GRE-Culverts FY21
GRE County · est $0.3M
Bid dateThursday, January 14—
GRE County · est $0.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 4%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 23 more items below.
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Sunesis Construction CO | R4Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|
| 611E59100 103" X 71" CONDUIT, TYPE A, 707.02 ALUMINIZED | 36 FT | $742 | $650 | $1,058 | $668 | 12% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 265 SF | $83.25 | $105 | $135 | $54.50 | 10% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 42" CMP | 198 FT | $108 | $80.00 | $201 | $82.50 | 10% |
| 203E20000 EMBANKMENT | 472 CY | $41.63 | $35.00 | $35.52 | $34.50 | 9% |
| Item | Quantity | R1Bcc Ohio INC | R2Axis Civil Construction LLC | R3Sunesis Construction CO | R4Eclipse CO LLC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,170 | $7,500 | $7,286 | $24,276 |
| 202E32800 CONCRETE SLOPE PROTECTION REMOVED | 3.8 SY | $103 | $300 | $75.99 | $82.50 |
| 202E35200 PIPE REMOVED, OVER 24" | 10 FT | $97.50 | $150 | $103 | $28.50 |
| 202E70120 SPECIAL - PIPE CLEANOUT, 27" TO 48" | 198 FT | $7.80 | $40.00 | $58.14 | $68.00 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 611E96550 FIELD PAVING OF EXISTING PIPE, 103"x71" CMP |
| 99 FT |
| $194 |
| $130 |
| $182 |
| $180 |
| 9% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 54" CMP | 110 FT | $116 | $120 | $174 | $201 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $11,654 | $20,000 | $37,212 | $72,231 | 5% |
| 611E31000 102" CONDUIT, TYPE A, 707.03 | 10 FT | $1,087 | $350 | $1,232 | $1,056 | 5% |
| 602E20000 CONCRETE MASONRY | 7.1 CY | $1,246 | $960 | $2,138 | $1,107 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,580 | $15,000 | $16,514 | $55,000 | 4% |
| 203E20001 EMBANKMENT, AS PER PLAN | 110 CY | $68.63 | $35.00 | $76.92 | $38.50 | 3% |
| 611E98270 CATCH BASIN, NO. 4A | 1 EACH | $7,491 | $3,900 | $3,986 | $9,279 | 3% |
| 832E30000 EROSION CONTROL | 7,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 611E22200 54" CONDUIT, TYPE A, 707.05 | 8 FT | $842 | $450 | $804 | $602 | 3% |
| 601E11000 RIPRAP, TYPE D | 22 SY | $304 | $135 | $196 | $148 | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $4,388 | $15,000 | $46,559 | $184,918 | 2% |
| 659E10000 SEEDING AND MULCHING | 2,600 SY | $1.68 | $1.35 | $5.67 | $1.50 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 27 CY | $139 | $120 | $99.92 | $79.50 | 2% |
| 202E20010 HEADWALL REMOVED | 2 EACH | $1,770 | $1,600 | $351 | $1,455 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $52.50 | $65.00 | $65.00 | $63.00 | 1% |
| 635 FT |
| $2.69 |
| $22.00 |
| $58.86 |
| $74.50 |
| 202E75000 FENCE REMOVED | 112 FT | $2.93 | $2.00 | $3.71 | $6.50 |
| 202E98400 REMOVAL MISC.: EXISTING CONCRETE FIELD PAVING | 60 SF | $14.88 | $45.00 | $19.37 | $17.50 |
| 203E10000 EXCAVATION | 72 CY | $9.75 | $25.00 | $8.51 | $17.00 |
| 203E10001 EXCAVATION, AS PER PLAN | 110 CY | $19.50 | $25.00 | $32.67 | $26.50 |
| 605E31100 AGGREGATE DRAINS | 40 FT | $9.11 | $16.00 | $10.00 | $25.50 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $2,727 | $3,500 | $1,857 | $1,628 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $2,370 | $1,800 | $248 | $715 |
| 659E00300 TOPSOIL | 27 CY | $105 | $35.00 | $110 | $84.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.34 TON | $336 | $500 | $1,027 | $525 |
| 659E31000 LIME | 0.54 ACRE | $52.50 | $50.00 | $71.93 | $52.50 |
| 659E35000 WATER | 14.2 MGAL | $1.05 | $1.00 | $1.03 | $1.00 |
| 518E62200 STRUCTURE DRAINAGE, MISC.: RESEAL JOINT WITH HYDRO | 1 EACH | $1,626 | $1,500 | $2,056 | $1,315 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 5 CY | $177 | $280 | $136 | $143 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 25 CY | $82.05 | $95.00 | $111 | $81.50 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $26.25 | $15.00 | $25.00 | $26.50 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $42.00 | $15.00 | $25.00 | $47.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,017 | $3,500 | $3,134 | $13,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,040 | $4,500 | $9,818 | $14,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E59100 103" X 71" CONDUIT, TYPE A, 707.02 ALUMINIZED | 36 FT | $741.58 | $27k | 11% |
| 519E11100 PATCHING CONCRETE STRUCTURE | 265 SF | $83.25 | $22k | 9% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 42" CMP | 198 FT | $108.44 | $21k | 9% |
| 203E20000 EMBANKMENT | 472 CY | $41.63 | $20k | 8% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 103"x71" CMP | 99 FT | $194.17 | $19k | 8% |
| 611E96550 FIELD PAVING OF EXISTING PIPE, 54" CMP | 110 FT | $115.57 | $13k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $11,654 | $12k | 5% |
| 611E31000 102" CONDUIT, TYPE A, 707.03 | 10 FT | $1,087 | $11k | 4% |
| 602E20000 CONCRETE MASONRY | 7.1 CY | $1,246 | $9k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,580 | $9k | 4% |