TUS-US 250-20.33
TUS County · est $1.4M
Bid dateThursday, April 1—
TUS County · est $1.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 55 more items below.
| Item | Quantity | R1Ruhlin Company | R2Complete General Construction Company | R3Shelly & Sands INC | R4Armstrong Steel Erectors INC | R5George J Igel & CO INC | R6Rietschlin Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 513E10260 STRUCTURAL STEEL MEMBERS, LEVEL 3 | 192,298 LB | $1.71 | $1.60 | $1.80 | $1.55 | $1.60 | $1.75 | 30% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 209 CY | $650 | $875 | $850 | $1,200 | $940 | $805 | 12% |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 78,011 LB | $1.35 | $1.20 | $1.14 |
| Item | Quantity | R1Ruhlin Company | R2Complete General Construction Company | R3Shelly & Sands INC | R4Armstrong Steel Erectors INC | R5George J Igel & CO INC | R6Rietschlin Construction INC |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $5,000 | $9,500 | $4,930 | $5,400 | $12,000 |
| 202E23000 PAVEMENT REMOVED | 575 SY | $10.00 | $10.00 | $8.00 | $10.00 | $13.91 | $10.00 |
| 202E38000 GUARDRAIL REMOVED | 580 FT | $2.00 | $2.00 | $2.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1.10 |
| $1.20 |
| $1.25 |
| 10% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $90,000 | $85,000 | $75,000 | $110,040 | $142,700 | $140,000 | 8% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 98 CY | $650 | $700 | $845 | $465 | $620 | $465 | 6% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 174 SY | $250 | $225 | $367 | $285 | $270 | $250 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,000 | $35,000 | $19,000 | $31,000 | $17,000 | $20,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $40,000 | $40,000 | $40,000 | $65,000 | 4% |
| 511E34450 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 75 CY | $450 | $500 | $430 | $540 | $635 | $625 | 3% |
| 607E39900 VANDAL PROTECTION FENCE, 6' STRAIGHT, COATED FABRI | 390 FT | $78.70 | $78.70 | $70.00 | $85.00 | $70.00 | $85.00 | 3% |
| 519E00100 SPECIAL - COMPOSITE FIBER WRAP SYSTEM (SEE PROPOSA | 838 SF | $35.00 | $55.00 | $55.00 | $30.00 | $55.00 | $56.00 | 3% |
| 511E43210 CLASS QC1 CONCRETE, PIER | 17 CY | $1,500 | $1,750 | $2,200 | $1,265 | $930 | $1,800 | 2% |
| 503E21100 UNCLASSIFIED EXCAVATION | 228 CY | $85.00 | $75.00 | $70.00 | $130 | $135 | $160 | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 92 CY | $209 | $180 | $200 | $175 | $175 | $227 | 2% |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 964 SY | $18.00 | $20.00 | $20.00 | $20.00 | $20.00 | $22.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $16,500 | $4,000 | $11,000 | $5,000 | $8,000 | $8,000 | 2% |
| 513E20000 WELDED STUD SHEAR CONNECTORS | 4,290 EACH | $3.80 | $3.80 | $4.25 | $3.80 | $3.80 | $4.10 | 1% |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 10 EACH | $1,500 | $1,500 | $1,316 | $1,013 | $1,300 | $1,150 | 1% |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 15 EACH | $950 | $700 | $742 | $579 | $725 | $650 | 1% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 41 CY | $335 | $443 | $325 | $430 | $430 | $362 | 1% |
| $2.50 |
| $2.00 |
| $4.00 |
| 202E47000 BRIDGE TERMINAL ASSEMBLY REMOVED | 4 EACH | $75.00 | $75.00 | $75.00 | $150 | $75.00 | $275 |
| 202E75000 FENCE REMOVED | 137 FT | $2.50 | $2.50 | $2.50 | $15.00 | $2.50 | $3.00 |
| 203E10000 EXCAVATION | 33 CY | $40.00 | $10.00 | $23.00 | $22.00 | $25.00 | $51.00 |
| 203E20000 EMBANKMENT | 172 CY | $20.00 | $15.00 | $5.25 | $30.00 | $13.00 | $18.00 |
| 204E10000 SUBGRADE COMPACTION | 568 SY | $4.00 | $6.00 | $4.25 | $17.50 | $5.50 | $2.50 |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 475 FT | $26.80 | $26.80 | $26.80 | $20.00 | $26.80 | $29.00 |
| 606E35000 BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $1,020 | $1,020 | $1,020 | $2,200 | $1,020 | $1,102 |
| 607E15000 FENCE, TYPE 47 | 97 FT | $28.50 | $28.50 | $28.50 | $25.00 | $28.50 | $31.00 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 181 SY | $56.05 | $50.00 | $62.00 | $40.00 | $55.00 | $47.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $92.00 | $100 | $92.00 | $92.00 | $92.00 | $54.00 |
| 659E00300 TOPSOIL | 28 CY | $25.00 | $20.00 | $64.00 | $103 | $14.00 | $63.00 |
| 659E10000 SEEDING AND MULCHING | 334 SY | $5.51 | $7.00 | $5.51 | $5.51 | $9.00 | $8.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 13 SY | $0.68 | $7.00 | $0.72 | $0.68 | $0.68 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.03 TON | $695 | $610 | $695 | $695 | $695 | $900 |
| 659E31000 LIME | 0.01 ACRE | $662 | $80.00 | $665 | $662 | $662 | $100 |
