MAD-SR 29-10.61
MAD County · est $3.0M
Bid dateThursday, October 1—
MAD County · est $3.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 9.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 83 more items below.
| Item | Quantity | R1J D Williamson Construction CO INC | R2Shelly & Sands INC | R3Ruhlin Company | R4Eagle Bridge CO | R5Double Z Construction Company | R6George J Igel & CO INC | R7Miller Bros Const INC | R8Complete General Construction Company | R9Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 56,262 SF | $6.25 | $6.40 | $8.00 | $6.10 | $8.00 | $8.00 | $9.00 | $8.00 | $6.19 | 16% |
| 511E34447 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK, AS PER | 697 CY | $480 |
| Item | Quantity | R1J D Williamson Construction CO INC | R2Shelly & Sands INC | R3Ruhlin Company | R4Eagle Bridge CO | R5Double Z Construction Company | R6George J Igel & CO INC | R7Miller Bros Const INC | R8Complete General Construction Company | R9Sunesis Construction CO |
|---|---|---|---|---|---|---|---|---|---|---|
| 201E21800 TREE REMOVED, 18" | 6 EACH | $310 | $300 | $578 | $600 | $400 | $578 | $240 | $900 | $1,302 |
| 201E23000 TREE REMOVED, 30" | 1 EACH | $1,025 | $1,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $650 |
| $600 |
| $800 |
| $750 |
| $762 |
| $865 |
| $900 |
| $1,042 |
| 16% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $255,000 | $137,000 | $225,000 | $215,000 | $190,000 | $228,300 | $340,000 | $185,000 | $274,249 | 12% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 172,799 LB | $0.92 | $0.90 | $1.10 | $1.00 | $1.10 | $1.15 | $1.20 | $1.10 | $1.24 | 7% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 57,327 SF | $2.05 | $2.00 | $1.00 | $2.00 | $2.00 | $2.00 | $1.00 | $2.00 | $2.03 | 6% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 57,327 SF | $2.05 | $2.00 | $1.00 | $2.00 | $1.25 | $1.25 | $1.00 | $1.25 | $2.03 | 6% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 56,262 SF | $1.90 | $2.00 | $1.25 | $1.85 | $2.50 | $2.50 | $1.00 | $2.50 | $1.88 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $100,000 | $100,000 | $100,000 | $100,000 | $100,000 | $100,000 | $74,000 | 5% |
| 511E34450 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 178 CY | $530 | $315 | $425 | $500 | $670 | $475 | $585 | $375 | $367 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $75,000 | $75,000 | $70,000 | $42,000 | $65,000 | $50,000 | $65,000 | $42,000 | $47,115 | 4% |
| 607E39900 VANDAL PROTECTION FENCE, 6' STRAIGHT, COATED FABRI | 1,074 FT | $68.75 | $62.50 | $79.25 | $76.00 | $63.00 | $76.00 | $76.00 | $71.50 | $67.00 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 451 CY | $160 | $155 | $140 | $140 | $155 | $140 | $175 | $155 | $155 | 3% |
| 526E30000 REINFORCED CONCRETE APPROACH SLABS (T=17") | 217 SY | $265 | $300 | $250 | $275 | $270 | $300 | $335 | $300 | $295 | 3% |
