TRU-Warner Rd Bridge
TRU County · est $1.5M
Bid dateThursday, February 11—
TRU County · est $1.5M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 81 more items below.
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2A P O'horo Company | R3Stanley Miller Construction Company | R4Shelly & Sands INC | R5Suburban Maintenance & Construction | R6INC Jet Excavating Company | R7Lockhart Concrete CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 513E10261 STRUCTURAL STEEL MEMBERS, LEVEL 3, AS PER PLAN | 48,078 LB | $1.85 | $1.89 | $2.41 | $2.25 | $2.25 | $2.30 | $2.50 | 10% |
| 511E43512 CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT INCLUDING | 162 CY | $500 | $400 | $391 | $625 | $450 | $585 | $1,070 | 10% |
| Item | Quantity | R1Marucci & Gaffney Excavating CO | R2A P O'horo Company | R3Stanley Miller Construction Company | R4Shelly & Sands INC | R5Suburban Maintenance & Construction | R6INC Jet Excavating Company | R7Lockhart Concrete CO |
|---|---|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 2,038 SY | $4.00 | $2.85 | $3.40 | $4.50 | $15.00 | $4.50 | $4.00 |
| 202E23500 WEARING COURSE REMOVED | 89 SY | $10.00 | $2.85 | $1.60 | $10.00 | $18.00 | $18.00 | $20.00 |
| 202E32000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 511E21522 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 132 CY | $585 | $715 | $653 | $900 | $500 | $875 | $950 | 9% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 58,790 LB | $1.11 | $1.09 | $1.19 | $1.16 | $1.20 | $1.20 | $1.06 | 8% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 3,200 SY | $16.50 | $14.00 | $22.22 | $20.00 | $7.00 | $16.75 | $20.00 | 6% |
| 524E94804 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK | 60 FT | $730 | $485 | $350 | $300 | $450 | $725 | $450 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $28,078 | $40,000 | $40,000 | $40,000 | $37,000 | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 260 CY | $145 | $145 | $189 | $150 | $200 | $175 | $145 | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 222 FT | $168 | $163 | $181 | $160 | $160 | $175 | $178 | 4% |
| 511E41012 CLASS QC1 CONCRETE WITH QC/QA, PIER ABOVE FOOTINGS | 42 CY | $860 | $900 | $814 | $1,820 | $1,000 | $1,100 | $1,280 | 4% |
| 203E40000 BORROW | 1,404 CY | $25.00 | $15.00 | $27.76 | $12.00 | $22.00 | $45.00 | $40.00 | 4% |
| 203E20000 EMBANKMENT | 4,403 CY | $7.85 | $6.00 | $5.30 | $5.25 | $12.00 | $12.50 | $20.00 | 4% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 167 SY | $200 | $225 | $244 | $275 | $250 | $275 | $185 | 4% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $30,000 | $50,000 | $2,167 | $15,000 | $10,000 | $75,000 | $40,000 | 4% |
| 203E10000 EXCAVATION | 4,403 CY | $6.35 | $8.00 | $8.93 | $10.00 | $13.00 | $12.50 | $20.00 | 3% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 396 CY | $70.00 | $58.00 | $92.00 | $98.00 | $110 | $85.00 | $130 | 3% |
| 524E94704 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK | 72 FT | $385 | $360 | $267 | $250 | $420 | $545 | $349 | 3% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 408 CY | $65.00 | $68.00 | $83.00 | $68.00 | $70.00 | $80.00 | $55.00 | 3% |
| 524E94902 DRILLED SHAFTS, 48" DIAMETER, ABOVE BEDROCK | 83 FT | $303 | $510 | $350 | $260 | $330 | $515 | $450 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $22,000 | $10,000 | $74,467 | $22,000 | $30,000 | $20,000 | $27,000 | 3% |
| 15 FT |
| $2.00 |
| $6.00 |
| $3.00 |
| $5.60 |
| $15.00 |
| $25.00 |
| $20.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 104 FT | $5.00 | $11.00 | $17.80 | $16.00 | $8.00 | $12.00 | $2.00 |
| 202E38000 GUARDRAIL REMOVED | 320 FT | $1.85 | $1.85 | $2.00 | $1.85 | $2.00 | $3.00 | $1.85 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $50.00 | $150 | $202 | $225 | $350 | $250 | $200 |
| 202E75000 FENCE REMOVED | 384 FT | $2.00 | $1.50 | $4.19 | $3.75 | $4.00 | $2.50 | $2.00 |
| 203E65000 SPECIAL - SETTLEMENT PLATFORM | 2 EACH | $1,500 | $2,100 | $250 | $850 | $3,000 | $1,250 | $1,500 |
| 204E10000 SUBGRADE COMPACTION | 3,165 SY | $1.50 | $1.75 | $1.00 | $3.15 | $3.00 | $1.00 | $2.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 50 CY | $10.00 | $15.00 | $13.34 | $18.00 | $30.00 | $15.00 | $15.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 50 CY | $40.00 | $60.00 | $38.90 | $60.00 | $85.00 | $55.00 | $35.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $80.00 | $300 | $90.00 | $150 | $500 | $100 | $150 |
