PIK-SR 772-13.77 Slide Repair
PIK County · est $1.3M
Bid dateThursday, January 14—
PIK County · est $1.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 25 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Alan Stone CO INC | R3Allard Excavation LLC | R4D G M INC | R5George J Igel & CO INC | R6Complete General Construction Company | R7Suburban Maintenance & Construction | R8INC Ohio-west Virginia Excavating CO | R9Kokosing Construction Company INC | R10Dennison Bridge INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W24X131 | 4,624 FT | $70.00 | $75.00 | $79.93 | $83.50 | $88.50 | $85.00 | $77.00 | $76.00 | $93.75 | $92.00 |
| Item | Quantity | R1Shelly & Sands INC | R2Alan Stone CO INC | R3Allard Excavation LLC | R4D G M INC | R5George J Igel & CO INC | R6Complete General Construction Company | R7Suburban Maintenance & Construction | R8INC Ohio-west Virginia Excavating CO | R9Kokosing Construction Company INC | R10Dennison Bridge INC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 202E35100 PIPE REMOVED, 24" AND UNDER | 5 FT | $18.00 | $72.00 | $41.00 | $25.00 | $100 | $85.00 | $30.00 | $36.00 | $250 | $30.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 32% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 3,199 FT | $52.00 | $67.00 | $69.32 | $38.70 | $67.00 | $78.00 | $63.00 | $65.50 | $65.00 | $95.00 | 16% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 36" DIAMETER, UN | 2,855 FT | $52.00 | $67.00 | $70.44 | $34.50 | $67.00 | $68.00 | $62.00 | $71.25 | $65.00 | $82.00 | 15% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 1,500 FT | $71.00 | $78.00 | $81.15 | $171 | $85.00 | $104 | $118 | $112 | $112 | $135 | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,200 | $35,000 | $20,000 | $56,500 | $45,000 | $15,000 | $60,000 | $94,500 | $60,000 | $18,000 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $24,000 | $30,000 | $40,000 | $40,000 | $40,000 | $40,000 | $44,850 | $40,000 | $40,000 | 4% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 208 CY | $150 | $160 | $170 | $175 | $150 | $150 | $190 | $178 | $150 | $400 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 208 CY | $135 | $145 | $148 | $148 | $135 | $135 | $165 | $155 | $135 | $350 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,430 FT | $18.00 | $20.00 | $14.00 | $17.00 | $19.50 | $18.00 | $32.00 | $20.00 | $21.50 | $25.00 | 3% |
| 202E23000 PAVEMENT REMOVED | 1,179 SY | $14.00 | $6.00 | $11.87 | $5.00 | $14.00 | $10.00 | $10.00 | $10.00 | $12.00 | $12.00 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 862.5 FT | $18.00 | $20.50 | $17.48 | $18.00 | $16.40 | $17.60 | $20.00 | $17.00 | $18.00 | $20.00 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $3,200 | $800 | $1,200 | $1,200 | $2,800 | $2,500 | $900 | $2,690 | $500 | $2,000 | 1% |
| 304E20000 AGGREGATE BASE | 219 CY | $51.00 | $42.00 | $81.65 | $45.00 | $66.00 | $80.00 | $70.00 | $58.00 | $65.00 | $130 | 1% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $7,400 | $7,250 | $6,000 | $10,000 | $4,000 | $15,000 | $1,900 | $6,000 | $10,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,010 | $7,000 | $8,916 | $22,000 | $8,400 | $10,000 | $20,000 | $14,000 | $5,500 | $17,000 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,500 | $7,000 | $4,475 | $17,500 | $12,050 | $18,000 | $20,000 | $10,500 | $15,000 | $25,000 | 1% |
| 204E10000 SUBGRADE COMPACTION | 1,400 SY | $4.00 | $3.00 | $2.45 | $1.00 | $4.00 | $3.50 | $3.00 | $2.00 | $2.50 | $5.00 | 1% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,000 | $2,300 | $1,200 | $1,900 | $1,900 | $2,740 | $2,300 | $2,500 | $2,000 | $2,500 | 0% |
| 621E00100 RPM | 15 EACH | $220 | $244 | $169 | $170 | $197 | $220 | $250 | $230 | $230 | $275 | 0% |
| 202E38000 GUARDRAIL REMOVED | 861 FT | $2.50 | $3.00 | $2.75 | $1.00 | $1.60 | $1.80 | $1.50 | $3.00 | $2.50 | $2.00 |