| 516E44201 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 15 EACH | $2,500 | $2,300 | $3,250 | $3,500 | $2,500 | $3,100 | $3,200 | $2,500 | $3,869 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 500 HOUR | $72.00 | $68.00 | $70.00 | $70.00 | $65.00 | $70.00 | $65.00 | $80.00 | $65.00 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $35,000 | $13,000 | $15,000 | $20,000 | $25,000 | $40,000 | $10,000 | $30,000 | $56,628 | 2% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $31,500 | $29,500 | $25,000 | $35,000 | $23,000 | $40,000 | $50,000 | $29,750 | $79,784 | 1% |
| 516E44401 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 10 EACH | $2,850 | $2,700 | $4,550 | $1,750 | $3,230 | $4,000 | $3,100 | $3,000 | $3,869 | 1% |
| 452E13060 9.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 315 SY | $87.00 | $125 | $80.00 | $125 | $99.00 | $95.00 | $88.00 | $95.00 | $126 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 18 MNTH | $1,400 | $2,520 | $2,000 | $1,500 | $1,150 | $2,900 | $1,800 | $1,500 | $1,004 | 1% |
| $714 |
| $1,250 |
| $800 |
| $714 |
| $660 |
| $1,500 |
| $3,911 |
| 201E24800 TREE REMOVED, 48" | 1 EACH | $1,550 | $1,500 | $918 | $1,750 | $1,000 | $918 | $900 | $2,000 | $4,411 |
| 202E23000 PAVEMENT REMOVED | 1,528 SY | $12.00 | $4.00 | $17.00 | $17.00 | $35.00 | $15.00 | $25.00 | $30.00 | $33.20 |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 512 SY | $14.00 | $5.00 | $13.00 | $6.00 | $25.00 | $14.00 | $17.50 | $20.00 | $14.41 |
| 202E32000 CURB REMOVED | 184 FT | $4.00 | $2.00 | $2.50 | $4.00 | $5.00 | $2.00 | $6.00 | $10.00 | $5.60 |
| 202E38000 GUARDRAIL REMOVED | 150 FT | $2.00 | $1.80 | $2.50 | $2.50 | $4.38 | $2.50 | $2.50 | $1.80 | $5.11 |
| 202E42050 ANCHOR ASSEMBLY REMOVED, TYPE B | 2 EACH | $110 | $105 | $150 | $150 | $264 | $150 | $150 | $105 | $240 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $90.00 | $85.00 | $150 | $150 | $176 | $150 | $150 | $85.00 | $192 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 247 FT | $35.00 | $16.00 | $10.75 | $18.00 | $26.00 | $18.00 | $20.00 | $15.00 | $14.42 |
| 202E70120 SPECIAL - PIPE CLEANOUT, 27" TO 48" | 314 FT | $50.00 | $20.00 | $14.50 | $22.00 | $46.00 | $31.00 | $20.00 | $10.00 | $16.64 |
| 203E10000 EXCAVATION | 105 CY | $12.00 | $13.50 | $35.00 | $70.00 | $80.00 | $40.00 | $25.00 | $30.00 | $27.86 |
| 203E20000 EMBANKMENT | 42 CY | $13.25 | $17.00 | $35.00 | $70.00 | $15.00 | $30.00 | $20.00 | $20.00 | $217 |
| 204E10000 SUBGRADE COMPACTION | 2,332 SY | $2.25 | $2.50 | $3.00 | $4.00 | $6.00 | $5.00 | $1.50 | $3.00 | $1.68 |
| 209E10000 DITCH CLEANOUT | 2,383 FT | $6.00 | $4.00 | $12.00 | $5.00 | $7.00 | $10.00 | $6.00 | $10.00 | $7.07 |
| 606E15050 GUARDRAIL, TYPE MGS | 125 FT | $20.25 | $19.60 | $17.50 | $17.50 | $16.40 | $17.50 | $17.50 | $19.60 | $16.40 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 2 EACH | $1,950 | $1,850 | $1,800 | $1,800 | $2,225 | $1,800 | $1,800 | $1,850 | $2,225 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,250 | $2,160 | $2,000 | $2,000 | $2,355 | $2,000 | $2,000 | $2,160 | $2,355 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 14 SY | $75.00 | $90.00 | $70.00 | $80.00 | $125 | $63.00 | $100 | $1,200 | $115 |
