BEL-SR 9-00.01
BEL County · est $1.3M
Bid dateThursday, December 3—
BEL County · est $1.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 36 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Kokosing Construction Company INC | R5George J Igel & CO INC | R6Suburban Maintenance & Construction | R7Litman Excavating INC | R8Complete General Construction Company | R9Dennison Bridge INC | R10Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W18X76, FURNISHED | 3,395 FT | $34.00 | $39.00 | $28.00 | $50.00 | $51.00 | $42.00 | $51.00 | $45.00 | $45.00 | $39.00 | 13% |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Kokosing Construction Company INC | R5George J Igel & CO INC | R6Suburban Maintenance & Construction | R7Litman Excavating INC | R8Complete General Construction Company | R9Dennison Bridge INC | R10Eclipse CO LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,500 | $17,500 | $23,000 | $40,000 | $15,000 | $25,000 | $7,540 | $7,000 | $5,000 | $29,591 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 1,900 FT | $46.50 | $49.00 | $58.50 | $50.00 | $60.00 | $60.00 | $41.00 | $100 | $70.00 | $101 | 10% |
| 511E81300 CONCRETE, MISC.:8" x 24" x 57" PRECAST CONCRETE LA | 496 EACH | $165 | $185 | $190 | $152 | $160 | $250 | $260 | $160 | $275 | $175 | 9% |
| 524E94605 DRILLED SHAFTS, 30" DIAMETER INTO BEDROCK, AS PER | 1,100 FT | $70.00 | $74.00 | $70.50 | $69.00 | $80.00 | $140 | $43.00 | $80.00 | $105 | $124 | 9% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 30" DIAMETER, UN | 1,125 FT | $56.50 | $53.00 | $59.00 | $50.00 | $52.50 | $60.00 | $41.00 | $100 | $70.00 | $116 | 7% |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 2,495 FT | $22.00 | $32.00 | $24.00 | $34.00 | $33.00 | $25.80 | $31.00 | $34.00 | $30.00 | $29.00 | 6% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 800 FT | $59.50 | $74.00 | $70.00 | $63.00 | $75.00 | $131 | $41.00 | $80.00 | $95.00 | $134 | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 254 CY | $175 | $176 | $196 | $176 | $189 | $225 | $176 | $176 | $185 | $177 | 5% |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1,417 CY | $28.00 | $24.00 | $23.50 | $86.00 | $65.00 | $12.00 | $15.90 | $60.00 | $80.00 | $107 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $32,750 | $36,810 | $45,250 | $40,000 | $40,000 | $40,000 | $19,020 | $40,000 | $40,000 | $50,000 | 4% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 1,040 FT | $29.50 | $49.00 | $47.00 | $30.00 | $55.00 | $52.00 | $38.00 | $100 | $60.00 | $94.00 | 4% |
| 304E20000 AGGREGATE BASE | 407 CY | $75.00 | $80.00 | $79.00 | $125 | $68.50 | $65.00 | $44.13 | $70.00 | $120 | $77.50 | 4% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 320 CY | $78.00 | $165 | $160 | $110 | $77.50 | $75.00 | $89.13 | $90.00 | $130 | $82.50 | 3% |
| 606E15151 GUARDRAIL, TYPE MGS HALF POST SPACING, AS PER PLAN | 1,050 FT | $23.75 | $23.75 | $26.50 | $23.75 | $25.00 | $25.00 | $385 | $26.60 | $25.00 | $24.25 | 3% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 97 CY | $237 | $330 | $377 | $440 | $360 | $230 | $195 | $550 | $475 | $375 | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 115 CY | $195 | $115 | $284 | $270 | $305 | $115 | $285 | $170 | $300 | $185 | 3% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 102 CY | $210 | $276 | $301 | $377 | $295 | $285 | $276 | $276 | $290 | $279 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,150 | $7,302 | $7,000 | $6,000 | $10,000 | $25,000 | $13,819 | $14,000 | $15,000 | $26,376 | 2% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (62 CY | $235 | $256 | $279 | $178 | $275 | $250 | $256 | $256 | $270 | $256 | 2% |
| 202E23000 PAVEMENT REMOVED, (ASPHALT) | 2,813 SY | $5.00 | $4.00 | $5.50 | $10.00 | $11.25 | $10.00 | $2.81 | $10.00 | $18.00 | $11.00 | 2% |
| 202E38000 GUARDRAIL REMOVED | 2,038 FT | $1.80 | $1.80 | $0.50 | $3.00 | $2.25 | $4.00 | $2.06 | $1.60 | $2.00 | $3.00 |
| 202E98000 REMOVAL MISC.: PILING REMOVED | 1 LS | $10,000 | $18,000 | $17,000 | $2,000 | $20,000 | $30,000 | $8,830 | $20,000 | $25,000 | $14,901 |
| 203E10000 EXCAVATION | 12 CY | $18.00 | $21.00 | $15.50 | $30.00 | $35.00 | $15.00 | $38.75 | $35.00 | $25.00 | $57.50 |
| 203E20000 EMBANKMENT | 281 CY | $9.75 | $17.00 | $10.00 | $29.00 | $11.00 | $19.00 | $15.92 | $15.00 | $25.00 | $21.50 |
