PER-CR 3-03.37 (Roseville Br)
PER County · est $0.9M
Bid dateThursday, March 26—
PER County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 9.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 43 more items below.
| Item | Quantity | R1Complete General Construction Company | R2George J Igel & CO INC | R3Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|
| 515E12110 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $39,000 | $42,000 | $38,578 | 37% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 101 CY | $640 | $600 | $750 | 8% |
| 511E46210 CLASS QC1 CONCRETE, RETAINING/WINGWALL INCLUDING F | 67 CY | $800 | $900 | $1,300 | 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 95 CY | $550 | $700 | $900 | 6% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $52,000 |
| Item | Quantity | R1Complete General Construction Company | R2George J Igel & CO INC | R3Shelly & Sands INC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $9,000 | $5,000 | $5,000 |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 230 SY | $17.50 | $15.00 | $12.00 |
| 202E98300 REMOVAL MISC.: DRIVEWAY REMOVED | 37 SY | $22.40 | $30.00 | $40.00 |
| 203E10000 EXCAVATION | 32 CY | $35.00 | $40.00 | $25.00 |
| 203E20000 EMBANKMENT | 15 CY | $35.00 | $30.00 | $25.00 |
| 204E10000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $118,000 |
| $60,600 |
| 6% |
| 638E98600 WATER WORK, MISC.: 6" WATERLINE | 425 FT | $120 | $125 | $80.00 | 6% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $40,000 | $15,000 | $45,000 | 5% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 107 SY | $260 | $250 | $310 | 3% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 193.5 FT | $135 | $122 | $130 | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 22,484 LB | $1.15 | $1.10 | $1.08 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $20,000 | $38,000 | $35,200 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $40,000 | $40,000 | 2% |
| 507E00150 STEEL PILES HP10X42, DRIVEN | 480 FT | $35.00 | $20.00 | $35.00 | 2% |
| 526E90010 TYPE A INSTALLATION | 71 FT | $225 | $160 | $180 | 2% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $15,000 | $10,000 | $20,000 | 2% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 122 CY | $110 | $75.00 | $75.00 | 2% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 640 FT | $20.00 | $22.00 | $21.00 | 2% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 118 CY | $100 | $85.00 | $100 | 1% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 40 CY | $270 | $270 | $313 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $10,000 | $5,000 | $3,800 | 1% |
| 454 SY |
| $5.00 |
| $6.00 |
| $4.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 1.25") | 206 SY | $30.00 | $15.00 | $30.00 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 37.5 FT | $21.20 | $21.20 | $22.50 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 2 EACH | $2,360 | $2,360 | $2,250 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $985 | $985 | $1,000 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,090 | $2,090 | $1,950 |
| 690E98000 SPECIAL - ADJUST CLEANOUT TO GRADE | 1 EACH | $5,000 | $300 | $800 |
| 659E10000 SEEDING AND MULCHING | 656 SY | $3.70 | $5.00 | $3.80 |
| 659E20000 COMMERCIAL FERTILIZER | 0.1 TON | $600 | $600 | $600 |
| 659E31000 LIME | 0.14 ACRE | $70.00 | $70.00 | $70.00 |
| 659E35000 WATER | 4 MGAL | $1.00 | $1.00 | $1.00 |
| 304E20000 AGGREGATE BASE | 47 CY | $80.00 | $90.00 | $90.00 |
| 407E10000 TACK COAT (0.06 GAL./SQ. YD.) | 50 GAL | $5.00 | $5.00 | $2.00 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 13 CY | $80.00 | $90.00 | $115 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 15 CY | $286 | $286 | $323 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (10 CY | $274 | $274 | $290 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (17 CY | $274 | $274 | $285 |
| 638E07800 6" GATE VALVE AND VALVE BOX | 5 EACH | $1,055 | $1,200 | $900 |
| 638E10200 6" FIRE HYDRANT | 1 EACH | $5,000 | $3,000 | $4,300 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 11 EACH | $8.00 | $8.00 | $9.00 |
| 630E01100 GROUND MOUNTED SUPPORT, NO. 1 POST | 12 FT | $30.00 | $30.00 | $13.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $10.00 | $10.00 | $20.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $65.00 | $65.00 | $55.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $10.00 | $10.00 | $20.00 |
| 642E00300 CENTER LINE, TYPE 1 | 0.05 MILE | $22,590 | $38,210 | $23,000 |
| 616E10000 WATER | 10 MGAL | $60.00 | $30.00 | $35.00 |
| 690E98400 SPECIAL - MISC.: WORK INVOLVING ASBESTOS CONTAINI | 1 LS | $7,000 | $15,000 | $4,000 |
| 202E38500 BRIDGE RAILING REMOVED | 234 FT | $10.00 | $5.00 | $15.00 |
| 511E33500 SEMI-INTEGRAL DIAPHRAGM GUIDE | 2 EACH | $5,000 | $1,300 | $2,700 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 204 SY | $24.50 | $24.50 | $24.50 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 32 EACH | $150 | $160 | $105 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 186 FT | $14.00 | $20.00 | $14.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 135 FT | $10.00 | $11.00 | $8.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 34 FT | $15.00 | $15.00 | $8.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,000 | $6,000 | $5,600 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $9,000 | $5,000 | $4,000 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $2,000 | $2,700 | $3,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $9,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12110 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 8 EACH | $39,000 | $312k | 32% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 101 CY | $640 | $65k | 7% |
| 511E46210 CLASS QC1 CONCRETE, RETAINING/WINGWALL INCLUDING F | 67 CY | $800 | $54k | 5% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 95 CY | $550 | $52k | 5% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $52,000 | $52k | 5% |
| 638E98600 WATER WORK, MISC.: 6" WATERLINE | 425 FT | $120 | $51k | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $40,000 | $40k | 4% |
| 526E10000 REINFORCED CONCRETE APPROACH SLABS (T=12") | 107 SY | $260 | $28k | 3% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 193.5 FT | $135 | $26k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 22,484 LB | $1.15 | $26k | 3% |