D05-BH FY2021
D05 County · est $0.7M
Bid dateThursday, August 13—
D05 County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 43 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Athos Contracting | R4Righter Company INC | % of bid |
|---|---|---|---|---|---|---|
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 802 SF | $93.00 | $90.00 | $95.00 | $115 | 20% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 340 SF | $93.00 | $100 | $100 | $115 | 8% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 289 SF | $93.00 | $100 | $100 | $115 | 7% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 289 SF | $93.00 | $110 | $100 | $115 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $25,764 | $40,000 | $38,000 | $40,000 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,279 | $15,000 | $17,200 | $50,000 |
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Athos Contracting | R4Righter Company INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,925 | $10,000 | $5,000 | $62,000 |
| 201E21800 TREE REMOVED, 18" | 4 EACH | $390 | $800 | $550 | $1,000 |
| 202E32800 CONCRETE SLOPE PROTECTION REMOVED | 3 SY | $48.75 | $300 | $1,000 | $1,000 |
| 601E21000 CONCRETE SLOPE PROTECTION | 3 SY | $580 | $300 | $1,200 | $1,000 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 1,571 SY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 6% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 15 CY | $1,298 | $1,600 | $1,650 | $2,200 | 5% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 14 CY | $1,298 | $1,600 | $1,650 | $2,000 | 5% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 184 SF | $93.00 | $100 | $100 | $115 | 5% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 17 CY | $921 | $500 | $1,800 | $500 | 4% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 17 CY | $921 | $500 | $1,800 | $500 | 4% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 164 SF | $86.00 | $160 | $95.00 | $150 | 4% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 9 CY | $1,298 | $2,000 | $1,750 | $1,000 | 3% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 8 CY | $1,298 | $1,600 | $1,150 | $2,000 | 3% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $8,708 | $9,200 | $9,200 | $20,000 | 2% |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $8,708 | $9,200 | $9,200 | $20,000 | 2% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 95 SF | $86.00 | $185 | $115 | $150 | 2% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 8 CY | $921 | $500 | $2,100 | $1,000 | 2% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 79 SF | $86.00 | $165 | $120 | $150 | 2% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 7 CY | $921 | $2,500 | $2,100 | $1,000 | 2% |
| $2.25 |
| $4.00 |
| $5.00 |
| $4.80 |
| 659E20000 COMMERCIAL FERTILIZER | 7 TON | $252 | $550 | $1,000 | $25.00 |
| 659E31000 LIME | 0.32 ACRE | $223 | $500 | $1,000 | $62.50 |
| 659E35000 WATER | 14.2 MGAL | $1.05 | $2.00 | $1,000 | $1.00 |
| 832E30000 EROSION CONTROL | 1,400 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 41 SF | $86.00 | $200 | $250 | $150 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 33 SF | $86.00 | $225 | $275 | $150 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 20 SY | $11.75 | $36.00 | $55.00 | $25.00 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 33 SF | $10.22 | $50.00 | $32.00 | $50.00 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 35.2 CY | $120 | $110 | $155 | $200 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $878 | $2,500 | $9,200 | $40,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $1,755 | $5,000 | $10,850 | $20,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 802 LB | $1.70 | $2.00 | $0.78 | $3.00 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 96 EACH | $19.31 | $25.00 | $30.00 | $25.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 11 SY | $11.75 | $36.00 | $96.00 | $25.00 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 70 SF | $10.22 | $36.00 | $32.00 | $50.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $683 | $2,500 | $9,000 | $40,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,510 | $5,000 | $10,850 | $20,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,755 LB | $1.70 | $2.00 | $0.78 | $3.00 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 130 EACH | $19.31 | $25.00 | $30.00 | $25.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 45 SY | $11.75 | $36.00 | $25.00 | $25.00 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 34 SF | $10.22 | $50.00 | $32.00 | $50.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 9 SF | $86.00 | $300 | $325 | $150 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $1,365 | $2,500 | $9,000 | $40,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,510 | $6,500 | $10,850 | $20,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,783 LB | $1.70 | $2.00 | $0.78 | $3.00 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 84 EACH | $19.31 | $25.00 | $30.00 | $25.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 74 SY | $11.75 | $36.00 | $14.00 | $25.00 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 97 SF | $10.22 | $36.00 | $32.00 | $50.00 |
| 519E11100 PATCHING CONCRETE STRUCTURE | 23 SF | $86.00 | $185 | $298 | $150 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $683 | $2,500 | $9,000 | $40,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $1,755 | $7,500 | $10,800 | $20,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 930 LB | $1.70 | $2.00 | $0.78 | $3.00 |
| 510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT | 44 EACH | $19.31 | $25.00 | $30.00 | $25.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 40 SY | $11.75 | $25.00 | $25.00 | $25.00 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 5 SF | $10.22 | $100 | $100 | $250 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 12 CY | $120 | $110 | $165 | $175 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,503 | $6,000 | $20,000 | $18,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $300 | $3,000 | $2,500 | $7,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 802 SF | $93 | $75k | 17% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 340 SF | $93 | $32k | 7% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 289 SF | $93 | $27k | 6% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 289 SF | $93 | $27k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $25,764 | $26k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,279 | $23k | 5% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 15 CY | $1,298 | $19k | 4% |
| 511E50210 CLASS QC1 CONCRETE, SUBSTRUCTURE | 14 CY | $1,298 | $18k | 4% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 184 SF | $93 | $17k | 4% |
| 202E11301 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 17 CY | $921 | $16k | 4% |