| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Alan Stone CO INC | R4Axis Civil Construction LLC | R5Wolf Creek Contracting Company LLC | R6Parker Corporation | R7Shelly & Sands INC | R8Ohio-west Virginia Excavating CO | R9R C Construction Company And Son | R10INC Kanawha Stone Company Incorporated | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 2,349 CY | $62.25 | $68.00 | $54.00 | $82.00 | $76.50 | $85.00 | $68.00 | $90.00 | $100 | $84.50 | 26% |
| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Alan Stone CO INC | R4Axis Civil Construction LLC | R5Wolf Creek Contracting Company LLC | R6Parker Corporation | R7Shelly & Sands INC | R8Ohio-west Virginia Excavating CO | R9R C Construction Company And Son | R10INC Kanawha Stone Company Incorporated |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,000 | $13,000 | $27,000 | $20,000 | $6,577 | $10,000 | $18,025 | $3,000 | $15,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 203E10000 EXCAVATION | 7,159 CY | $11.00 | $12.00 | $18.00 | $18.50 | $10.75 | $20.00 | $19.00 | $15.00 | $15.00 | $22.21 | 14% |
| 624E10000 MOBILIZATION | 1 LS | $47,000 | $20,000 | $20,000 | $25,000 | $60,477 | $12,000 | $20,000 | $60,000 | $15,000 | $45,523 | 8% |
| 203E20000 EMBANKMENT | 3,910 CY | $9.00 | $9.00 | $2.00 | $12.00 | $11.21 | $20.00 | $23.00 | $20.00 | $20.00 | $6.92 | 6% |
| 203E35121 GRANULAR MATERIAL, TYPE C, AS PER PLAN | 519 CY | $62.50 | $70.00 | $76.50 | $95.00 | $95.51 | $85.00 | $78.00 | $135 | $100 | $82.89 | 6% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 82 CY | $390 | $390 | $325 | $310 | $449 | $388 | $390 | $280 | $380 | $414 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,000 | $24,000 | $33,000 | $24,000 | $15,468 | $17,000 | $27,700 | $50,000 | $30,000 | $35,635 | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 59 CY | $430 | $380 | $300 | $280 | $243 | $365 | $430 | $250 | $370 | $457 | 5% |
| 203E35001 GRANULAR EMBANKMENT, AS PER PLAN | 296 CY | $83.00 | $100 | $71.50 | $100 | $78.43 | $85.00 | $58.00 | $145 | $100 | $93.87 | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 336 SY | $68.60 | $85.00 | $60.00 | $85.00 | $78.42 | $85.00 | $90.00 | $85.00 | $140 | $80.00 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,204 | $20,000 | $10,000 | $7,300 | $7,500 | $9,500 | $5,200 | $15,000 | $20,000 | $5,240 | 3% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 760 FT | $21.80 | $18.00 | $21.00 | $25.00 | $33.93 | $10.00 | $18.00 | $27.00 | $25.00 | $33.99 | 3% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,900 | $2,000 | $3,000 | $1,800 | $2,530 | $1,500 | $2,500 | $2,600 | $2,500 | $3,027 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $7,200 | $5,000 | $12,500 | $10,000 | $9,200 | $10,000 | $18,500 | $6,500 | $15,000 | $75,148 | 1% |
| 602E20000 CONCRETE MASONRY | 0.92 CY | $7,506 | $1,700 | $4,800 | $2,200 | $2,264 | $1,500 | $4,000 | $2,500 | $2,900 | $3,305 | 1% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 47 CY | $144 | $80.00 | $229 | $130 | $111 | $130 | $120 | $150 | $200 | $208 | 1% |
| 601E34400 ROCK CHANNEL PROTECTION, WITH GROUT, TYPE C | 38 CY | $166 | $130 | $223 | $170 | $164 | $200 | $180 | $100 | $250 | $235 | 1% |
| 659E10000 SEEDING AND MULCHING | 4,710 SY | $1.30 | $1.25 | $1.75 | $1.10 | $1.27 | $1.00 | $2.25 | $1.00 | $3.00 | $1.17 | 1% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 304E20000 AGGREGATE BASE | 61 CY | $75.00 | $100 | $83.50 | $110 | $131 | $85.00 | $110 | $125 | $85.00 | $169 | 1% |
| $30,978 |
| 202E20010 HEADWALL REMOVED | 1 EACH | $130 | $300 | $1,200 | $500 | $171 | $500 | $100 | $295 | $1,000 | $197 |
| 202E23000 PAVEMENT REMOVED | 337 SY | $10.25 | $10.00 | $28.50 | $25.00 | $12.38 | $5.00 | $20.00 | $34.00 | $25.00 | $22.96 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 42 FT | $6.25 | $20.00 | $13.50 | $40.00 | $8.16 | $10.00 | $8.00 | $13.00 | $30.00 | $85.06 |