| 659E00100 SOIL ANALYSIS TEST | 1 EACH | $200 | $88.00 | $88.00 | $50.00 | $100 | $88.00 | $200 | $100 | $200 |
| 659E00300 TOPSOIL | 90 CY | $40.00 | $60.00 | $35.00 | $5.00 | $50.00 | $28.00 | $40.00 | $25.00 | $39.59 |
| 659E10000 SEEDING AND MULCHING | 811 SY | $3.00 | $1.76 | $1.76 | $6.00 | $8.00 | $1.76 | $2.75 | $4.00 | $4.11 |
| 659E14000 REPAIR SEEDING AND MULCHING | 41 SY | $1.00 | $0.68 | $0.68 | $2.00 | $4.00 | $0.68 | $1.00 | $4.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $500 | $609 | $609 | $750 | $610 | $609 | $500 | $610 | $500 |
| 659E31000 LIME | 0.17 ACRE | $200 | $151 | $151 | $10.00 | $80.00 | $151 | $200 | $80.00 | $200 |
| 659E35000 WATER | 6 MGAL | $1.00 | $1.00 | $1.00 | $10.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 670E00500 SLOPE EROSION PROTECTION | 10 SY | $3.00 | $1.38 | $1.38 | $4.00 | $25.00 | $1.38 | $2.75 | $25.00 | $2.75 |
| 670E00700 DITCH EROSION PROTECTION | 1,785 SY | $3.00 | $1.44 | $1.44 | $4.00 | $3.50 | $1.44 | $2.75 | $2.40 | $2.75 |
| 832E30000 EROSION CONTROL | 25,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 20 FT | $11.25 | $20.00 | $20.00 | $13.00 | $20.00 | $11.00 | $24.00 | $35.00 | $24.32 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 710 FT | $10.75 | $10.00 | $20.00 | $10.00 | $10.00 | $13.00 | $13.50 | $20.00 | $9.83 |
| 605E31100 AGGREGATE DRAINS | 54 FT | $10.50 | $9.00 | $15.00 | $8.00 | $18.00 | $25.00 | $13.00 | $20.00 | $7.47 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 32 FT | $3.00 | $6.00 | $10.00 | $2.00 | $5.00 | $2.00 | $2.00 | $2.00 | $9.74 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 32 FT | $3.00 | $6.00 | $10.00 | $2.00 | $5.00 | $1.00 | $2.00 | $2.00 | $9.74 |
| 304E20000 AGGREGATE BASE | 447 CY | $46.50 | $50.00 | $55.00 | $50.00 | $70.00 | $65.00 | $70.00 | $55.00 | $69.27 |
| 407E20000 NON-TRACKING TACK COAT | 285 GAL | $3.00 | $3.00 | $3.25 | $3.25 | $3.00 | $3.25 | $2.00 | $3.00 | $3.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 16 CY | $260 | $250 | $525 | $525 | $250 | $525 | $300 | $250 | $250 |
| 442E00100 ANTI-SEGREGATION EQUIPMENT | 138 CY | $6.25 | $6.00 | $13.25 | $13.25 | $6.00 | $13.25 | $15.00 | $6.00 | $6.00 |
| 442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 64 CY | $225 | $220 | $205 | $205 | $220 | $205 | $280 | $220 | $220 |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 74 CY | $195 | $190 | $170 | $170 | $190 | $170 | $260 | $190 | $190 |
| 451E31000 SPECIAL - PRESSURE RELIEF JOINT, TYPE B | 64 FT | $100 | $95.00 | $125 | $120 | $95.00 | $130 | $175 | $200 | $223 |
| 609E24510 CURB, TYPE 4-C | 27 FT | $33.00 | $62.50 | $35.00 | $60.00 | $42.00 | $40.00 | $40.00 | $95.00 | $40.00 |
| 609E26000 CURB, TYPE 6 | 151 FT | $20.00 | $25.01 | $25.00 | $40.00 | $40.00 | $30.00 | $42.00 | $50.00 | $40.00 |
| 621E00100 RPM (2-WAY, RED/YELLOW) | 7 EACH | $255 | $251 | $275 | $251 | $251 | $251 | $251 | $234 | $234 |
