STA-/STA Culverts FY2020
STA County · est $0.4M
Bid dateThursday, May 21—
STA County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 45 more items below.
| Item | Quantity | R1Rudzik Excavating INC | R2Stanley Miller Construction Company | R3Eclipse CO LLC | R4S E T INC | R5Glenn O Hawbaker INC | R6Lockhart Concrete CO | R7Americon Industrial Services LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 611E28001 84" CONDUIT, TYPE A, AS PER PLAN, 706.02, 707.02 ( | 67 FT | $840 | $410 | $445 | $561 | $275 | $800 | $850 | 20% |
| 611E96550 FIELD PAVING OF EXISTING PIPE (MAH-014T-0007) | 255 FT | $170 | $88.00 | $121 | $342 | $300 | $137 | $145 | 15% |
| 624E10000 |
| Item | Quantity | R1Rudzik Excavating INC | R2Stanley Miller Construction Company | R3Eclipse CO LLC | R4S E T INC | R5Glenn O Hawbaker INC | R6Lockhart Concrete CO | R7Americon Industrial Services LLC |
|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING (STA-619-01.97) | 1 LS | $500 | $1,610 | $2,000 | $1,000 | $1,500 | $3,000 | $7,500 |
| 202E11004 STRUCTURE REMOVED | 1 EACH | $4,000 | $3,378 | $7,026 | $6,140 | $11,000 | $29,000 | $7,500 |
| 202E20010 HEADWALL REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $24,406 |
| $23,234 |
| $42,200 |
| $52,000 |
| $46,000 |
| $29,000 |
| $65,000 |
| 9% |
| 611E10401 24" CONDUIT, TYPE B, AS PER PLAN, 707.33 | 57 FT | $400 | $96.10 | $403 | $306 | $90.00 | $200 | $300 | 8% |
| 611E99621 MANHOLE, NO. 5, AS PER PLAN | 1 EACH | $18,500 | $9,463 | $9,596 | $7,611 | $7,000 | $3,000 | $25,000 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 84 CY | $220 | $245 | $437 | $286 | $240 | $300 | $300 | 7% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 31 CY | $330 | $378 | $610 | $363 | $350 | $375 | $600 | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 120 SY | $85.00 | $112 | $75.00 | $55.00 | $107 | $200 | $100 | 4% |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 8 SNMT | $1,190 | $945 | $1,040 | $935 | $920 | $900 | $990 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,855 | $53,161 | $18,692 | $7,860 | $5,000 | $34,700 | $20,000 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 263 FT | $30.00 | $18.89 | $24.00 | $20.00 | $20.00 | $19.00 | $17.00 | 3% |
| 201E11000 CLEARING AND GRUBBING (MAH-14T-0007) | 1 LS | $7,500 | $1,610 | $4,000 | $3,500 | $1,500 | $3,000 | $7,500 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,700 | $4,000 | $9,250 | $7,200 | $130 | $29,000 | $10,000 | 2% |
| 602E20000 CONCRETE MASONRY | 5 CY | $1,250 | $866 | $871 | $2,200 | $1,000 | $10.00 | $2,000 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $60.00 | $75.00 | $68.50 | $65.00 | $50.00 | $50.00 | $75.00 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=3") | 365 SY | $16.00 | $15.56 | $12.50 | $17.00 | $15.00 | $5.00 | $45.00 | 2% |
| 201E11000 CLEARING AND GRUBBING (STA-241-13.32) | 1 LS | $5,500 | $1,610 | $13,000 | $6,000 | $5,000 | $3,000 | $7,500 | 2% |
| 203E20000 EMBANKMENT | 104 CY | $50.00 | $30.00 | $11.50 | $15.00 | $80.00 | $20.00 | $50.00 | 2% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 255 FT | $20.00 | $34.00 | $61.50 | $55.00 | $54.00 | $90.00 | $80.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,891 | $10,912 | $15,000 | $4,000 | $2,500 | $17,500 | $15,000 | 2% |
| 3 EACH |
| $1,085 |
| $503 |
| $1,294 |
| $1,840 |
| $800 |
| $500 |
| $500 |
| 202E23000 PAVEMENT REMOVED | 251 SY | $9.00 | $13.68 | $14.00 | $14.00 | $40.00 | $10.00 | $20.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 53 FT | $30.00 | $7.61 | $52.50 | $5.00 | $30.00 | $20.00 | $50.00 |
| 202E38000 GUARDRAIL REMOVED | 365 FT | $3.00 | $2.25 | $1.50 | $3.00 | $8.00 | $2.50 | $1.50 |
| 203E10000 EXCAVATION | 50 CY | $50.00 | $23.00 | $12.00 | $20.00 | $60.00 | $20.00 | $50.00 |
| 203E35120 GRANULAR MATERIAL, TYPE C | 40 CY | $98.00 | $59.00 | $125 | $63.00 | $85.00 | $40.00 | $100 |
| 204E10000 SUBGRADE COMPACTION | 251 SY | $3.00 | $1.00 | $2.00 | $2.00 | $4.00 | $2.00 | $3.00 |
| 204E50000 GEOTEXTILE FABRIC | 60 SY | $11.50 | $5.50 | $3.00 | $3.00 | $6.00 | $5.00 | $10.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 1 EACH | $2,500 | $2,445 | $3,885 | $2,420 | $4,000 | $2,200 | $2,200 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $2,500 | $1,111 | $1,287 | $1,100 | $1,800 | $950 | $1,000 |
