HAM-Winton Woods Park
HAM County · est $0.4M
Bid dateThursday, January 14—
HAM County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 12 more items below.
| Item | Quantity | R1Scioto Valley Paving | R2Barrett Paving Materials INC | R3B&b Sealing LLC | R4John R Jurgensen Company | R5Rack & Ballauer Excavating CO INC | R6Roberts Paving INC | R7Fillmore Construction | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 988 CY | $180 | $150 | $169 | $172 | $183 | $181 | $184 | 46% |
| 609E98100 CURB, MISC.: CONCRETE PARKING BLOCK | 373 EACH | $100 | $125 | $53.49 | $100 | $115 | $89.00 | $80.00 | 10% |
| 609E98000 |
| Item | Quantity | R1Scioto Valley Paving | R2Barrett Paving Materials INC | R3B&b Sealing LLC | R4John R Jurgensen Company | R5Rack & Ballauer Excavating CO INC | R6Roberts Paving INC | R7Fillmore Construction |
|---|---|---|---|---|---|---|---|---|
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" | 197 SY | $1.22 | $12.00 | $10.24 | $3.00 | $6.40 | $3.50 | $5.00 |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (4 CY | $175 | $360 | $169 | $250 | $200 | $190 | $500 |
| 630E80100 SIGN, FLAT SHEET |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 780 FT |
| $40.00 |
| $12.00 |
| $11.56 |
| $12.00 |
| $12.00 |
| $12.91 |
| $20.00 |
| 8% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 118 CY | $160 | $160 | $172 | $205 | $255 | $190 | $200 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1" | 23,451 SY | $0.75 | $1.85 | $2.51 | $1.65 | $1.95 | $2.25 | $2.00 | 5% |
| 202E52990 SPECIAL - PARKING BLOCK REMOVED | 531 EACH | $30.00 | $25.00 | $4.51 | $23.00 | $25.00 | $25.00 | $10.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $20,000 | $10,000 | $8,500 | $6,500 | $4,500 | $4,500 | 3% |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN, C | 140 FT | $70.00 | $58.75 | $15.00 | $58.00 | $55.00 | $74.00 | $20.00 | 3% |
| 203E10001 EXCAVATION, AS PER PLAN | 310 CY | $30.00 | $75.00 | $25.94 | $70.00 | $55.00 | $97.00 | $100 | 2% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 185 CY | $50.00 | $100 | $69.36 | $170 | $75.00 | $65.04 | $200 | 2% |
| 642E01200 PARKING LOT STALL MARKING, TYPE 1 | 10,690 FT | $0.85 | $0.85 | $0.98 | $0.99 | $0.37 | $0.92 | $0.90 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $2,000 | $6,300 | $2,000 | $3,500 | $4,250 | $4,500 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 1,767 GAL | $4.00 | $3.00 | $4.75 | $1.00 | $1.00 | $3.84 | $4.00 | 2% |
| 609E98000 CURB, MISC.: INTEGRAL CONCRETE CURB | 140 FT | $50.00 | $12.00 | $58.39 | $46.00 | $23.75 | $13.20 | $40.00 | 2% |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 53 CY | $125 | $125 | $116 | $64.58 | $125 | $100 | $500 | 2% |
| 608E12000 5" CONCRETE WALK | 1,100 SF | $6.00 | $7.00 | $16.37 | $8.00 | $8.50 | $7.90 | $10.00 | 2% |
| 659E00501 SEEDING AND MULCHING, CLASS 1, AS PER PLAN | 1,535 SY | $2.10 | $2.10 | $4.00 | $2.00 | $2.10 | $2.30 | $5.00 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,500 | $5,780 | $1,000 | $7,000 | $6,000 | $4,000 | $17,500 | 1% |
| 608E52000 CURB RAMP, TYPE B2 | 85 SF | $25.00 | $30.00 | $30.00 | $15.00 | $46.00 | $31.00 | $14.00 | 1% |
| 644E00500 STOP LINE | 131 FT | $11.75 | $11.75 | $13.51 | $12.00 | $8.00 | $12.14 | $7.63 | 0% |
| 28 SF |
| $25.00 |
| $36.00 |
| $30.00 |
| $36.00 |
| $50.00 |
| $25.50 |
| $25.00 |
| 630E86003 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 12 EACH | $25.00 | $25.00 | $75.00 | $25.00 | $25.00 | $28.00 | $25.00 |
| 642E00300 CENTER LINE, TYPE 1 | 0.27 MILE | $1,800 | $1,800 | $2,070 | $1,800 | $3,100 | $1,450 | $1,427 |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 220 FT | $0.75 | $0.75 | $86.00 | $0.87 | $0.65 | $0.86 | $1.95 |
| 642E00701 TRANSVERSE/DIAGONAL LINE, TYPE 1, AS PER PLAN 4" | 1,330 FT | $1.10 | $1.10 | $1.26 | $1.28 | $0.35 | $3.10 | $4.65 |
| 642E01410 WORD ON PAVEMENT, 96", TYPE 1 | 4 EACH | $86.00 | $86.00 | $98.90 | $86.00 | $75.00 | $98.00 | $168 |
| 642E01703 HANDICAP SYMBOL MARKING, TYPE 1, AS PER PLAN | 14 EACH | $104 | $104 | $119 | $105 | $30.00 | $95.00 | $162 |
| 644E00600 CROSSWALK LINE | 180 FT | $5.87 | $5.87 | $6.75 | $6.00 | $6.50 | $6.20 | $5.73 |
| 644E01300 LANE ARROW | 2 EACH | $137 | $137 | $158 | $135 | $90.00 | $146 | $186 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $1,500 | $3,000 | $2,500 | $2,000 | $4,500 | $3,500 | $2,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 988 CY | $180 | $178k | 45% |
| 609E98100 CURB, MISC.: CONCRETE PARKING BLOCK | 373 EACH | $100 | $37k | 9% |
| 609E98000 CURB, MISC.: EXTRUDED CONCRETE CURB | 780 FT | $40 | $31k | 8% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 118 CY | $160 | $19k | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1" | 23,451 SY | $0.75 | $18k | 4% |
| 202E52990 SPECIAL - PARKING BLOCK REMOVED | 531 EACH | $30 | $16k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN, C | 140 FT | $70 | $10k | 2% |
| 203E10001 EXCAVATION, AS PER PLAN | 310 CY | $30 | $9k | 2% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 185 CY | $50 | $9k | 2% |