PUT-SR 109-04.53
PUT County · est $0.4M
Bid dateThursday, October 1—
PUT County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 39 more items below.
| Item | Quantity | R1Vernon Nagel INC | R2All Purpose Contracting INC | R3Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|
| 611E95000 10' X 5' CONDUIT, TYPE A, 706.05, DESIGN EARTH COV | 112 FT | $825 | $750 | $884 | 30% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 97 CY | $255 | $275 | $247 | 8% |
| 511E46011 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 25 CY | $950 | $1,800 | $1,269 | 8% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 52 CY | $400 | $805 | $574 | 7% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 153 CY | $125 | $140 | $162 | 6% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $15,000 | $20,000 | $9,523 | 5% |
| 304E20000 AGGREGATE BASE | 226 CY | $55.00 | $70.00 |
| Item | Quantity | R1Vernon Nagel INC | R2All Purpose Contracting INC | R3Eclipse CO LLC |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $1,000 | $3,500 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 238 FT | $4.00 | $10.00 | $15.50 |
| 203E20000 EMBANKMENT | 366 CY | $12.00 | $15.00 | $16.50 |
| 204E10000 SUBGRADE COMPACTION | 696 SY | $1.00 | $3.00 | $2.00 |
| 606E17360 GUARDRAIL, TYPE MGS, LONG-SPAN | 100 FT | $20.00 | $25.00 | $21.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $55.50 |
| 4% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 39 CY | $298 | $300 | $290 | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 6,763 LB | $1.50 | $2.75 | $2.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $12,000 | $40,136 | 3% |
| 203E10000 EXCAVATION | 742 CY | $12.00 | $20.00 | $12.50 | 3% |
| 253E02000 PAVEMENT REPAIR | 20 CY | $385 | $250 | $215 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $5,400 | $8,350 | 2% |
| 512E33000 TYPE 2 WATERPROOFING | 333 SY | $20.00 | $20.00 | $19.50 | 2% |
| 659E00300 TOPSOIL | 248 CY | $25.00 | $30.00 | $53.00 | 2% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 78 CY | $75.00 | $100 | $76.50 | 2% |
| 606E15051 GUARDRAIL, TYPE MGS, AS PER PLAN | 300 FT | $18.75 | $23.00 | $20.50 | 2% |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 509 SY | $10.00 | $10.00 | $7.50 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 10 CY | $500 | $275 | $268 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,700 | $6,500 | $13,500 | 2% |
| 2 EACH |
| $2,280 |
| $2,725 |
| $2,498 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $980 | $1,085 | $1,015 |
| 623E38500 MONUMENT ASSEMBLY | 2 EACH | $500 | $600 | $1,038 |
| 659E10000 SEEDING AND MULCHING | 2,227 SY | $1.00 | $2.00 | $1.44 |
| 659E20000 COMMERCIAL FERTILIZER | 0.4 TON | $600 | $500 | $500 |
| 659E31000 LIME | 0.5 ACRE | $0.10 | $100 | $72.00 |
| 659E35000 WATER | 13 MGAL | $0.01 | $5.00 | $0.50 |
| 832E30000 EROSION CONTROL | 3,500 EACH | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 59 FT | $15.00 | $20.00 | $19.00 |
| 611E01500 6" CONDUIT, TYPE F | 31 FT | $14.00 | $30.00 | $40.50 |
| 611E02000 8" CONDUIT, TYPE C | 26 FT | $20.00 | $32.00 | $39.00 |
| 611E02500 8" CONDUIT, TYPE E | 20 FT | $14.00 | $30.00 | $25.47 |
| 611E03100 10" CONDUIT, TYPE B | 30 FT | $22.00 | $33.00 | $43.00 |
| 611E04600 12" CONDUIT, TYPE C | 49 FT | $40.00 | $50.00 | $63.50 |
| 611E04900 12" CONDUIT, TYPE D | 114 FT | $25.00 | $60.00 | $26.50 |
| 611E98450 CATCH BASIN, NO. 2-2A | 1 EACH | $1,500 | $1,300 | $2,007 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,500 | $1,600 | $2,312 |
| 407E10000 TACK COAT | 79 GAL | $2.00 | $2.25 | $2.10 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 2 EACH | $52.00 | $150 | $92.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2 EACH | $8.00 | $50.00 | $38.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 8 EACH | $10.00 | $15.00 | $7.50 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4 EACH | $15.00 | $50.00 | $20.50 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $20.00 | $50.00 | $20.50 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.22 MILE | $4,000 | $6,000 | $7,725 |
| 642E00300 CENTER LINE, TYPE 1 | 0.11 MILE | $8,000 | $10,000 | $7,725 |
| 407E10000 TACK COAT | 20 GAL | $2.00 | $2.00 | $2.15 |
| 616E10000 WATER | 1 MGAL | $10.00 | $1.00 | $180 |
| 617E10100 COMPACTED AGGREGATE | 50 CY | $60.00 | $50.00 | $96.50 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $3,500 | $6,000 | $16,500 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 79 SY | $25.00 | $55.00 | $23.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 30 SF | $10.00 | $10.00 | $10.50 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 30 CY | $70.00 | $100 | $94.50 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,200 | $4,000 | $25,627 |
| 619E16000 FIELD OFFICE, TYPE A | 2 MNTH | $700 | $1,000 | $630 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E95000 10' X 5' CONDUIT, TYPE A, 706.05, DESIGN EARTH COV | 112 FT | $825 | $92k | 26% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 97 CY | $255 | $25k | 7% |
| 511E46011 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 25 CY | $950 | $24k | 7% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 52 CY | $400 | $21k | 6% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 153 CY | $125 | $19k | 5% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $15,000 | $15k | 4% |
| 304E20000 AGGREGATE BASE | 226 CY | $55 | $12k | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 39 CY | $298 | $12k | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 6,763 LB | $1.5 | $10k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |