BUT-US 127-16.56
BUT County · est $2.1M
Bid dateThursday, November 5—
BUT County · est $2.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 8 more items below.
| Item | Quantity | R1Sunesis Construction CO | R2Barrett Paving Materials INC | R3Eagle Bridge CO | R4John R Jurgensen Company | R5Rack & Ballauer Excavating CO INC | % of bid |
|---|---|---|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $633,701 | $445,000 | $525,000 | $612,311 | $350,000 | 24% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $379,648 | $260,000 | $400,000 | $567,662 | $110,000 | 14% |
| 690E21000 SPECIAL - MISC.: SUBGRADE TREATMENT | 1 LS | $318,223 | $155,000 | $140,000 | $153,788 | $142,000 | 12% |
| Item | Quantity | R1Sunesis Construction CO | R2Barrett Paving Materials INC | R3Eagle Bridge CO | R4John R Jurgensen Company | R5Rack & Ballauer Excavating CO INC |
|---|---|---|---|---|---|---|
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,450 | $1,500 | $2,000 | $1,450 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $3,060 | $10,500 | $17,500 | $10,500 | $15,000 |
| 251E01030 PARTIAL DEPTH PAVEMENT REPAIR (442) | 13 CY | $396 | $500 | $501 | $1,524 | $1,000 |
| 630E99000 SPECIAL - SIGNS AND SUPPORTS |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $264,654 |
| $470,000 |
| $385,000 |
| $383,337 |
| $1,135,000 |
| 10% |
| 450E99000 SPECIAL - RIGID PAVEMENT | 1 LS | $219,012 | $278,000 | $300,000 | $107,725 | $300,000 | 8% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $140,221 | $300,000 | $150,000 | $218,570 | $230,450 | 5% |
| 625E99000 SPECIAL - LIGHTING | 1 LS | $103,002 | $185,000 | $155,000 | $106,130 | $150,000 | 4% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $96,986 | $93,500 | $100,000 | $96,075 | $23,000 | 4% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $94,405 | $55,000 | $100,000 | $100,000 | $60,000 | 4% |
| 614E12420 DETOUR SIGNING | 1 LS | $77,917 | $12,950 | $10,000 | $8,600 | $25,000 | 3% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $71,391 | $112,580 | $150,000 | $174,000 | $125,000 | 3% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 50,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 25 MNTH | $1,789 | $900 | $1,400 | $1,143 | $1,900 | 2% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $42,916 | $96,495 | $110,000 | $31,000 | $54,000 | 2% |
| 640E99000 SPECIAL - PAVEMENT MARKING | 1 LS | $28,718 | $22,500 | $20,000 | $14,151 | $35,000 | 1% |
| 690E20220 SPECIAL - CONSTRUCTION PLANS | 1 LS | $28,475 | $48,250 | $7,500 | $13,000 | $28,000 | 1% |
| 690E20020 SPECIAL - FIELD SURVEYS | 1 LS | $15,153 | $32,165 | $9,000 | $7,000 | $6,000 | 1% |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $14,532 | $8,400 | $40,000 | $18,373 | $60,000 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $13,382 | $13,500 | $5,000 | $13,382 | $15,000 | 1% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $11,880 | $22,500 | $30,000 | $70,000 | $25,000 | 0% |
| 1 LS |
| $8,793 |
| $17,500 |
| $20,000 |
| $13,985 |
| $15,000 |
| 107E99000 SPECIAL - UTILITY COORDINATION | 1 LS | $6,017 | $32,165 | $500 | $10,965 | $20,000 |
| 108E99000 SPECIAL - CPM PROGRESS SCHEDULE | 1 LS | $3,500 | $6,000 | $4,000 | $9,324 | $23,000 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $9,966 | $10,850 | $4,500 | $10,000 | $10,000 |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,450 | $20,500 | $30,000 | $26,427 | $30,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $633,701 | $634k | 23% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $379,648 | $380k | 14% |
| 690E21000 SPECIAL - MISC.: SUBGRADE TREATMENT | 1 LS | $318,223 | $318k | 12% |
| 690E20240 SPECIAL - ROADWAY | 1 LS | $264,654 | $265k | 10% |
| 450E99000 SPECIAL - RIGID PAVEMENT | 1 LS | $219,012 | $219k | 8% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $140,221 | $140k | 5% |
| 625E99000 SPECIAL - LIGHTING | 1 LS | $103,002 | $103k | 4% |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $96,986 | $97k | 4% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $94,405 | $94k | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $77,917 | $78k | 3% |