| 204E50000 GEOTEXTILE FABRIC | 130 SY | $2.00 | $2.00 | $2.70 | $2.25 | $2.50 | $2.00 | $2.80 |
| 606E15050 GUARDRAIL, TYPE MGS | 575 FT | $16.80 | $15.90 | $17.67 | $16.80 | $16.00 | $16.75 | $15.90 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 3 EACH | $1,840 | $2,125 | $2,361 | $1,840 | $1,900 | $2,200 | $2,125 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $970 | $885 | $983 | $970 | $1,100 | $925 | $885 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,120 | $2,175 | $2,417 | $2,120 | $2,100 | $2,275 | $2,175 |
| 606E98000 GUARDRAIL, MISC.: CURVED GUARDRAIL PANELS, TYPE MG | 25 FT | $21.60 | $150 | $167 | $22.00 | $15.00 | $155 | $150 |
| 623E38500 MONUMENT ASSEMBLY | 4 EACH | $1,100 | $775 | $750 | $1,300 | $650 | $1,000 | $950 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 2 EACH | $145 | $145 | $150 | $145 | $300 | $150 | $100 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 137 SY | $25.00 | $25.00 | $31.00 | $30.00 | $90.00 | $45.00 | $20.00 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 26 CY | $70.00 | $100 | $123 | $110 | $150 | $125 | $150 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 12 CY | $70.00 | $115 | $153 | $120 | $120 | $150 | $150 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $10.00 | $25.00 | $100 | $88.00 | $100 | $50.00 | $250 |
| 659E00300 TOPSOIL | 659 CY | $18.00 | $12.00 | $33.25 | $21.00 | $30.00 | $30.00 | $40.00 |
| 659E10000 SEEDING AND MULCHING | 5,121 SY | $1.00 | $1.50 | $1.36 | $0.73 | $0.83 | $1.25 | $2.78 |
| 659E14000 REPAIR SEEDING AND MULCHING | 256 SY | $0.20 | $1.00 | $1.00 | $0.69 | $1.00 | $1.00 | $1.00 |
| 659E15000 INTER-SEEDING | 256 SY | $0.20 | $0.10 | $0.75 | $0.69 | $0.05 | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.71 TON | $400 | $400 | $600 | $651 | $800 | $800 | $995 |
| 659E31000 LIME | 1.06 ACRE | $50.00 | $20.00 | $150 | $154 | $0.10 | $500 | $200 |
| 659E35000 WATER | 15 MGAL | $0.50 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $17.00 |
| 670E00500 SLOPE EROSION PROTECTION | 1,470 SY | $3.00 | $2.50 | $2.72 | $1.34 | $3.00 | $3.00 | $2.00 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 546 SY | $3.00 | $2.00 | $2.13 | $1.49 | $4.00 | $4.00 | $2.25 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $8,000 | $2,500 | $2,225 | $1,500 | $3,000 | $2,300 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $5,000 | $500 | $2,889 | $5,200 | $4,800 | $6,000 | $4,900 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $6,800 | $8,000 | $1,500 | $6,758 | $6,800 | $7,000 | $11,000 |
| 832E30000 EROSION CONTROL | 12,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.21 CY | $2,500 | $1,100 | $2,138 | $2,820 | $2,000 | $5,000 | $2,700 |
| 605E31100 AGGREGATE DRAINS | 441 FT | $15.00 | $16.00 | $13.80 | $12.00 | $8.00 | $13.00 | $9.50 |
| 611E04400 12" CONDUIT, TYPE B | 81 FT | $60.00 | $45.00 | $27.60 | $62.00 | $65.00 | $75.00 | $73.00 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,500 | $1,250 | $2,014 | $2,240 | $1,500 | $2,100 | $1,175 |
| 407E10000 TACK COAT | 118 GAL | $3.50 | $3.50 | $3.34 | $2.00 | $2.20 | $3.50 | $3.50 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 75 CY | $200 | $200 | $289 | $237 | $267 | $250 | $200 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (5 CY | $315 | $315 | $333 | $500 | $196 | $325 | $315 |
| 617E10100 COMPACTED AGGREGATE | 73 CY | $68.00 | $80.00 | $104 | $95.00 | $65.00 | $90.00 | $70.00 |
| 690E98400 SPECIAL - VIDEO DOCUMENTATION OF HAUL ROUTES | 1 LS | $1,000 | $250 | $2,667 | $3,000 | $14,000 | $2,500 | $5,000 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 23 EACH | $8.00 | $8.00 | $8.89 | $8.00 | $7.00 | $10.00 | $10.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 32.8 FT | $20.00 | $8.10 | $9.00 | $27.50 | $16.00 | $10.00 | $8.10 |
| 630E80100 SIGN, FLAT SHEET | 6.5 SF | $30.00 | $37.75 | $41.94 | $26.00 | $40.00 | $40.00 | $37.75 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $65.00 | $86.70 | $96.33 | $45.00 | $50.00 | $75.00 | $87.00 |
| 630E85200 REMOVAL OF GROUND MOUNTED SIGN AND DELIVERY | 27 EACH | $22.00 | $35.00 | $38.83 | $14.50 | $25.00 | $25.00 | $35.00 |
