ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 17 more items below.
| Item | Quantity | R1Double Z Construction Company | R2Shelly & Sands INC | R3Complete General Construction Company | % of bid |
|---|---|---|---|---|---|
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 644 SY | $130 | $125 | $130 | 21% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 644 SY | $94.00 | $125 | $167 | 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,000 | $8,000 | $105,000 | 10% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $23,500 | $20,000 | 7% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 620 FT | $40.00 | $22.00 | $23.00 | 6% |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 276 FT | $80.00 | $128 | $95.00 | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 37 CY | $500 |
| Item | Quantity | R1Double Z Construction Company | R2Shelly & Sands INC | R3Complete General Construction Company |
|---|---|---|---|---|
| 202E38000 GUARDRAIL REMOVED | 225 FT | $2.50 | $32.00 | $2.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 |
| 407E20000 NON-TRACKING TACK COAT | 80 GAL | $3.50 | $3.30 | $3.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $15.00 | $28.00 | $65.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.23 MILE | $3,950 | $4,200 | $3,950 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $600 |
| $479 |
| 5% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 133 SY | $120 | $150 | $125 | 4% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 21 CF | $750 | $850 | $800 | 4% |
| 606E35120 BRIDGE TERMINAL ASSEMBLY, TYPE 3 | 4 EACH | $3,850 | $4,900 | $3,240 | 4% |
| 848E30100 LATEX MODIFIED CONCRETE OVERLAY (VARIABLE THICKNES | 19 CY | $725 | $725 | $725 | 3% |
| 848E50000 HAND CHIPPING | 97 SY | $110 | $55.00 | $88.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" DEPTH) | 891 SY | $11.00 | $15.00 | $10.25 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $9,100 | $7,500 | $35,000 | 2% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,000 | $2,250 | $2,260 | 2% |
| 848E50200 FULL-DEPTH REPAIR | 20 CY | $350 | $600 | $725 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 225 FT | $25.00 | $53.00 | $23.60 | 1% |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,300 | $5,000 | $5,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $2,500 | $5,000 | 1% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 350 SY | $9.91 | $10.00 | $10.00 | 1% |
| 642E00300 CENTER LINE, TYPE 1 | 0.14 MILE | $6,100 | $6,500 | $6,100 |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 80 FT | $6.00 | $6.00 | $6.00 |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 124 FT | $6.00 | $6.00 | $6.00 |
| 642E00900 ISLAND MARKING, TYPE 1 | 48 SF | $10.00 | $10.00 | $10.00 |
| 642E01300 LANE ARROW, TYPE 1 | 1 EACH | $400 | $428 | $400 |
| 614E12740 WORK ZONE LIGHTING SYSTEM | 1 EACH | $2,000 | $30,000 | $2,500 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, (BIDIRECTIONAL) | 28 EACH | $10.00 | $10.00 | $26.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 28 EACH | $15.00 | $13.00 | $36.00 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.34 MILE | $6,150 | $6,500 | $6,150 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 50 FT | $12.00 | $13.00 | $12.00 |
| 509E20001 CONCRETE REINFORCEMENT, REPLACEMENT OF EXISTING CO | 50 LB | $1.00 | $2.00 | $7.00 |
| 848E50100 TEST SLAB | 1 LS | $1,600 | $2,500 | $3,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 848E10100 LATEX MODIFIED CONCRETE OVERLAY USING HYDRODEMOLIT | 644 SY | $130 | $84k | 20% |
| 848E20000 SURFACE PREPARATION USING HYDRODEMOLITION | 644 SY | $94 | $61k | 14% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $40,000 | $40k | 10% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 7% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 620 FT | $40 | $25k | 6% |
| 517E72750 RAILING (THRIE BEAM RETROFIT) | 276 FT | $80 | $22k | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 37 CY | $500 | $19k | 4% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 133 SY | $120 | $16k | 4% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 21 CF | $750 | $16k | 4% |
| 606E35120 BRIDGE TERMINAL ASSEMBLY, TYPE 3 | 4 EACH | $3,850 | $15k | 4% |