GRE-US 68-09.57/13.35
GRE County · est $1.0M
Bid dateThursday, July 2—
GRE County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 73 more items below.
| Item | Quantity | R1Sunesis Construction CO | R2Eagle Bridge CO | R3Great Lakes Construction CO | R4Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 511E53014 CLASS QC3 CONCRETE, MISC.:SUPERSTRUCTURE CONCRETE | 85 CY | $1,571 | $950 | $1,180 | $1,780 | 13% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $121,801 | $135,000 | $150,000 | $85,000 | 12% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $99,564 | $115,000 | $150,000 | $165,000 | 10% |
| AA1 601E11000 RIPRAP, TYPE D (ALTERNATE 1) | 542 SY | $153 | $100 | $157 | $60.00 |
| Item | Quantity | R1Sunesis Construction CO | R2Eagle Bridge CO | R3Great Lakes Construction CO | R4Complete General Construction Company |
|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $6,212 | $12,000 | $10,000 | $13,000 |
| 202E38000 GUARDRAIL REMOVED | 100 FT | $1.50 | $12.53 | $1.50 | $12.50 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $55.00 | $251 | $55.00 | $250 |
| 203E10000 EXCAVATION | 95 CY | $89.15 | $150 | $165 | $40.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $68,102 | $70,000 | $150,000 | $55,000 | 7% |
| 511E43221 CLASS QC SCC CONCRETE, PIER, AS PER PLAN | 19 CY | $3,310 | $1,100 | $1,020 | $3,500 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $61,994 | $40,000 | $47,000 | $40,000 | 6% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 955 SY | $58.99 | $97.50 | $76.00 | $90.00 | 5% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 955 SY | $51.89 | $75.00 | $90.00 | $53.00 | 5% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 299 FT | $156 | $189 | $140 | $212 | 5% |
| AB3 507E71200 SPECIAL - PILE ENCASEMENT ( ALTERNATE 3 - FIVE STA | 286 FT | $158 | $265 | $240 | $258 | 4% |
| 503E21100 UNCLASSIFIED EXCAVATION | 118 CY | $293 | $70.00 | $215 | $155 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 144 CY | $220 | $221 | $220 | $220 | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 22,556 LB | $1.14 | $1.00 | $1.05 | $1.10 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 41 CF | $529 | $620 | $595 | $645 | 2% |
| 601E32105 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 192 CY | $112 | $140 | $130 | $105 | 2% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $19,628 | $27,500 | $60,000 | $160,000 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 880 FT | $21.79 | $20.00 | $19.50 | $19.50 | 2% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 144 SY | $106 | $85.00 | $60.00 | $110 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $13,311 | $8,500 | $7,000 | $7,500 | 1% |
| 203E20001 EMBANKMENT, AS PER PLAN |
| 6 CY |
| $57.55 |
| $100 |
| $185 |
| $29.50 |
| 209E15050 RESHAPING UNDER GUARDRAIL | 0.04 MILE | $3,250 | $10,023 | $3,250 | $10,000 |
| 606E15050 GUARDRAIL, TYPE MGS | 100 FT | $20.00 | $24.06 | $20.00 | $24.00 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,000 | $2,255 | $2,000 | $2,250 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 690 SY | $3.33 | $5.00 | $1.80 | $2.50 |
| 659E00541 SEEDING AND MULCHING, CLASS 3C, AS PER PLAN | 1,940 SY | $2.90 | $4.00 | $1.90 | $3.90 |
| 659E14000 REPAIR SEEDING AND MULCHING | 131 SY | $1.00 | $3.00 | $1.00 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.35 TON | $450 | $1,000 | $450 | $450 |
| 659E31000 LIME | 0.54 ACRE | $10.00 | $20.00 | $10.00 | $10.00 |
| 659E35000 WATER | 14.2 MGAL | $10.00 | $25.00 | $10.00 | $9.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,265 | $1,500 | $2,000 | $1,265 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $4,290 | $6,000 | $5,000 | $2,700 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.75) | 2,938 SY | $3.42 | $2.96 | $3.20 | $2.95 |
| 254E01600 PATCHING PLANED SURFACE | 31 SY | $30.00 | $30.07 | $30.00 | $30.00 |
| 407E20000 NON-TRACKING TACK COAT | 250 GAL | $1.00 | $1.00 | $1.00 | $1.00 |
| 617E10100 COMPACTED AGGREGATE | 15 CY | $215 | $175 | $165 | $100 |
| 617E25000 WATER | 0.31 MGAL | $188 | $10.00 | $100 | $200 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 0.25 MILE | $23,485 | $27,500 | $22,000 | $16,500 |
| 621E00100 RPM | 14 EACH | $173 | $203 | $202 | $257 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 14 EACH | $1.00 | $15.00 | $15.00 | $25.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 6 EACH | $10.00 | $12.03 | $10.00 | $11.00 |
| 626E00116 BARRIER REFLECTOR, TYPE 5 (BI-DIRECTIONAL) | 4 EACH | $15.00 | $11.03 | $15.00 | $11.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.01 MILE | $34,943 | $35,023 | $34,943 | $34,943 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.08 MILE | $24,610 | $24,667 | $24,610 | $24,610 |
