MOE-SR 78-24.46
MOE County · est $1.9M
Bid dateThursday, September 30—
MOE County · est $1.9M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 3.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 14 more items below.
| Item | Quantity | R1Buds INC | R2Alan Stone CO INC | R3Allison Park Contractors INC | % of bid |
|---|---|---|---|---|---|
| 862E99000 ROCKFALL PROTECTION, MISC.: ROCK BOLTS | 3,600 FT | $146 | $147 | $185 | 26% |
| 862E00601 SLOPE DRAPE, AS PER PLAN, PINNED | 3,113 SY | $133 | $141 | $175 | 20% |
| 862E00601 SLOPE DRAPE, AS PER PLAN | 2,298 SY | $123 | $119 | $135 | 14% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 2,775 SF | $65.00 | $81.50 | $50.00 | 9% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $138,000 | $75,000 | $50,000 | 7% |
| Item | Quantity | R1Buds INC | R2Alan Stone CO INC | R3Allison Park Contractors INC |
|---|---|---|---|---|
| 659E10000 SEEDING AND MULCHING | 446 SY | $4.00 | $6.00 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.2 TON | $700 | $649 | $1,000 |
| 659E31000 LIME | 0.4 ACRE | $200 | $830 | $125 |
| 659E35000 WATER | 10 MGAL | $1.00 | $118 | $5.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 |
| 407E20000 NON-TRACKING TACK COAT | 272 GAL |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 624E10000 MOBILIZATION | 1 LS | $110,000 | $85,000 | $75,000 | 5% |
| 862E00500 SCALING | 180 HOUR | $488 | $373 | $550 | 4% |
| 862E00700 TRIM BLASTING | 2,000 SF | $32.25 | $68.00 | $18.00 | 3% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $57,000 | $52,000 | $84,712 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 133 CY | $285 | $311 | $350 | 2% |
| 862E00610 EXCAVATION | 1,282 CY | $27.00 | $29.50 | $45.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,000 | $12,000 | $14,000 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $30,000 | $7,100 | $15,000 | 1% |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $18,000 | $4,200 | $7,000 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 650 FT | $22.00 | $25.50 | $65.00 | 1% |
| 671E15060 EROSION CONTROL MAT, TYPE G | 1,323 SY | $6.00 | $58.50 | $6.00 | 0% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,200 | $1,800 | $1,500 | 0% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,400 | $2,700 | $3,000 | 0% |
| 621E00100 RPM | 23 EACH | $161 | $158 | $215 | 0% |
| 617E10100 COMPACTED AGGREGATE | 17 CY | $180 | $150 | $275 | 0% |
| $3.60 |
| $3.50 |
| $10.00 |
| 408E10000 PRIME COAT | 160 GAL | $9.00 | $8.00 | $20.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 23 EACH | $20.00 | $24.50 | $100 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.34 MILE | $3,000 | $3,100 | $10,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.17 MILE | $5,000 | $5,400 | $10,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 13 EACH | $10.00 | $31.50 | $25.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 13 EACH | $15.00 | $38.50 | $30.00 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.15 MILE | $6,000 | $6,700 | $23,000 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 24 FT | $15.00 | $13.50 | $10.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 862E99000 ROCKFALL PROTECTION, MISC.: ROCK BOLTS | 3,600 FT | $146 | $526k | 25% |
| 862E00601 SLOPE DRAPE, AS PER PLAN, PINNED | 3,113 SY | $133.4 | $415k | 20% |
| 862E00601 SLOPE DRAPE, AS PER PLAN | 2,298 SY | $123 | $283k | 14% |
| 520E10001 PNEUMATICALLY PLACED CONCRETE SHOTCRETE, AS PER PL | 2,775 SF | $65 | $180k | 9% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $138,000 | $138k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $110,000 | $110k | 5% |
| 862E00500 SCALING | 180 HOUR | $488 | $88k | 4% |
| 862E00700 TRIM BLASTING | 2,000 SF | $32.25 | $65k | 3% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $57,000 | $57k | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 133 CY | $285 | $38k | 2% |