| Item | Quantity | R1Coopers Excavating LLC | R2Axis Civil Construction LLC | R3Eclipse CO LLC | R4Sunesis Construction CO | R5John R Jurgensen Company | % of bid |
|---|---|---|---|---|---|---|---|
| 601E25001 DUMPED ROCK FILL, TYPE A, AS PER PLAN | 1,790 CY | $55.00 | $78.00 | $68.50 | $87.49 | $127 | 37% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $20,000 | $16,559 | $16,135 | $20,000 | 9% |
| 203E10000 EXCAVATION | 1,500 CY | $15.50 | $35.00 | $28.00 | $41.57 | $35.68 | 9% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM |
| Item | Quantity | R1Coopers Excavating LLC | R2Axis Civil Construction LLC | R3Eclipse CO LLC | R4Sunesis Construction CO | R5John R Jurgensen Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,700 | $5,000 | $4,505 | $16,807 | $10,219 |
| 202E35200 PIPE REMOVED, OVER 24" | 12 FT | $20.00 | $100 | $30.50 | $24.39 | $220 |
| 202E38000 GUARDRAIL REMOVED | 207 FT | $5.00 | $5.00 | $6.50 | $6.00 | $6.00 |
| 204E10000 SUBGRADE COMPACTION | 137 SY | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $20,000 |
| $3,500 |
| $9,500 |
| $3,035 |
| $668 |
| 7% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 480 FT | $26.00 | $28.00 | $28.50 | $26.00 | $28.12 | 5% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 337.5 FT | $24.76 | $24.25 | $26.50 | $24.25 | $24.25 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 20 CY | $410 | $320 | $709 | $365 | $357 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 19 CY | $410 | $260 | $507 | $366 | $535 | 3% |
| 618E40800 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 920 FT | $8.00 | $5.50 | $6.00 | $10.44 | $5.50 | 3% |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.75 MILE | $8,600 | $9,075 | $9,374 | $8,600 | $8,600 | 2% |
| 203E20000 EMBANKMENT | 252 CY | $25.00 | $22.00 | $15.00 | $6.02 | $28.31 | 2% |
| 614E18030 MAINTAINING TRAFFIC, MISC.: RUMBLE STRIPES MILLED | 720 FT | $8.00 | $16.00 | $22.00 | $10.28 | $31.84 | 2% |
| 611E13200 30" CONDUIT, TYPE A, (706.02) | 20 FT | $275 | $240 | $135 | $211 | $407 | 2% |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.38 MILE | $11,800 | $13,450 | $12,861 | $11,800 | $11,800 | 2% |
| 203E35141 GRANULAR MATERIAL, TYPE E, AS PER PLAN | 78 CY | $53.00 | $88.00 | $46.50 | $108 | $90.38 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1-1/2" | 255 SY | $16.00 | $28.00 | $26.50 | $17.59 | $50.00 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,000 | $24,000 | $45,000 | $6,008 | $18,027 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $5,500 | $15,000 | $3,600 | $4,427 | 1% |
| 621E00100 RPM | 24 EACH | $165 | $225 | $140 | $165 | $82.66 | 1% |
| $4.00 |
| $4.00 |
| $8.80 |
| $4.60 |
| 204E50000 GEOTEXTILE FABRIC, TYPE B | 1,306 SY | $2.75 | $3.50 | $6.00 | $1.12 | $2.61 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 1 EACH | $2,500 | $2,494 | $2,718 | $2,494 | $2,494 |
| 601E12000 RIPRAP, WITH GROUT | 15 SY | $175 | $165 | $143 | $416 | $762 |
| 659E00300 TOPSOIL | 36 CY | $30.00 | $40.00 | $62.50 | $108 | $150 |
| 659E10000 SEEDING AND MULCHING | 323 SY | $8.00 | $7.80 | $6.50 | $8.32 | $6.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.05 TON | $610 | $610 | $1,635 | $1,500 | $1,500 |
| 659E31000 LIME | 0.07 ACRE | $86.71 | $80.00 | $218 | $200 | $200 |
| 659E35000 WATER | 5 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 0.56 CY | $7,000 | $2,500 | $2,275 | $11,173 | $4,037 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 200 FT | $8.00 | $12.00 | $10.50 | $15.19 | $28.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 13 FT | $25.00 | $12.00 | $13.50 | $56.96 | $150 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 209 FT | $5.00 | $5.00 | $3.50 | $3.00 | $1.89 |
| 304E20000 AGGREGATE BASE | 21 CY | $125 | $88.00 | $77.00 | $109 | $244 |
| 407E20000 NON-TRACKING TACK COAT | 33 GAL | $13.00 | $6.00 | $3.50 | $13.00 | $40.90 |
| 441E50201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (10 CY | $345 | $320 | $474 | $386 | $791 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 24 EACH | $5.00 | $20.00 | $9.50 | $43.01 | $20.87 |
| 626E00112 BARRIER REFLECTOR, TYPE 3, BIDIRECTIONAL | 4 EACH | $15.00 | $20.00 | $16.50 | $15.00 | $15.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.75 MILE | $1,300 | $2,550 | $1,417 | $8,600 | $1,300 |
| 642E00300 CENTER LINE, TYPE 1 | 0.38 MILE | $1,500 | $4,550 | $1,635 | $1,500 | $1,500 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $200 | $88.00 | $71.00 | $65.75 | $184 |
| 614E11630 INCREASED BARRIER DELINEATION | 220 FT | $2.75 | $3.00 | $3.00 | $2.75 | $5.13 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,950 | $2,000 | $2,126 | $2,400 | $3,658 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $250 | $180 | $211 | $326 | $1,300 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 6 EACH | $11.00 | $15.00 | $12.00 | $11.00 | $45.24 |
| 614E13360 OBJECT MARKER, TWO WAY | 6 EACH | $15.00 | $15.00 | $16.50 | $15.00 | $47.62 |
| 616E10000 WATER | 60 MGAL | $1.00 | $1.00 | $24.50 | $11.69 | $12.11 |
| 619E16000 FIELD OFFICE, TYPE A | 5 MNTH | $100 | $1,500 | $500 | $1,285 | $1,373 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 601E25001 DUMPED ROCK FILL, TYPE A, AS PER PLAN | 1,790 CY | $55 | $98k | 32% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $25k | 8% |
| 203E10000 EXCAVATION | 1,500 CY | $15.5 | $23k | 8% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $20k | 6% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 480 FT | $26 | $12k | 4% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1 | $10k | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 337.5 FT | $24.76 | $8k | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 20 CY | $410 | $8k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 19 CY | $410 | $8k | 3% |
| 618E40800 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 920 FT | $8 | $7k | 2% |