TUS-IR 77-(0.06)(5.89)
TUS County · est $0.9M
Bid dateThursday, December 15—
TUS County · est $0.9M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 19 more items below.
| Item | Quantity | R1Stanley Miller Construction Company | R2Inliner Solutions | R3Black Horse Bridge Construction INC | % of bid |
|---|---|---|---|---|---|
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 525 FT | $455 | $625 | $650 | 19% |
| 624E10000 MOBILIZATION | 1 LS | $217,500 | $65,000 | $100,000 | 17% |
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 378 FT | $566 | $825 | $850 | 17% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $145,000 | $160,000 | $48,000 | 11% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 889 FT | $56.00 | $36.00 | $90.00 | 4% |
| 611E23600 60" CONDUIT, TYPE A, 707.02 (0.249), 707.03 (0.249 | 14 FT | $3,460 | $1,925 | $800 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS |
| Item | Quantity | R1Stanley Miller Construction Company | R2Inliner Solutions | R3Black Horse Bridge Construction INC |
|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $2,161 | $4,000 | $3,600 |
| 202E35200 PIPE REMOVED, OVER 24" | 14 FT | $146 | $18.00 | $220 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $580 | $300 |
| 659E00300 TOPSOIL | 586 CY | $20.00 | $120 | $38.00 |
| 659E10000 SEEDING AND MULCHING | 5,278 SY | $1.00 | $3.50 | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $45,000 |
| $15,000 |
| $7,000 |
| 4% |
| 601E11000 RIPRAP, TYPE D | 29 SY | $1,500 | $365 | $400 | 3% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 150 CY | $250 | $185 | $200 | 3% |
| 203E20000 EMBANKMENT | 291 CY | $127 | $65.00 | $40.00 | 3% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (A) | 1 LS | $35,000 | $12,000 | $95,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $22,500 | $58,000 | 2% |
| 203E10000 EXCAVATION | 124 CY | $197 | $75.00 | $18.00 | 2% |
| 832E30000 EROSION CONTROL | 20,000 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 602E20000 CONCRETE MASONRY | 13.4 CY | $1,417 | $2,200 | $2,650 | 1% |
| 503E21100 UNCLASSIFIED EXCAVATION | 121 CY | $146 | $95.00 | $40.00 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 620 FT | $25.00 | $100 | $28.00 | 1% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 63 CY | $225 | $185 | $140 | 1% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN (B) | 1 LS | $13,889 | $12,000 | $75,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,000 | $21,000 | $15,000 | 1% |
| 264 SY |
| $1.00 |
| $1.25 |
| $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.71 TON | $800 | $1,175 | $1,200 |
| 659E31000 LIME | 1.09 ACRE | $150 | $58.00 | $100 |
| 659E35000 WATER | 29 MGAL | $1.00 | $2.00 | $1.00 |
| 605E13402 6" UNCLASSIFIED PIPE UNDERDRAINS FOR SPRINGS | 30 FT | $10.00 | $55.00 | $36.00 |
| 605E32200 AGGREGATE DRAINS FOR SPRINGS | 30 FT | $10.00 | $42.00 | $30.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 3 EACH | $500 | $675 | $650 |
| 614E12200 SPECIAL - WORK ZONE GUARDRAIL | 50 FT | $100 | $70.00 | $80.00 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $4,500 | $4,000 | $2,640 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $100 | $1,500 | $60.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 16 EACH | $25.00 | $48.00 | $32.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 16 EACH | $25.00 | $55.00 | $38.00 |
| 616E10000 WATER | 100 MGAL | $1.00 | $2.00 | $1.00 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $300 | $2,200 | $1,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 525 FT | $455 | $239k | 18% |
| 624E10000 MOBILIZATION | 1 LS | $217,500 | $218k | 16% |
| 833E10000 CONDUIT RENEWAL USING SPRAY APPLIED STRUCTURAL LIN | 378 FT | $566 | $214k | 16% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $145,000 | $145k | 11% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 889 FT | $56 | $50k | 4% |
| 611E23600 60" CONDUIT, TYPE A, 707.02 (0.249), 707.03 (0.249 | 14 FT | $3,460 | $48k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $45,000 | $45k | 3% |
| 601E11000 RIPRAP, TYPE D | 29 SY | $1,500 | $44k | 3% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 150 CY | $250 | $38k | 3% |
| 203E20000 EMBANKMENT | 291 CY | $127 | $37k | 3% |