| 203E10000 EXCAVATION | 24 CY | $15.00 | $15.00 | $19.00 | $20.00 | $60.00 | $25.00 | $15.00 | $19.00 | $18.00 | $25.00 |
| 203E20000 EMBANKMENT | 132 CY | $20.00 | $13.00 | $15.75 | $20.00 | $50.00 | $40.00 | $15.00 | $20.00 | $25.00 | $35.00 |
| 601E27000 DUMPED ROCK FILL, TYPE C | 5 CY | $110 | $96.00 | $72.30 | $120 | $215 | $105 | $150 | $160 | $425 | $150 |
| 659E10000 SEEDING AND MULCHING | 994 SY | $2.90 | $2.50 | $1.75 | $2.50 | $2.24 | $2.25 | $3.00 | $3.00 | $2.90 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $610 | $600 | $500 | $650 | $641 | $641 | $600 | $640 | $610 | $1,000 |
| 659E31000 LIME | 0.21 ACRE | $80.00 | $750 | $200 | $80.00 | $150 | $151 | $300 | $84.00 | $80.00 | $100 |
| 659E35000 WATER | 6 MGAL | $1.00 | $110 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $10.00 |
| 611E10200 24" CONDUIT, TYPE A, 707.33 | 8 FT | $175 | $273 | $118 | $125 | $550 | $110 | $160 | $99.00 | $310 | $300 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 1,226 FT | $0.25 | $2.00 | $1.00 | $1.00 | $2.95 | $2.25 | $3.25 | $2.00 | $3.40 | $4.00 |
| 407E20000 NON-TRACKING TACK COAT | 352 GAL | $3.25 | $3.50 | $3.25 | $3.25 | $3.25 | $3.25 | $4.00 | $3.00 | $3.25 | $10.00 |
| 408E10000 PRIME COAT | 107 GAL | $6.00 | $6.00 | $4.00 | $6.00 | $6.00 | $6.00 | $5.00 | $4.00 | $6.00 | $25.00 |
| 617E10100 COMPACTED AGGREGATE | 6 CY | $150 | $116 | $66.32 | $125 | $420 | $102 | $125 | $115 | $370 | $150 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 15 EACH | $12.00 | $31.50 | $9.95 | $1.00 | $20.00 | $22.00 | $75.00 | $19.00 | $30.00 | $20.00 |
| 626E00112 BARRIER REFLECTOR, TYPE 3 (BIDIRECTIONAL) | 18 EACH | $10.00 | $12.00 | $17.00 | $10.00 | $8.90 | $9.00 | $20.00 | $52.00 | $10.00 | $10.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.46 MILE | $2,650 | $3,000 | $919 | $2,800 | $3,785 | $2,650 | $3,000 | $2,780 | $2,650 | $4,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.23 MILE | $4,795 | $5,300 | $1,200 | $5,500 | $4,825 | $4,795 | $5,000 | $5,000 | $4,795 | $5,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 29 EACH | $8.00 | $10.50 | $10.00 | $15.00 | $12.00 | $12.00 | $35.00 | $31.00 | $10.00 | $15.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 29 EACH | $12.00 | $33.00 | $10.00 | $15.00 | $15.00 | $32.00 | $35.00 | $33.00 | $25.00 | $25.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 0.19 MILE | $5,595 | $6,100 | $5,595 | $8,200 | $5,265 | $5,595 | $6,500 | $5,595 | $5,595 | $6,500 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.27 MILE | $3,995 | $4,500 | $3,995 | $4,200 | $3,230 | $3,995 | $4,500 | $4,100 | $3,995 | $4,000 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 26 FT | $12.50 | $14.00 | $12.50 | $7.00 | $2.50 | $12.50 | $15.00 | $13.00 | $12.50 | $5.00 |
| 616E10000 WATER | 2 MGAL | $32.00 | $0.60 | $1.00 | $1.00 | $100 | $125 | $1.00 | $10.00 | $250 | $50.00 |
| 530E00400 SPECIAL - STRUCTURES, CAST-IN-PLACE CONCRETE PANEL | 1 EACH | $2,100 | $3,500 | $5,977 | $3,000 | $6,500 | $5,000 | $2,000 | $3,000 | $3,500 | $2,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W24X131 | 4,624 FT | $70 | $324k | 31% |
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 3,199 FT | $52 | $166k | 16% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILE, 36" DIAMETER, UN | 2,855 FT | $52 | $148k | 14% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 1,500 FT | $71 | $107k | 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,200 | $50k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 208 CY | $150 | $31k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 208 CY | $135 | $28k | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 1,430 FT | $18 | $26k | 2% |
| 202E23000 PAVEMENT REMOVED | 1,179 SY | $14 | $17k | 2% |