| 204E10000 SUBGRADE COMPACTION | 383 SY | $2.75 | $7.00 | $3.00 | $5.00 | $2.22 | $0.50 | $7.00 | $5.00 | $3.00 | $7.12 |
| 690E12010 SPECIAL - GEOTEXTILE FABRIC,712.09, TYPE A | 761 SY | $2.00 | $2.50 | $2.50 | $3.00 | $3.08 | $2.50 | $2.00 | $3.00 | $8.00 | $2.76 |
| 659E20000 COMMERCIAL FERTILIZER | 0.5 TON | $800 | $1,000 | $1,500 | $1,400 | $1,610 | $2,000 | $1,000 | $650 | $1,200 | $1,487 |
| 659E31000 LIME | 1 ACRE | $800 | $80.00 | $200 | $80.00 | $92.00 | $1,000 | $100 | $80.00 | $800 | $84.97 |
| 659E35000 WATER | 25 MGAL | $8.00 | $1.00 | $0.01 | $1.00 | $1.15 | $0.05 | $1.00 | $10.00 | $1.00 | $1.06 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $2,750 | $4,000 | $100 | $5,000 | $4,056 | $10,000 | $250 | $15,000 | $10,000 | $5,879 |
| 605E31100 AGGREGATE DRAINS | 100 FT | $9.00 | $25.00 | $16.50 | $18.00 | $11.11 | $15.00 | $20.00 | $40.00 | $10.00 | $22.56 |
| 611E01400 6" CONDUIT, TYPE E,707.31 (PERFORATED) | 599 FT | $4.50 | $12.00 | $5.00 | $16.00 | $4.79 | $20.00 | $4.00 | $10.00 | $15.00 | $8.69 |
| 611E01500 6" CONDUIT, TYPE F,707.33 (NON-PERFORATED) | 168 FT | $6.00 | $17.50 | $33.50 | $16.00 | $8.69 | $20.00 | $22.00 | $20.00 | $15.00 | $16.29 |
| 611E10200 24" CONDUIT, TYPE A | 60 FT | $59.00 | $110 | $184 | $16.00 | $66.39 | $135 | $225 | $88.00 | $195 | $344 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $195 | $275 | $310 | $500 | $217 | $200 | $500 | $500 | $250 | $554 |
| 407E20000 NON-TRACKING TACK COAT | 135 GAL | $4.00 | $18.00 | $10.00 | $5.00 | $4.60 | $18.00 | $4.00 | $4.00 | $10.00 | $4.25 |
| 408E10000 PRIME COAT | 124 GAL | $3.75 | $20.00 | $15.00 | $7.00 | $431 | $5.00 | $3.75 | $10.00 | $20.00 | $3.98 |
| 617E10100 COMPACTED AGGREGATE | 26 CY | $69.00 | $135 | $124 | $125 | $150 | $85.00 | $125 | $120 | $85.00 | $154 |
| 621E00100 RPM | 9 EACH | $315 | $315 | $315 | $315 | $362 | $315 | $315 | $320 | $350 | $335 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 9 EACH | $4.00 | $1.00 | $10.50 | $20.00 | $7.92 | $20.00 | $20.00 | $80.00 | $50.00 | $58.57 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.26 MILE | $3,255 | $3,500 | $3,255 | $3,255 | $3,743 | $3,255 | $3,255 | $3,300 | $3,000 | $3,457 |
| 642E00300 CENTER LINE, TYPE 1 | 0.13 MILE | $5,880 | $6,000 | $5,880 | $5,880 | $6,762 | $5,880 | $5,880 | $5,900 | $6,000 | $6,245 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $2,500 | $2,000 | $4,500 | $500 | $11,013 | $200 | $25,000 | $2,500 | $12,000 | $28,977 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 16 EACH | $11.50 | $20.00 | $32.00 | $16.00 | $18.40 | $10.00 | $8.00 | $35.00 | $25.00 | $12.75 |
| 614E13360 OBJECT MARKER, TWO WAY | 16 EACH | $11.50 | $25.00 | $36.00 | $20.00 | $24.15 | $10.00 | $12.00 | $40.00 | $25.00 | $15.93 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.34 MILE | $3,450 | $5,000 | $3,450 | $3,450 | $12,770 | $2,500 | $3,450 | $3,500 | $9,500 | $3,664 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 24 FT | $14.00 | $15.00 | $12.00 | $12.00 | $25.40 | $10.00 | $12.00 | $15.00 | $50.00 | $12.74 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,900 | $2,000 | $10,000 | $5,000 | $5,000 | $5,000 | $27,000 | $2,000 | $15,000 | $6,914 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 601E27001 DUMPED ROCK FILL, TYPE C, AS PER PLAN | 2,349 CY | $62.25 | $146k | 25% |
| 203E10000 EXCAVATION | 7,159 CY | $11 | $79k | 13% |
| 624E10000 MOBILIZATION | 1 LS | $47,000 | $47k | 8% |
| 203E20000 EMBANKMENT | 3,910 CY | $9 | $35k | 6% |
| 203E35121 GRANULAR MATERIAL, TYPE C, AS PER PLAN | 519 CY | $62.5 | $32k | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 82 CY | $390 | $32k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,000 | $29k | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 59 CY | $430 | $25k | 4% |
| 203E35001 GRANULAR EMBANKMENT, AS PER PLAN | 296 CY | $83 | $25k | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 336 SY | $68.6 | $23k | 4% |