| Item | Quantity | R1Axis Civil Construction LLC | R2Complete General Construction Company | R3Shelly & Sands INC | R4Trucco Construction CO INC | R5Newcomer Concrete Services INC | % of bid |
|---|---|---|---|---|---|---|---|
| 608E98000 WALKWAY, MISC.: 4" STAMPED CONCRETE | 11,525 SF | $14.50 | $12.00 | $12.90 | $14.25 | $15.00 | 23% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 13,870 SF | $7.95 | $7.50 | $9.25 | $10.65 | $8.00 | 15% |
| 625E10481 LIGHT POLE, DECORATIVE, AS PER PLAN | 16 EACH | $5,000 | $4,000 | $3,800 | $4,909 | $5,400 | 11% |
| Item | Quantity | R1Axis Civil Construction LLC | R2Complete General Construction Company | R3Shelly & Sands INC | R4Trucco Construction CO INC | R5Newcomer Concrete Services INC |
|---|---|---|---|---|---|---|
| 202E23010 PAVEMENT REMOVED, ASPHALT | 25 SY | $12.00 | $10.00 | $37.00 | $71.15 | $30.00 |
| 203E10000 EXCAVATION | 37 CY | $45.00 | $32.00 | $110 | $583 | $55.00 |
| 204E10000 SUBGRADE COMPACTION | 241 SY | $2.00 | $5.00 | $1.50 | $1.65 | $24.75 |
| 204E13000 EXCAVATION OF SUBGRADE | 20 CY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,994 FT |
| $27.50 |
| $26.00 |
| $22.00 |
| $22.90 |
| $27.00 |
| 8% |
| 202E30000 WALK REMOVED | 27,132 SF | $1.90 | $2.50 | $1.90 | $1.60 | $4.05 | 7% |
| 625E10500 LIGHT POLE, MISC.: DECORATIVE POLE ONLY | 11 EACH | $4,100 | $4,100 | $4,000 | $4,038 | $4,440 | 6% |
| 625E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, TYPE 4, 4000K, | 16 EACH | $1,582 | $1,900 | $1,990 | $1,520 | $1,672 | 4% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 241 SY | $88.00 | $85.00 | $108 | $118 | $75.00 | 3% |
| 625E29000 TRENCH | 1,887 FT | $11.00 | $10.00 | $10.50 | $10.02 | $11.02 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $38,000 | $40,000 | $44,500 | $80,000 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $20,000 | $26,000 | $50,000 | 3% |
| 625E98000 LIGHTING, MISC.: RECONSTRUCTED EXISTING FOUNDATION | 27 EACH | $660 | $700 | $690 | $650 | $715 | 3% |
| 202E32000 CURB REMOVED | 1,184 FT | $12.00 | $12.00 | $18.00 | $11.35 | $10.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 1,178 SY | $9.00 | $8.00 | $11.30 | $12.15 | $30.00 | 1% |
| 625E23000 NO. 4 AWG 600 VOLT DISTRIBUTION CABLE | 5,634 FT | $1.75 | $2.00 | $1.75 | $1.70 | $1.87 | 1% |
| 625E25408 CONDUIT, 2", 725.051 | 1,887 FT | $5.00 | $14.00 | $15.15 | $4.83 | $5.31 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $9,000 | $7,500 | $10,600 | $2,000 | $5,000 | 1% |
| 608E52000 CURB RAMP | 433 SF | $20.00 | $25.00 | $33.00 | $31.65 | $14.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,500 | $6,000 | $4,500 | $5,952 | $9,000 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $10,000 | $5,100 | $4,444 | $3,575 | 1% |
| $30.00 |
| $45.00 |
| $67.00 |
| $90.75 |
| $80.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B, 712.09, TYPE A | 20 CY | $85.00 | $52.00 | $102 | $122 | $65.00 |
| 608E53020 DETECTABLE WARNING | 96 SF | $45.00 | $35.00 | $19.00 | $35.60 | $25.00 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $5,000 | $3,000 | $2,120 | $1,145 | $2,500 |
| 690E98000 SPECIAL - GAS VALVE BOX ADJUSTED TO GRADE | 17 EACH | $165 | $225 | $350 | $60.00 | $200 |
| 832E30000 EROSION CONTROL | 1,300 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E00100 4" CONDUIT, TYPE B | 200 FT | $10.00 | $25.00 | $16.00 | $14.60 | $15.00 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 2 EACH | $700 | $725 | $640 | $908 | $500 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 200 FT | $5.00 | $3.49 | $4.25 | $2.00 | $2.00 |
| 304E20000 AGGREGATE BASE | 5 CY | $250 | $125 | $125 | $295 | $65.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 2 CY | $800 | $250 | $290 | $678 | $1,650 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 13 EACH | $190 | $235 | $350 | $196 | $150 |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 33 EACH | $190 | $135 | $350 | $196 | $200 |
| 625E00450 CONNECTION, FUSED PULL APART | 32 EACH | $67.00 | $100 | $96.00 | $65.35 | $71.88 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 16 EACH | $28.00 | $100 | $96.00 | $27.40 | $30.14 |
| 625E23410 NO. 12 AWG POLE AND BRACKET CABLE | 800 FT | $6.50 | $1.75 | $1.60 | $6.28 | $6.90 |
| 625E36000 PLASTIC CAUTION TAPE | 1,887 FT | $0.20 | $0.75 | $1.00 | $0.16 | $0.20 |
| 625E75400 LIGHT POLE REMOVED | 26 EACH | $255 | $250 | $255 | $250 | $275 |
| 625E75506 LUMINAIRE REMOVED | 32 EACH | $102 | $40.00 | $43.00 | $100 | $110 |
| 625E75800 DISCONNECT CIRCUIT | 5 EACH | $102 | $325 | $319 | $100 | $110 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 84 FT | $12.00 | $18.75 | $20.00 | $12.00 | $22.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 13 EACH | $115 | $195 | $207 | $115 | $165 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 12 EACH | $65.00 | $75.00 | $80.00 | $65.00 | $73.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $25.00 | $10.00 | $10.60 | $25.00 | $44.00 |
| 630E87520 REMOVAL OF POLE MOUNTED SIGN AND REERECTION | 13 EACH | $60.00 | $135 | $144 | $60.00 | $73.00 |
| 616E10000 WATER | 1 MGAL | $1.00 | $3,000 | $830 | $150 | $750 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E98000 WALKWAY, MISC.: 4" STAMPED CONCRETE | 11,525 SF | $14.5 | $167k | 22% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 13,870 SF | $7.95 | $110k | 14% |
| 625E10481 LIGHT POLE, DECORATIVE, AS PER PLAN | 16 EACH | $5,000 | $80k | 10% |
| 609E24510 CURB, TYPE 4-C | 1,994 FT | $27.5 | $55k | 7% |
| 202E30000 WALK REMOVED | 27,132 SF | $1.9 | $52k | 7% |
| 625E10500 LIGHT POLE, MISC.: DECORATIVE POLE ONLY | 11 EACH | $4,100 | $45k | 6% |
| 625E27551 LUMINAIRE, DECORATIVE, AS PER PLAN, TYPE 4, 4000K, | 16 EACH | $1,582 | $25k | 3% |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 241 SY | $88 | $21k | 3% |
| 625E29000 TRENCH | 1,887 FT | $11 | $21k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,000 | $20k | 3% |