| 204E10000 SUBGRADE COMPACTION | 1,440 SY | $2.75 | $3.00 | $5.00 | $3.50 | $3.75 | $5.00 | $0.33 | $3.00 | $3.00 | $2.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $825 | $825 | $1,700 | $825 | $865 | $1,000 | $1.01 | $960 | $900 | $908 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $230 | $110 | $419 | $120 | $235 | $250 | $418 | $1,000 | $300 | $156 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $88.00 | $56.00 | $88.00 | $135 | $100 | $750 | $88.00 | $100 | $153 |
| 659E00300 TOPSOIL | 153 CY | $20.00 | $30.00 | $62.50 | $40.00 | $45.00 | $45.00 | $41.10 | $25.00 | $65.00 | $58.50 |
| 659E10000 SEEDING AND MULCHING | 1,375 SY | $2.60 | $1.85 | $2.50 | $1.84 | $2.80 | $4.00 | $1.06 | $1.84 | $3.00 | $2.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 69 SY | $2.60 | $0.70 | $11.00 | $0.68 | $1.03 | $3.00 | $9.27 | $0.68 | $3.00 | $2.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.2 TON | $610 | $620 | $956 | $620 | $950 | $500 | $813 | $620 | $1,000 | $622 |
| 659E31000 LIME | 0.28 ACRE | $80.00 | $155 | $1,200 | $156 | $240 | $500 | $1,107 | $156 | $100 | $81.50 |
| 659E35000 WATER | 8 MGAL | $1.00 | $1.00 | $112 | $1.00 | $1.50 | $1.00 | $229 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $250 | $300 | $479 | $400 | $300 | $250 | $2,829 | $500 | $300 | $221 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25") | 1,665 SY | $5.00 | $4.50 | $5.50 | $4.25 | $11.00 | $7.00 | $4.50 | $4.50 | $5.00 | $4.50 |
| 407E10000 TACK COAT | 351 GAL | $2.00 | $2.00 | $1.50 | $2.25 | $2.10 | $3.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 183 GAL | $9.00 | $8.00 | $3.50 | $8.00 | $8.25 | $7.00 | $8.00 | $8.00 | $10.00 | $8.00 |
| 621E00100 RPM | 27 EACH | $100 | $100 | $112 | $100 | $105 | $125 | $120 | $100 | $105 | $102 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 27 EACH | $12.00 | $8.00 | $50.00 | $28.00 | $13.25 | $50.00 | $68.51 | $15.00 | $20.00 | $10.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 12 EACH | $10.00 | $8.50 | $13.50 | $8.50 | $9.00 | $13.00 | $9.66 | $7.85 | $10.00 | $8.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 13 FT | $10.00 | $15.00 | $5.50 | $12.00 | $13.25 | $13.00 | $12.00 | $20.00 | $20.00 | $10.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $65.00 | $50.00 | $28.00 | $75.00 | $36.00 | $100 | $72.00 | $85.00 | $100 | $61.00 |
| 646E10010 EDGE LINE, 6" | 0.4 MILE | $8,000 | $7,305 | $2,400 | $7,305 | $12,250 | $5,500 | $9,000 | $7,795 | $10,000 | $7,951 |
| 646E10200 CENTER LINE | 0.2 MILE | $10,000 | $10,375 | $1,700 | $10,375 | $15,500 | $5,500 | $18,000 | $9,815 | $12,000 | $10,012 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,650 | $8,000 | $8,400 | $15,000 | $8,000 | $33,000 | $9,180 | $9,000 | $8,500 | $13,500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.2 MILE | $3,000 | $2,995 | $1,700 | $2,995 | $3,150 | $3,000 | $3,595 | $2,995 | $3,250 | $3,055 |
| 616E10000 WATER | 10 MGAL | $10.00 | $25.00 | $56.00 | $85.00 | $40.00 | $1.00 | $30.00 | $60.00 | $75.00 | $31.00 |
| 617E10100 COMPACTED AGGREGATE | 115 CY | $65.00 | $95.00 | $93.00 | $90.00 | $90.00 | $50.00 | $80.24 | $65.00 | $175 | $107 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 655 FT | $2.00 | $2.00 | $3.00 | $7.00 | $5.00 | $9.00 | $10.91 | $15.00 | $10.00 | $4.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 4 FT | $15.00 | $45.00 | $25.00 | $50.00 | $60.00 | $9.00 | $40.25 | $15.00 | $50.00 | $32.00 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $13,500 | $3,500 | $8,700 | $5,500 | $15,000 | $40,000 | $4,020 | $7,000 | $15,000 | $19,500 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $1,600 | $2,700 | $429 | $1,600 | $2,500 | $900 | $7,200 | $2,500 | $2,000 | $650 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,000 | $10,000 | $10,000 | $10,000 | $12,500 | $15,000 | $1,900 | $5,000 | $10,000 | $17,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: W18X76, FURNISHED | 3,395 FT | $34 | $115k | 12% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 1,900 FT | $46.5 | $88k | 9% |
| 511E81300 CONCRETE, MISC.:8" x 24" x 57" PRECAST CONCRETE LA | 496 EACH | $164.5 | $82k | 8% |
| 524E94605 DRILLED SHAFTS, 30" DIAMETER INTO BEDROCK, AS PER | 1,100 FT | $70 | $77k | 8% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 30" DIAMETER, UN | 1,125 FT | $56.5 | $64k | 7% |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 2,495 FT | $22 | $55k | 6% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 800 FT | $59.5 | $48k | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 254 CY | $175 | $44k | 5% |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1,417 CY | $28 | $40k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $32,750 | $33k | 3% |