| 601E10000 RIPRAP | 13 SY | $305 | $316 | $61.00 | $300 | $150 | $120 | $400 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 8 CY | $250 | $279 | $97.00 | $140 | $300 | $125 | $125 |
| 616E10000 WATER | 1 MGAL | $1.00 | $1.00 | $59.50 | $50.00 | $1,600 | $50.00 | $1.00 |
| 659E00300 TOPSOIL | 128 CY | $27.00 | $44.00 | $60.00 | $67.00 | $80.00 | $30.00 | $70.00 |
| 659E10000 SEEDING AND MULCHING | 1,158 SY | $3.00 | $4.40 | $3.50 | $4.00 | $2.00 | $1.00 | $6.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 58 SY | $2.00 | $2.00 | $0.50 | $1.00 | $11.00 | $1.00 | $6.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.15 TON | $100 | $800 | $662 | $600 | $2,500 | $650 | $610 |
| 659E31000 LIME | 0.24 ACRE | $100 | $200 | $52.50 | $100 | $1,800 | $500 | $75.00 |
| 659E35000 WATER | 6 MGAL | $1.00 | $1.00 | $1.00 | $2.00 | $1,000 | $50.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E00900 6" CONDUIT, TYPE B | 30 FT | $13.00 | $12.40 | $25.50 | $27.00 | $55.00 | $15.00 | $20.00 |
| 611E01400 6" CONDUIT, TYPE E | 30 FT | $7.00 | $12.40 | $16.50 | $27.00 | $55.00 | $15.00 | $20.00 |
| 611E01500 6" CONDUIT, TYPE F | 30 FT | $7.00 | $12.40 | $16.50 | $27.00 | $55.00 | $15.00 | $20.00 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $760 | $834 | $655 | $1,200 | $2,100 | $500 | $1,200 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 10 CY | $295 | $150 | $303 | $181 | $500 | $240 | $400 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 120 FT | $3.00 | $8.80 | $5.50 | $3.00 | $20.00 | $5.00 | $10.00 |
| 304E20000 AGGREGATE BASE | 43 CY | $67.00 | $108 | $83.00 | $70.00 | $150 | $50.00 | $75.00 |
| 407E20000 NON-TRACKING TACK COAT | 38 GAL | $5.50 | $9.00 | $3.50 | $7.00 | $9.00 | $10.00 | $3.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 28 GAL | $11.00 | $9.00 | $26.50 | $22.00 | $9.00 | $10.00 | $5.00 |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 4 CY | $220 | $99.00 | $150 | $220 | $260 | $55.00 | $100 |
| 621E00100 RPM | 4 EACH | $695 | $100 | $772 | $475 | $430 | $65.00 | $1,100 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 4 EACH | $100 | $5.56 | $9.00 | $6.00 | $27.00 | $12.00 | $5.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 45 FT | $18.50 | $22.25 | $17.50 | $25.00 | $31.00 | $17.00 | $20.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 6 SF | $88.00 | $38.89 | $45.00 | $40.00 | $515 | $80.00 | $35.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.08 MILE | $10,100 | $10,206 | $29,400 | $10,120 | $800 | $10,000 | $37,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.04 MILE | $20,200 | $20,411 | $29,400 | $20,207 | $800 | $20,000 | $75,000 |
| 614E12420 DETOUR SIGNING | 1 LS | $4,400 | $6,106 | $5,145 | $4,400 | $4,200 | $5,000 | $4,900 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 30 CY | $100 | $132 | $176 | $410 | $150 | $200 | $300 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $4,000 | $3,056 | $5,570 | $1,340 | $9,000 | $29,000 | $35,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (MAH-14T-0007) | 1 LS | $4,000 | $19,756 | $23,211 | $17,000 | $18,000 | $15,560 | $5,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (STA-241-13.23) | 1 LS | $3,500 | $16,445 | $13,814 | $14,200 | $29,000 | $15,560 | $5,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (STA-619-1.97) | 1 LS | $2,000 | $12,778 | $1,276 | $1,000 | $29,000 | $15,560 | $5,000 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $650 | $1,389 | $683 | $1,525 | $2,600 | $500 | $1,750 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E28001 84" CONDUIT, TYPE A, AS PER PLAN, 706.02, 707.02 ( | 67 FT | $840 | $56k | 15% |
| 611E96550 FIELD PAVING OF EXISTING PIPE (MAH-014T-0007) | 255 FT | $170 | $43k | 12% |
| 624E10000 MOBILIZATION | 1 LS | $24,406 | $24k | 7% |
| 611E10401 24" CONDUIT, TYPE B, AS PER PLAN, 707.33 | 57 FT | $400 | $23k | 6% |
| 611E99621 MANHOLE, NO. 5, AS PER PLAN | 1 EACH | $18,500 | $19k | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 84 CY | $220 | $18k | 5% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 31 CY | $330 | $10k | 3% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 120 SY | $85 | $10k | 3% |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 8 SNMT | $1,190 | $10k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,855 | $9k | 2% |