BRO-SR 123-00.00 PV
BRO County · est $0.7M
Bid dateThursday, August 25—
BRO County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 2 more items below.
| Item | Quantity | R1Brown County Asphalt INC | R2Shelly Company | R3John R Jurgensen Company | % of bid |
|---|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 2,037 CY | $186 | $187 | $208 | 61% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 48,896 SY | $0.75 | $1.38 | $2.09 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $45,500 | $38,307 | 5% |
| 644E00104 EDGE LINE, 6" | 6.88 MILE | $4,151 | $4,151 | $4,151 | 5% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 500 SY | $40.00 | $44.50 | $84.34 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $20,000 | 3% |
| 254E01600 PATCHING PLANED SURFACE |
| Item | Quantity | R1Brown County Asphalt INC | R2Shelly Company | R3John R Jurgensen Company |
|---|---|---|---|---|
| 644E00500 STOP LINE | 52 FT | $9.29 | $9.29 | $9.29 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 104 FT | $2.25 | $2.25 | $2.25 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 9,779 SY |
| $2.00 |
| $2.25 |
| $2.35 |
| 3% |
| 407E20000 NON-TRACKING TACK COAT | 4,156 GAL | $3.00 | $3.50 | $5.00 | 2% |
| 644E00300 CENTER LINE | 3.44 MILE | $3,296 | $3,296 | $3,296 | 2% |
| 617E10100 COMPACTED AGGREGATE | 150 CY | $75.00 | $93.50 | $48.76 | 2% |
| 621E00100 RPM | 280 EACH | $37.50 | $37.50 | $37.50 | 2% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 13.76 MILE | $658 | $658 | $658 | 1% |
| 632E26500 DETECTOR LOOP | 2 EACH | $3,405 | $4,200 | $2,750 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 6.88 MILE | $950 | $950 | $950 | 1% |
| 512E10400 TREATING OF CONCRETE BRIDGE DECK WITH SRS | 465 SY | $12.50 | $12.50 | $12.50 | 1% |
| 618E39000 RUMBLE STRIPS, TRANSVERSE (ASPHALT CONCRETE) | 3 EACH | $1,050 | $1,050 | $1,050 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,525 | $3,500 | $4,164 | 0% |
| 512E10300 SEALING CONCRETE BRIDGE DECKS WITH HMWM RESIN | 50 SY | $40.00 | $40.00 | $40.00 | 0% |
| 614E12460 WORK ZONE MARKING SIGN | 8 EACH | $100 | $125 | $115 | 0% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 280 EACH | $2.50 | $23.00 | $23.81 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 2,037 CY | $186 | $379k | 61% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 48,896 SY | $0.75 | $37k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 5% |
| 644E00104 EDGE LINE, 6" | 6.88 MILE | $4,151 | $29k | 5% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 500 SY | $40 | $20k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 3% |
| 254E01600 PATCHING PLANED SURFACE | 9,779 SY | $2 | $20k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 4,156 GAL | $3 | $12k | 2% |
| 644E00300 CENTER LINE | 3.44 MILE | $3,296 | $11k | 2% |
| 617E10100 COMPACTED AGGREGATE | 150 CY | $75 | $11k | 2% |