| 642E00300 CENTER LINE, TYPE 1 | 0.05 MILE | $24,795 | $24,852 | $24,795 | $24,795 |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 36 FT | $5.10 | $5.11 | $5.10 | $5.10 |
| 642E01500 DOTTED LINE, 4", TYPE 1 | 72 FT | $5.05 | $5.06 | $5.05 | $5.05 |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 108 FT | $9.90 | $9.92 | $9.90 | $9.90 |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 0.15 MILE | $41,610 | $41,706 | $41,610 | $41,610 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $65.00 | $65.00 | $72.00 | $80.00 |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 3 EACH | $1,985 | $2,000 | $1,900 | $1,900 |
| 614E12420 DETOUR SIGNING | 1 LS | $2,142 | $5,000 | $450 | $450 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 18 EACH | $11.49 | $11.00 | $11.00 | $11.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 4 EACH | $15.67 | $15.00 | $15.00 | $15.00 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.53 MILE | $3,750 | $3,759 | $3,750 | $3,750 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.15 MILE | $3,395 | $3,403 | $3,395 | $3,395 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.76 MILE | $3,565 | $3,573 | $3,565 | $3,565 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 0.3 MILE | $3,300 | $3,308 | $3,300 | $3,300 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 48 FT | $2.50 | $2.51 | $2.50 | $2.50 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $3,802 | $9,000 | $3,500 | $20,000 |
| 202E11202 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $836 | $24,000 | $1.00 | $3,446 |
| 204E10000 SUBGRADE COMPACTION | 542 SY | $12.57 | $5.00 | $7.80 | $8.00 |
| 204E50000 GEOTEXTILE FABRIC | 600 SY | $2.47 | $4.00 | $2.75 | $6.00 |
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 268 SY | $36.86 | $18.04 | $50.50 | $18.00 |
| 530E00200 SPECIAL - STRUCTURES , MISC.: TEMPORARY CONSTRUCTI | 1 LS | $8,613 | $7,500 | $5,000 | $16,500 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 31 CY | $171 | $150 | $165 | $140 |
| 602E97000 MASONRY, MISC.:STONE MASONRY RESTORATION AND REPAI | 107 SF | $93.46 | $50.00 | $45.00 | $565 |
| 602E98200 MASONRY, MISC.:STONE MASONRY RESTORATION AND REPAI | 1.5 CY | $3,667 | $3,200 | $2,000 | $6,500 |
| 613E41250 LOW STRENGTH MORTAR BACKFILL (TYPE 1) | 11 CY | $237 | $675 | $700 | $465 |
| 509E20001 REINFORCING STEEL, REPLACEMENT OF EXISTING REINFOR | 200 LB | $2.61 | $1.00 | $4.65 | $1.50 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 24 EACH | $13.97 | $24.00 | $25.00 | $25.00 |
| 511E53014 CLASS QC3 CONCRETE, MISC.:SUBSTRUCTURE CONCRETE WI | 6 CY | $1,255 | $1,900 | $2,365 | $2,575 |
| 511E81300 CONCRETE, MISC.:EMBEDDED GALVANIC ANODES (EGA) | 280 EACH | $31.87 | $40.00 | $26.00 | $30.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 138 SY | $40.99 | $25.06 | $25.00 | $25.00 |
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 43 SY | $27.94 | $16.04 | $20.00 | $16.00 |
| 512E10600 CONCRETE REPAIR BY EPOXY INJECTION | 2 FT | $125 | $500 | $750 | $355 |
| 512E33000 TYPE 2 WATERPROOFING | 14 SY | $58.46 | $75.00 | $40.00 | $95.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 10 SF | $4.36 | $7.00 | $25.00 | $21.50 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 6 CY | $173 | $175 | $185 | $160 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 345 FT | $20.02 | $12.00 | $15.00 | $13.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 10 SF | $136 | $400 | $500 | $225 |
| 530E00200 SPECIAL - STRUCTURES, MISC.: TEMPORARY CONSTRUCTIO | 1 LS | $4,093 | $10,000 | $19,000 | $16,500 |
| 530E00200 SPECIAL - STRUCTURES: CONSULTANT FOR CONCRETE QUAL | 1 LS | $2,880 | $7,500 | $8,000 | $5,441 |
| 848E30201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY (VARIABLE | 27 CY | $387 | $260 | $355 | $365 |
| 848E50000 HAND CHIPPING | 6 SY | $93.95 | $100 | $490 | $120 |
| 848E50100 TEST SLAB | 1 LS | $1,695 | $2,000 | $1,800 | $8,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,423 | $20,000 | $20,000 | $15,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $4,250 | $7,000 | $20,000 | $6,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E53014 CLASS QC3 CONCRETE, MISC.:SUPERSTRUCTURE CONCRETE | 85 CY | $1,571 | $134k | 11% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $121,801 | $122k | 10% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $99,564 | $100k | 8% |
| AA1 601E11000 RIPRAP, TYPE D (ALTERNATE 1) | 542 SY | $152.93 | $83k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $68,102 | $68k | 5% |
| 511E43221 CLASS QC SCC CONCRETE, PIER, AS PER PLAN | 19 CY | $3,310 | $63k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $61,994 | $62k | 5% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 955 SY | $58.99 | $56k | 4% |
| 848E10201 SUPERPLASTICIZED DENSE CONCRETE OVERLAY USING HYDR | 955 SY | $51.89 | $50k | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 299 FT | $155.72 | $47k | 4% |