| 621E00100 RPM (2-WAY, YELLOW/YELLOW) | 5 EACH | $255 | $251 | $275 | $251 | $251 | $251 | $251 | $234 | $234 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 26 EACH | $8.00 | $7.50 | $10.00 | $10.00 | $20.00 | $10.00 | $10.00 | $7.50 | $10.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 4 EACH | $8.00 | $7.50 | $8.50 | $8.50 | $20.00 | $8.50 | $8.50 | $7.50 | $8.50 |
| 632E90400 SIGNALIZATION, MISC.: RWIS SENSOR, VX21-2 | 1 EACH | $4,000 | $11,460 | $3,750 | $3,750 | $5,500 | $11,460 | $11,500 | $2,500 | $3,750 |
| 644E00104 EDGE LINE, 6" | 0.03 MILE | $40,000 | $39,020 | $7,200 | $7,200 | $39,020 | $39,020 | $39,020 | $7,200 | $39,020 |
| 644E00300 CENTER LINE | 0.02 MILE | $40,500 | $39,730 | $12,900 | $12,900 | $39,730 | $39,730 | $39,730 | $12,900 | $39,730 |
| 646E10010 EDGE LINE, 6" | 0.49 MILE | $10,500 | $10,210 | $8,180 | $8,180 | $10,210 | $10,210 | $10,210 | $8,180 | $10,210 |
| 646E10200 CENTER LINE | 0.13 MILE | $11,000 | $10,630 | $14,650 | $14,650 | $10,630 | $10,630 | $10,630 | $14,650 | $10,630 |
| 831E00100 LONGITUDINAL CHANNELIZING DEVICE | 140 FT | $95.50 | $92.50 | $62.00 | $62.00 | $75.00 | $62.00 | $62.00 | $92.50 | $62.00 |
| 831E00500 REMOVAL OF LONGITUDINAL CHANNELIZING DEVICE | 140 FT | $6.75 | $3.00 | $7.50 | $7.50 | $4.50 | $7.50 | $7.50 | $6.50 | $7.50 |
| 614E12420 DETOUR SIGNING | 1 LS | $20,000 | $35,000 | $26,400 | $30,000 | $30,000 | $30,000 | $25,600 | $30,000 | $30,422 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $100 | $200 | $200 | $450 | $150 | $310 | $200 | $200 | $380 |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 18 SNMT | $1,000 | $850 | $550 | $600 | $500 | $360 | $950 | $600 | $950 |
| 616E10000 WATER | 2 MGAL | $5.00 | $62.00 | $100 | $10.00 | $80.00 | $49.00 | $85.00 | $61.25 | $53.62 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,950 | $2,920 | $2,000 | $2,000 | $2,500 | $2,000 | $2,000 | $2,920 | $2,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 12 EACH | $10.25 | $15.00 | $10.00 | $7.00 | $15.00 | $14.00 | $25.00 | $10.00 | $25.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 4 EACH | $12.25 | $22.00 | $15.00 | $12.00 | $13.00 | $17.00 | $35.00 | $10.00 | $35.00 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 200 FT | $7.50 | $16.00 | $20.00 | $30.00 | $26.00 | $20.00 | $12.00 | $25.00 | $34.03 |
| 202E22900 APPROACH SLAB REMOVED | 176 SY | $24.50 | $19.00 | $35.00 | $35.00 | $40.00 | $35.00 | $40.00 | $50.00 | $19.70 |
| 503E21100 UNCLASSIFIED EXCAVATION | 163 CY | $56.00 | $95.00 | $105 | $85.00 | $99.00 | $160 | $80.00 | $270 | $82.15 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 272 EACH | $19.00 | $28.00 | $20.00 | $15.00 | $19.00 | $27.00 | $22.00 | $25.00 | $14.65 |
| 511E33501 SEMI-INTEGRAL DIAPHRAGM GUIDE, AS PER PLAN | 8 EACH | $1,500 | $2,300 | $3,250 | $3,250 | $2,400 | $2,800 | $3,150 | $6,000 | $2,330 |
| 511E44110 CLASS QC1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING | 23 CY | $725 | $2,100 | $1,500 | $1,200 | $1,050 | $820 | $1,100 | $2,000 | $758 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 1,756 SY | $5.00 | $8.50 | $9.00 | $8.50 | $8.00 | $8.50 | $8.00 | $8.50 | $8.50 |
