| Item | Quantity | R1D G M INC | R2Scioto Valley Paving LLC | R3Heavy Highway Construction Company | R4LLC R C Construction Company And Son INC | R5Alan Stone CO INC | R6Axis Civil Construction LLC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 611E07201 18" CONDUIT, TYPE A, AS PER PLAN ,707.33 | 3,118 FT | $77.00 | $65.00 | $58.00 | $120 | $55.00 | $97.50 | 36% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 133 CY | $1,300 | $1,600 | $1,500 | $400 | $3,300 | $2,950 | 26% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 3,273 FT | $15.00 | $12.00 | $12.00 |
| Item | Quantity | R1D G M INC | R2Scioto Valley Paving LLC | R3Heavy Highway Construction Company | R4LLC R C Construction Company And Son INC | R5Alan Stone CO INC | R6Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|
| 202E35200 PIPE REMOVED, OVER 24" | 42 FT | $50.00 | $40.00 | $15.00 | $100 | $84.00 | $55.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 342 SY | $0.05 | $4.00 | $1.30 | $0.20 | $4.00 | $1.30 |
| 659E20000 COMMERCIAL FERTILIZER | 0.46 TON | $1,000 | $1,000 | $1,400 | $1,200 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $10.00 |
| $13.50 |
| $45.00 |
| 7% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 353.4 CY | $85.00 | $150 | $100 | $85.00 | $113 | $175 | 5% |
| 202E20010 HEADWALL REMOVED | 114 EACH | $200 | $80.00 | $200 | $250 | $118 | $400 | 3% |
| 304E20000 AGGREGATE BASE | 185 CY | $100 | $125 | $80.00 | $85.00 | $83.00 | $130 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $16,000 | $15,000 | $10,000 | $15,000 | $13,000 | $20,000 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $16,000 | $4,500 | $25,000 | $25,000 | $41,000 | $30,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $15,000 | $80,000 | $22,000 | $5,000 | $15,000 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $12,500 | $25,000 | $20,000 | $25,000 | $17,000 | $40,000 | 2% |
| 611E10201 24" CONDUIT, TYPE A, AS PER PLAN ,707.33 | 120 FT | $90.00 | $95.00 | $65.00 | $150 | $76.00 | $140 | 2% |
| 611E20701 48" CONDUIT, TYPE A, AS PER PLAN, 707.33 | 42 FT | $250 | $200 | $175 | $500 | $169 | $450 | 2% |
| 620E00500 DELINEATOR, POST GROUND MOUNTED ,TYPE C | 114 EACH | $90.00 | $50.00 | $100 | $150 | $130 | $100 | 2% |
| 832E30000 EROSION CONTROL | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 659E10000 SEEDING AND MULCHING | 3,420 SY | $2.00 | $4.00 | $1.30 | $10.00 | $5.00 | $1.30 | 1% |
| 204E10000 SUBGRADE COMPACTION | 669 SY | $10.00 | $5.00 | $1.50 | $2.00 | $2.00 | $50.00 | 1% |
| 503E21104 UNCLASSIFIED EXCAVATION, INCLUDING ROCK | 181 CY | $35.00 | $150 | $100 | $100 | $24.00 | $95.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $8,500 | $10,000 | $15,000 | $7,800 | $40,000 | 1% |
| 611E08701 21" CONDUIT, TYPE A, AS PER PLAN ,707.33 | 35 FT | $90.00 | $150 | $65.00 | $125 | $75.50 | $110 | 0% |
| 203E35000 GRANULAR EMBANKMENT | 112 CY | $25.00 | $135 | $100 | $85.00 | $9.50 | $208 | 0% |
| $651 |
| $1,400 |
| 659E31000 LIME | 0.71 ACRE | $100 | $1,000 | $80.00 | $800 | $916 | $80.00 |
| 659E35000 WATER | 18.47 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $0.10 | $1.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E07201 18" CONDUIT, TYPE A, AS PER PLAN ,707.33 | 3,118 FT | $77 | $240k | 36% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 133 CY | $1,300 | $173k | 26% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 3,273 FT | $15 | $49k | 7% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 353.4 CY | $85 | $30k | 5% |
| 202E20010 HEADWALL REMOVED | 114 EACH | $200 | $23k | 3% |
| 304E20000 AGGREGATE BASE | 185 CY | $100 | $19k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $16,000 | $16k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $16,000 | $16k | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $15k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $12,500 | $13k | 2% |