| 630E86050 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DELIVER | 20 EACH | $25.00 | $43.00 | $47.61 | $24.50 | $25.00 | $25.00 | $43.00 |
| 646E10000 EDGE LINE, 4" | 0.36 MILE | $8,500 | $6,450 | $27,000 | $6,500 | $6,450 | $9,000 | $8,500 |
| 646E10200 CENTER LINE | 0.18 MILE | $20,000 | $6,900 | $31,000 | $6,900 | $6,900 | $21,000 | $20,000 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $20.00 | $75.00 | $80.60 | $80.00 | $50.00 | $35.00 | $150 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,500 | $10,000 | $6,089 | $3,900 | $12,000 | $4,500 | $5,480 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $50.00 | $140 | $125 | $225 | $150 | $150 | $200 |
| 616E10000 WATER | 1 MGAL | $1.00 | $50.00 | $1.00 | $32.00 | $3,000 | $1.00 | $50.00 |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $20,000 | $75,000 | $10,611 | $20,000 | $98,000 | $75,000 | $70,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $10,000 | $15,000 | $40,556 | $15,000 | $50,000 | $20,000 | $35,000 |
| 503E21100 UNCLASSIFIED EXCAVATION | 183 CY | $30.00 | $58.00 | $23.00 | $28.50 | $90.00 | $45.00 | $25.00 |
| 511E33500 SEMI-INTEGRAL DIAPHRAGM GUIDE | 2 EACH | $2,250 | $2,200 | $3,159 | $2,500 | $1,500 | $3,000 | $1,450 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 302 SY | $22.50 | $25.00 | $28.00 | $25.00 | $18.00 | $26.00 | $6.75 |
| 513E20000 WELDED STUD SHEAR CONNECTORS | 1,764 EACH | $3.40 | $3.40 | $4.35 | $4.25 | $4.00 | $5.00 | $7.50 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 28 SF | $8.00 | $5.00 | $24.00 | $9.00 | $15.00 | $20.00 | $22.80 |
| 516E25000 NYLON REINFORCED NEOPRENE SHEETING | 300 SF | $10.00 | $8.00 | $9.35 | $9.00 | $2.00 | $9.00 | $8.15 |
| 516E44200 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 8 EACH | $860 | $750 | $1,449 | $1,236 | $1,100 | $1,125 | $910 |
| 516E44201 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 8 EACH | $785 | $950 | $1,373 | $981 | $850 | $825 | $835 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 88 CY | $85.00 | $75.00 | $92.00 | $93.00 | $90.00 | $75.00 | $55.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 251 FT | $15.00 | $11.00 | $12.62 | $13.50 | $12.00 | $15.00 | $10.45 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 152 FT | $12.00 | $10.00 | $3.00 | $7.00 | $8.00 | $12.00 | $15.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 16 FT | $12.00 | $11.00 | $20.00 | $8.00 | $8.00 | $20.00 | $35.00 |
| 524E94604 DRILLED SHAFTS, 30" DIAMETER, INTO BEDROCK | 30 FT | $490 | $280 | $196 | $600 | $400 | $600 | $349 |
| 524E94702 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK | 63 FT | $145 | $280 | $196 | $200 | $300 | $255 | $349 |
| 524E94802 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK | 27 FT | $209 | $320 | $267 | $450 | $330 | $370 | $349 |
| 526E90010 TYPE A INSTALLATION | 69 FT | $100 | $100 | $97.00 | $190 | $120 | $145 | $95.00 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $6,000 | $2,000 | $5,000 | $6,100 | $2,000 | $2,500 | $10,000 |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 30 CF | $453 | $450 | $350 | $475 | $475 | $475 | $567 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $11,000 | $24,629 | $14,000 | $7,700 | $20,000 | $29,000 | $30,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $5,000 | $4,089 | $5,500 | $5,000 | $5,000 | $10,000 |
| 619E16010 FIELD OFFICE, TYPE B | 7 MNTH | $750 | $1,000 | $800 | $2,900 | $2,000 | $1,200 | $1,100 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 513E10261 STRUCTURAL STEEL MEMBERS, LEVEL 3, AS PER PLAN | 48,078 LB | $1.85 | $89k | 8% |
| 511E43512 CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT INCLUDING | 162 CY | $500 | $81k | 7% |
| 511E21522 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 132 CY | $585 | $77k | 7% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 58,790 LB | $1.11 | $65k | 6% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 3,200 SY | $16.5 | $53k | 5% |
| 524E94804 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK | 60 FT | $730 | $44k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 260 CY | $145 | $38k | 3% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 222 FT | $168 | $37k | 3% |
| 511E41012 CLASS QC1 CONCRETE WITH QC/QA, PIER ABOVE FOOTINGS | 42 CY | $860 | $36k | 3% |