| 513E20001 WELDED STUD SHEAR CONNECTORS, AS PER PLAN | 4,080 EACH | $4.00 | $3.25 | $4.00 | $4.05 | $3.40 | $3.50 | $4.95 | $3.90 | $4.48 |
| 513E90000 STRUCTURAL STEEL, MISC.: ADDITIONAL INTERMEDIATE B | 1,782 LB | $10.00 | $9.50 | $13.00 | $10.00 | $10.00 | $9.00 | $11.00 | $12.00 | $8.98 |
| 513E95020 STRUCTURAL STEEL, MISC.: FIELD DRILLED HOLES IN EX | 1 LS | $4,100 | $4,000 | $4,000 | $5,000 | $4,000 | $4,000 | $4,500 | $10,000 | $5,677 |
| 514E00504 GRINDING FINS, TEARS, SLIVERS ON EXISTING STRUCTUR | 45 MNHR | $100 | $110 | $85.00 | $100 | $150 | $150 | $100 | $150 | $101 |
| 514E10000 FINAL INSPECTION REPAIR | 26 EACH | $100 | $110 | $125 | $100 | $200 | $200 | $100 | $200 | $101 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 129 FT | $32.00 | $70.00 | $35.00 | $45.00 | $45.00 | $60.00 | $36.00 | $70.00 | $70.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 126 SF | $6.00 | $8.00 | $7.00 | $6.00 | $12.00 | $11.00 | $6.75 | $15.00 | $3.73 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 210 SF | $7.25 | $8.00 | $9.00 | $12.00 | $15.00 | $11.00 | $7.75 | $10.00 | $5.86 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 388 SF | $10.50 | $9.00 | $13.00 | $10.00 | $11.00 | $15.00 | $9.00 | $25.00 | $13.94 |
| 516E46501 BEARING, PTFE (TEFLON), AS PER PLAN | 10 EACH | $25.00 | $620 | $500 | $2,000 | $500 | $1.00 | $900 | $3,500 | $130 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 68 CY | $70.00 | $90.00 | $95.00 | $100 | $85.00 | $94.00 | $95.00 | $150 | $94.80 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 222 SF | $80.00 | $105 | $90.00 | $105 | $100 | $105 | $90.00 | $105 | $110 |
| 526E90030 TYPE C INSTALLATION | 129 FT | $122 | $211 | $150 | $185 | $190 | $200 | $210 | $175 | $204 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $15,000 | $39,000 | $45,000 | $30,000 | $25,000 | $30,000 | $35,000 | $16,666 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $25,000 | $25,000 | $7,500 | $18,000 | $12,500 | $7,300 | $5,000 | $9,350 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 514E00050 SURFACE PREPARATION OF EXISTING STRUCTURAL STEEL | 56,262 SF | $6.25 | $352k | 14% |
| 511E34447 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK, AS PER | 697 CY | $480 | $335k | 13% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $255,000 | $255k | 10% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 172,799 LB | $0.92 | $159k | 6% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 57,327 SF | $2.05 | $118k | 5% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 57,327 SF | $2.05 | $118k | 5% |
| 514E00056 FIELD PAINTING OF EXISTING STRUCTURAL STEEL, PRIME | 56,262 SF | $1.9 | $107k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 511E34450 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 178 CY | $530 | $94k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $75,000 | $75k | 3% |