PIK-CR 50-03.32 OH16-01
PIK County · est $1.1M
Bid dateThursday, April 14—
PIK County · est $1.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 28 more items below.
| Item | Quantity | R1Allied Construction, LLC | R2Alan Stone CO INC | R3Allard Excavation LLC | R4Ohio-west Virginia Excavating CO | R5Shelly & Sands INC | R6Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W21X62 | 3,885 FT | $52.45 | $57.00 | $64.15 | $59.00 | $63.00 | $79.54 | 27% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 1,910 FT | $70.50 | $57.88 | $50.50 | $51.60 | $47.00 | $89.24 | 18% |
| 524E94605 DRILLED SHAFTS, 30" DIAMETER INTO BEDROCK, AS PER | 1,545 FT | $85.00 | $72.04 | $51.00 |
| Item | Quantity | R1Allied Construction, LLC | R2Alan Stone CO INC | R3Allard Excavation LLC | R4Ohio-west Virginia Excavating CO | R5Shelly & Sands INC | R6Sunesis Construction CO |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $40,339 | $8,705 | $15,000 | $46,200 | $17,351 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 28 FT | $25.00 | $29.86 | $8.80 | $35.00 | $7.00 | $12.22 |
| 202E35200 PIPE REMOVED, OVER 24" | 30 FT | $35.00 | $27.86 | $9.00 | $50.00 | $7.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $126 |
| $67.00 |
| $145 |
| 17% |
| 203E10000 EXCAVATION | 1,280 CY | $35.00 | $11.02 | $14.75 | $22.00 | $17.00 | $30.17 | 6% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE LAGGING 8" | 161 EACH | $210 | $477 | $352 | $325 | $550 | $484 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $23,783 | $64,650 | $40,000 | $20,000 | $88,017 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,550 | $25,481 | $28,650 | $15,500 | $45,000 | $34,730 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 750 FT | $29.00 | $21.00 | $20.00 | $35.00 | $20.00 | $32.16 | 3% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE LAGGING 8" | 100 EACH | $210 | $511 | $350 | $325 | $550 | $564 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 68 CY | $270 | $325 | $390 | $270 | $270 | $270 | 2% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE LAGGING 8" | 106 EACH | $146 | $410 | $419 | $260 | $450 | $462 | 2% |
| 623E40500 REFERENCE MONUMENT | 6 EACH | $2,500 | $401 | $360 | $500 | $1,000 | $639 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $6,047 | $11,000 | $11,000 | $6,500 | $7,824 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $7,225 | $10,000 | $3,000 | $13,000 | $9,100 | 1% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $9,965 | $500 | $61,034 | $1,000 | $60,000 | $84,355 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $9,785 | $8,423 | $6,995 | $8,000 | $7,000 | $10,598 | 1% |
| 518E62600 STRUCTURE DRAINAGE, MISC.: PREFABRICATED GEOCOMPOS | 4,215 SF | $2.03 | $3.00 | $2.65 | $3.50 | $1.75 | $2.65 | 1% |
| 253E02000 PAVEMENT REPAIR | 10 CY | $700 | $843 | $1,400 | $720 | $700 | $781 | 1% |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,700 | $5,419 | $5,000 | $7,000 | $6,200 | $8,256 | 1% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $1,833 | $500 | $1,200 | $1,500 | $3,400 | $1,452 | 1% |
| $13.64 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $1,000 | $154 | $87.30 | $1,300 | $100 | $257 |
| 203E20000 EMBANKMENT | 77 CY | $20.00 | $36.64 | $6.40 | $33.00 | $7.00 | $13.26 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 18 CY | $100 | $130 | $80.00 | $225 | $140 | $211 |
| 659E10000 SEEDING AND MULCHING | 2,156 SY | $1.65 | $3.31 | $2.12 | $1.65 | $1.60 | $3.65 |
| 659E14000 REPAIR SEEDING AND MULCHING | 108 SY | $1.65 | $1.20 | $0.05 | $1.65 | $0.80 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.29 TON | $800 | $1,806 | $1,200 | $800 | $870 | $1,500 |
| 659E31000 LIME | 0.45 ACRE | $80.00 | $241 | $500 | $80.00 | $153 | $200 |
| 659E35000 WATER | 12 MGAL | $1.00 | $0.01 | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1.6 CY | $100 | $1,888 | $7,304 | $2,600 | $2,500 | $3,505 |
| 611E52300 19" X 30" CONDUIT, TYPE A, 706.04 | 28 FT | $40.00 | $247 | $305 | $330 | $250 | $272 |
| 611E52500 24" X 38" CONDUIT, TYPE A, 706.04 | 36 FT | $40.00 | $270 | $321 | $365 | $275 | $307 |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 8 CY | $500 | $602 | $1,000 | $520 | $500 | $500 |
| 407E10000 TACK COAT | 123 GAL | $2.70 | $3.25 | $1.85 | $3.00 | $2.70 | $2.70 |
| 642E00300 CENTER LINE, TYPE 1 | 0.25 MILE | $6,200 | $5,419 | $4,500 | $4,500 | $4,500 | $7,600 |
| 611E04600 12" CONDUIT, TYPE C | 308 FT | $9.44 | $43.52 | $25.87 | $60.00 | $48.00 | $68.01 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $67.50 | $81.88 | $75.00 | $85.00 | $70.00 | $75.00 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,100 | $3,444 | $1,900 | $3,000 | $2,860 | $2,100 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 16 EACH | $17.00 | $43.35 | $12.25 | $36.00 | $5.00 | $17.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 16 EACH | $21.00 | $45.76 | $12.25 | $38.00 | $11.00 | $21.00 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.04 MILE | $8,600 | $30,766 | $25,550 | $25,550 | $25,550 | $8,600 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.12 MILE | $12,000 | $10,777 | $8,950 | $9,000 | $8,950 | $12,000 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 0.19 MILE | $8,600 | $6,322 | $5,250 | $5,300 | $5,250 | $8,600 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 22 FT | $4.00 | $16.86 | $14.00 | $15.00 | $14.00 | $4.00 |
| 616E10000 WATER | 4 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $40.00 | $12.96 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.: SOLDIER PILES W21X62 | 3,885 FT | $52.45 | $204k | 25% |
| 524E94603 DRILLED SHAFTS, 30" DIAMETER, ABOVE BEDROCK, AS PE | 1,910 FT | $70.5 | $135k | 17% |
| 524E94605 DRILLED SHAFTS, 30" DIAMETER INTO BEDROCK, AS PER | 1,545 FT | $85 | $131k | 16% |
| 203E10000 EXCAVATION | 1,280 CY | $35 | $45k | 6% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE LAGGING 8" | 161 EACH | $210 | $34k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,550 | $23k | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 750 FT | $29 | $22k | 3% |
| 530E00400 SPECIAL - STRUCTURES: PRECAST CONCRETE LAGGING 8" | 100 EACH | $210 | $21k | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 68 CY | $270 | $18k | 2% |