $2,000 | 0% |
| 648 FT |
| $2.65 |
| $2.65 |
| 644E00900 ISLAND MARKING | 60 SF | $2.50 | $2.50 |
| 644E01110 SCHOOL SYMBOL MARKING, 96" | 6 EACH | $400 | $400 |
| 644E01200 PARKING LOT STALL MARKING | 1,128 FT | $1.00 | $1.00 |
| 644E01300 LANE ARROW | 23 EACH | $75.00 | $75.00 |
| 644E01400 WORD ON PAVEMENT, 72" | 2 EACH | $95.00 | $95.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 30 HOUR | $65.00 | $68.00 |
| 614E12460 WORK ZONE MARKING SIGN | 4 EACH | $90.00 | $90.00 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.8 MILE | $1,655 | $1,655 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 592 FT | $0.55 | $0.55 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 592 FT | $0.50 | $0.50 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 164 FT | $2.50 | $2.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 164 FT | $2.40 | $2.40 |
| 616E10000 WATER | 0.25 MGAL | $475 | $50.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 2,510 CY | $159.15 | $399k | 42% |
| 644E50200 PAVEMENT MARKING, MISC.:CROSSWALK LINE, AS PER PLA | 8,072 SF | $18.5 | $149k | 16% |
| 253E02000 PAVEMENT REPAIR | 400 CY | $295.4 | $118k | 12% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 2 | 45,065 SY | $1.93 | $87k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,602 | $41k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 644E19000 SHARED LANE MARKING | 32 EACH | $475 | $15k | 2% |
| 441E00100 ANTI-SEGREGATION EQUIPMENT | 1,870 CY | $6.5 | $12k | 1% |
| 407E20000 NON-TRACKING TACK COAT | 3,380 GAL | $3.5 | $12k | 1% |
| 304E20000 AGGREGATE BASE | 300 CY | $37.8 | $11k | 1% |