| 659E35000 WATER | 1 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $20.00 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 234 FT | $10.00 | $15.00 | $12.00 | $10.00 | $25.00 | $10.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=1.5") | 1,300 SY | $5.00 | $4.85 | $9.00 | $6.10 | $8.00 | $7.10 |
| 304E20000 AGGREGATE BASE | 159 CY | $65.00 | $75.00 | $70.00 | $102 | $95.00 | $104 |
| 407E10000 TACK COAT | 68 GAL | $2.75 | $3.61 | $3.00 | $3.50 | $3.50 | $3.00 |
| 408E10000 PRIME COAT | 82 GAL | $4.50 | $41.24 | $20.00 | $40.00 | $40.00 | $5.00 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (29 CY | $242 | $186 | $300 | $180 | $180 | $261 |
| 609E24500 CURB, TYPE 4-B | 76 FT | $25.00 | $75.00 | $57.00 | $30.00 | $28.00 | $22.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 16 EACH | $7.50 | $7.50 | $7.50 | $10.00 | $7.50 | $9.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 17 FT | $25.00 | $25.00 | $25.00 | $12.50 | $25.00 | $27.00 |
| 630E80100 SIGN, FLAT SHEET | 2 SF | $35.00 | $35.00 | $35.00 | $50.00 | $35.00 | $38.00 |
| 646E10000 EDGE LINE, 4" | 0.7 MILE | $3,600 | $3,600 | $4,582 | $3,600 | $4,582 | $5,000 |
| 646E10200 CENTER LINE | 0.6 MILE | $3,850 | $3,850 | $8,658 | $3,850 | $8,658 | $9,400 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $65.00 | $80.00 | $72.00 | $90.00 | $73.50 | $72.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $4,956 | $5,000 | $3,800 | $3,775 | $3,775 | $4,100 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.5 MILE | $2,360 | $2,360 | $1,800 | $1,800 | $1,800 | $1,944 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 1 MILE | $2,360 | $2,360 | $900 | $900 | $900 | $972 |
| 202E22900 APPROACH SLAB REMOVED | 156 SY | $35.00 | $40.00 | $27.00 | $45.00 | $38.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED (3" THICKNESS) | 692 SY | $12.00 | $15.00 | $7.00 | $10.00 | $6.00 | $5.00 |
| 510E10001 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT, AS | 268 EACH | $22.00 | $20.00 | $25.00 | $22.50 | $25.00 | $23.50 |
| 511E33501 SEMI-INTEGRAL DIAPHRAGM GUIDE, AS PER PLAN | 4 EACH | $1,500 | $750 | $2,500 | $1,000 | $1,000 | $1,100 |
| 512E33000 TYPE 2 WATERPROOFING | 11 SY | $35.00 | $75.00 | $36.00 | $120 | $30.00 | $72.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 222 SY | $35.00 | $23.50 | $25.00 | $10.00 | $23.50 | $25.50 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 58 FT | $40.00 | $75.00 | $75.00 | $70.00 | $65.00 | $81.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 16 SF | $7.00 | $40.00 | $12.00 | $8.00 | $10.00 | $26.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 37 SF | $9.00 | $7.00 | $12.00 | $12.00 | $15.00 | $14.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 82 FT | $40.00 | $42.00 | $30.00 | $30.00 | $32.00 | $28.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 67 CY | $100 | $150 | $105 | $120 | $130 | $86.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 105 FT | $16.00 | $8.00 | $2.50 | $8.50 | $15.00 | $14.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 32 FT | $23.00 | $20.00 | $8.00 | $12.50 | $20.00 | $23.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 2 SF | $1,500 | $150 | $600 | $905 | $521 | $1,580 |
| 526E90030 TYPE C INSTALLATION | 58 FT | $165 | $200 | $267 | $290 | $180 | $160 |
| 601E20001 CRUSHED AGGREGATE SLOPE PROTECTION, AS PER PLAN | 311 SY | $25.00 | $20.00 | $29.00 | $50.00 | $34.00 | $30.00 |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 10 SF | $200 | $140 | $140 | $125 | $140 | $215 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,500 | $13,000 | $7,900 | $15,000 | $8,000 | $12,000 |
| 619E16010 FIELD OFFICE, TYPE B | 5 MNTH | $2,500 | $2,000 | $2,900 | $1,700 | $1,930 | $1,400 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 513E10260 STRUCTURAL STEEL MEMBERS, LEVEL 3 | 192,298 LB | $1.71 | $329k | 25% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 209 CY | $650 | $136k | 10% |
| 509E10001 EPOXY COATED REINFORCING STEEL, AS PER PLAN | 78,011 LB | $1.35 | $105k | 8% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $90,000 | $90k | 7% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 98 CY | $650 | $64k | 5% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 174 SY | $250 | $44k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,000 | $40k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 511E34450 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK (PARAPE | 75 CY | $450 | $34k | 3% |
| 607E39900 VANDAL PROTECTION FENCE, 6' STRAIGHT, COATED FABRI | 390 FT | $78.7 | $31k | 2% |