PUT-SR 65-10.73
PUT County · est $0.6M
Bid dateThursday, November 3—
PUT County · est $0.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 49 more items below.
| Item | Quantity | R1Vernon Nagel INC | R2Eclipse CO LLC | % of bid |
|---|---|---|---|---|
| 611E94940 9' X 6' CONDUIT, TYPE A, 706.05, DESIGN EARTH COVE | 100 FT | $1,600 | $1,203 | 36% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 45 CY | $800 | $966 | 8% |
| 511E46011 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 21 CY | $1,400 | $2,325 | 7% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 63 CY | $350 | $450 | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 77 CY | $275 | $330 | 5% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $20,000 | $13,427 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $44,200 | 5% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 143 CY | $130 | $175 | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 5,606 LB | $2.50 | $6.00 | 3% |
| 203E10000 EXCAVATION | 873 CY | $14.00 | $25.00 | 3% |
| 659E00300 TOPSOIL | 403 CY | $25.00 | $65.00 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $10,000 | $33,414 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $11,000 | 2% |
| 304E20000 AGGREGATE BASE | 161 CY | $60.00 | $82.00 | 2% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 103 CY | $90.00 | $117 | 2% |
| 253E02000 PAVEMENT REPAIR | 20 CY | $425 | $501 | 2% |
| 203E20000 EMBANKMENT | 437 CY | $18.00 | $22.00 | 2% |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $7,000 | $5,797 | 2% |
| 512E33000 TYPE 2 WATERPROOFING | 303 SY | $22.00 | $24.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 449 SY | $14.00 | $8.00 | 1% |
| Item | Quantity | R1Vernon Nagel INC | R2Eclipse CO LLC |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $3,160 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 80 FT | $5.00 | $23.00 |
| 202E38000 GUARDRAIL REMOVED | 638 FT | $2.00 | $2.00 |
| 202E42001 ANCHOR ASSEMBLY REMOVED, TYPE A, AS PER PLAN | 4 EACH | $325 | $343 |
| 204E10000 SUBGRADE COMPACTION | 499 SY | $1.00 | $1.00 |
| 209E72000 PREPARING SUBGRADE FOR SHOULDER PAVING | 4 STA | $100 | $1,866 |
| 606E15051 GUARDRAIL, TYPE MGS, AS PER PLAN | 200 FT | $24.20 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $26.00 |
| 606E15101 GUARDRAIL, TYPE MGS WITH LONG POSTS, AS PER PLAN | 187.5 FT | $27.40 | $30.00 |
| 606E17360 GUARDRAIL, TYPE MGS, LONG-SPAN | 43.75 FT | $22.00 | $27.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $2,860 | $3,104 |
| 659E10000 SEEDING AND MULCHING | 2,818 SY | $1.50 | $3.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.4 TON | $800 | $448 |
| 659E31000 LIME | 0.8 ACRE | $35.00 | $26.00 |
| 659E35000 WATER | 20 MGAL | $1.00 | $1.00 |
| 660E20000 SODDING REINFORCED | 806 SY | $7.25 | $13.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $675 | $711 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $1,750 | $1,845 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $3,000 | $3,821 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 95 FT | $20.00 | $14.00 |
| 611E01100 6" CONDUIT, TYPE C | 34 FT | $25.00 | $53.00 |
| 611E02500 8" CONDUIT, TYPE E | 20 FT | $20.00 | $44.00 |
| 611E03100 10" CONDUIT, TYPE B | 30 FT | $20.00 | $55.00 |
| 611E07600 18" CONDUIT, TYPE C | 65 FT | $70.00 | $115 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $3,000 | $4,625 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, T=1.5" | 593 SY | $10.00 | $7.00 |
| 407E20000 NON-TRACKING TACK COAT | 100 GAL | $1.00 | $3.00 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 2 EACH | $85.00 | $90.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $15.00 | $9.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BI-DIRECTIONAL | 6 EACH | $9.00 | $12.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 28.6 FT | $15.00 | $30.00 |
| 630E08600 SIGN POST REFLECTOR | 2 EACH | $50.00 | $53.00 |
| 630E80100 SIGN, FLAT SHEET | 7.1 SF | $30.00 | $55.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 1 EACH | $25.00 | $16.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $25.00 | $63.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $25.00 | $21.00 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 1 EACH | $100 | $153 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.25 MILE | $5,000 | $6,851 |
| 642E00300 CENTER LINE, TYPE 1 | 0.12 MILE | $10,000 | $6,851 |
| 407E10000 TACK COAT | 20 GAL | $1.00 | $3.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 10 CY | $400 | $474 |
| 616E10000 WATER | 1 MGAL | $10.00 | $66.00 |
| 617E10100 COMPACTED AGGREGATE | 50 CY | $75.00 | $84.00 |
| 512E10000 SEALING OF CONCRETE SURFACES | 78 SY | $35.00 | $28.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 34 SF | $12.00 | $9.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 13 CY | $90.00 | $2,081 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,750 | $12,503 |
| 619E16010 FIELD OFFICE, TYPE B | 2 MNTH | $800 | $685 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $8,131 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E94940 9' X 6' CONDUIT, TYPE A, 706.05, DESIGN EARTH COVE | 100 FT | $1,600 | $160k | 31% |
| 511E46511 CLASS QC1 CONCRETE, FOOTING, AS PER PLAN | 45 CY | $800 | $36k | 7% |
| 511E46011 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 21 CY | $1,400 | $29k | 6% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 63 CY | $350 | $22k | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 77 CY | $275 | $21k | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $20,000 | $20k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 4% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 143 CY | $130 | $19k | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 5,606 LB | $2.5 | $14k | 3% |
| 203E10000 EXCAVATION | 873 CY | $14 | $12k | 2% |